A Kabwe based Civil Engineering firm has to bid for the construction of the dam in Chibombo area. The activities and their time estimates are given below: Activity Optimistic Most Likely Pessimistic 1-2 14 17 25 2-3 14 18 21 2-4 13 15 18 2-8 16 19 28 3-5 15 18 27 4-6 13 17 21 5-9 14 18 20 7-9 16 20 41 8-9 14 16 22 The policy of the firm with respect to submitting bids is to bid the minimum amount that will provide a 95% of the probability at best break-even. The fixed costs for the project are K800, 000 and the variable costs are K9, 000 per day spent working on the project. What amount should the firm bid under this policy?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A Kabwe based Civil Engineering firm has to bid for the
construction of the dam in Chibombo area. The activities and
their time estimates are given below:
Activity Optimistic Most Likely Pessimistic
1-2
14
17
25
2 -3
14
18
21
2-4
13
15
18
2-8
16
19
28
3-5
15
18
27
4 -6
13
17
21
5-9
14
18
20
7-9
16
20
41
8-9
14
16
22
The policy of the firm with respect to submitting bids is to bid
the minimum amount that will provide a 95% of the
probability at best break-even. The fixed costs for the project
are K800, 000 and the variable costs are K9, 000 per day
spent working on the project. What amount should the firm
bid under this policy?
Transcribed Image Text:A Kabwe based Civil Engineering firm has to bid for the construction of the dam in Chibombo area. The activities and their time estimates are given below: Activity Optimistic Most Likely Pessimistic 1-2 14 17 25 2 -3 14 18 21 2-4 13 15 18 2-8 16 19 28 3-5 15 18 27 4 -6 13 17 21 5-9 14 18 20 7-9 16 20 41 8-9 14 16 22 The policy of the firm with respect to submitting bids is to bid the minimum amount that will provide a 95% of the probability at best break-even. The fixed costs for the project are K800, 000 and the variable costs are K9, 000 per day spent working on the project. What amount should the firm bid under this policy?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Storm sewers and detention
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning