A logistics company applies the EOQ model to manage its inventory of spare parts used for maintenance work for their trucks. Daily demand is normally distributed. The average daily demand is 10 units, with a standard deviation of 5 units. The EOQ is found to be 400 units and used as the order size for all orders. Order lead time is 4 days. Currently, the firm has just received an order. In how many days do they need to place the next order? 4 days 36 days 40 days None of the above. Demand is random, so the time until they reach the ROP again is also random
Q: Describe any two (2) limitations that may exist on the freedom of the contracting parties to choose…
A: There are three criteria or requisites of a legal contract, according to Section 10 of the Indian…
Q: to handle your company's project in delivering the quality project construction safely and within…
A: Your total cost performance and ability to achieve project deadlines will determine whether or not…
Q: A time study was made of an existing job to develop new time standards. A worker was observed for 45…
A: The detailed solution is given in Step 2.
Q: Identify three (3) supply chain risks and briefly explain what mitigation tactics you would use to…
A: A supply chain is a network of distributing the products and services from the producers/suppliers…
Q: Give me example of Formally Solicited project proposal in real-life situation.
A: A formally solicited project proposal is prepared in response to an official request for a new…
Q: 5. Given MC = Dtc/dQ = 42+18Q -12Q , given total fixed cost is 56 Find the total cost , average…
A: given, MC =Dtc/dQ = 42+18Q-12Q fixed cost =56
Q: Respond to the following statement: "The importance of location is frequently greatly exaggerated;…
A: Instead than making locational decisions alone, firms make them as part of larger considerations…
Q: Question 2 Control resources is important to lead more effective site management and to keep Master…
A: Control Resources is controlling and observing the use of physical resources on a project. It is the…
Q: ommunicate their ethical principles in a variety of ways: through the behaviour of their leaders, in…
A: Here considering the "Health care organization" for communication of their ethical principles…
Q: 6000 units of a part are needed every year. Currently, this part is manufactured internally. Each…
A:
Q: A company wants to produce hardware at a level rate and send 10 units to inventory. If their 6-month…
A: Forecasted demand = 110 units Inventory = 10 units Forecast months = 6
Q: 8.20 The following table gives the map coordinates and the shipping loads for a set of cities that…
A: Given data
Q: The entrepreneur explore opportunities. Discuss
A: In the entrepreneurial process, opportunity exploitation is a vital phase in developing a successful…
Q: Which of the following statements about requested changes is true? a. They are processed for review…
A: Change request are the request by an individual,employee or any of the person who has requested to…
Q: Assume that you buy a 1-year, 210,000-peso Philippine bond that pays 7 percent when the exchange…
A: The detailed solution is given in Step 2.
Q: The production manager at Zam Tech has developed following aggregate forecast of its products: The…
A: For a level plan the production level is kept constant. Here, since the cost of reuglar production…
Q: In the Melitz (2003) model, trade leads to
A: Explanation : Extension of the Krugman (1980) model, enterprises are miscellaneous in terms of…
Q: 2.1 Discuss human resources planning and be able to create a human resource plan, project…
A: as first question is incomplete and requires follwing questions to be answered as follows: we are…
Q: for four factors that your organisation should assess before to (or during) computer hardware…
A: Computers, software, and service procurement The policy aims to outline a method for new and…
Q: Describe the risks for a service process and for automation of production process
A: To be determined: The risks for a service process and for automation of production process.…
Q: As a project manager of construction industry, (a) Describe THREE (3) typical issues, with ONE (1)…
A: Project Success is known to those projects that have met all the business requirements. A…
Q: anchez Trucking has been experiencing delays at its warehouse operations Management hired a…
A: Given data: Requirement (Man hours) 960 1200 1440 1680 Probability 0.2 0.2 0.5 0.1 Number of…
Q: Question 10 Pulling this together.using the same data as the last few problems.A new logistics…
A: Kindly find the solution to question 10 in Step 2. THANKS!
Q: Do you think it's vital to split projects down into doable tasks? How does this breakdown work?
A: When the management in an organization splits projects into different tasks, then it is breaking…
Q: on should be taken in th
A: The use of Stock receipts helps you keep track of vendor work. Product amount, delivery time, and…
Q: Foxconn has a network of factories across the Chinese mainland, employing 1.2 million\speople, that…
A: Autonomy is an umbrella term for a wide range of technologies ranging from mechanical to electronic…
Q: A firm has established a distribution network for the supply of a raw material critical to its…
A: Formulas used: Solver Parameters: Solution:
Q: Construct a time series plot. What type of pattern exists in the data? a. Develop the three-week…
A: There are various methods to forecast demand/sales like the moving averages method, exponential…
Q: 15-19 A new president at Big State University has made student satisfaction with the enrollment and…
A: Given data: Number of samples (N) = 12Sample size (n) = 10 Complaints (np) =…
Q: Letherin Hides is a company that makes boots specifically targeting college students. Forecasts of…
A: Since details to backlog allowable or not we cant assume backlogs are allowed hence produce atleast…
Q: describe five sources of risks in a small business
A: Risk management can be stated as the approach of recognizing, evaluating, and handling the risks to…
Q: Which of the following best describes how product design might affect the purchase process as I laid…
A: Product design refers to ideas and a processes which are taken in a real form to get a new product…
Q: True or False: An objective of lean operations is the increase of inventory to the lowest possible…
A: Lean operations refers to the series of actions which are takes by the management to eliminate…
Q: The demand and forecast information for the XYZ Company over a 12-month period is shown in the table…
A: Given data:
Q: As a project manager, in construction industry (a) Explain the usual activities involved in each…
A: The construction project life cycle encompasses through the following stages, 1. Initiation: It…
Q: The goal of managing knowledge is to enhance an organisation's efficiency and save knowledge within…
A: Knowledge management is the deliberate act of defining, organizing, retaining, and sharing an…
Q: The Wacky Widget Company manufactures widgets. Manufacturing widgets takes four steps, done in…
A: Given data Demand rate = 0.14 widgets per minute The supply rate of the raw material = 0.18…
Q: An Electrical and Electronics parts manufacturer purchases circuit board for manufacturing…
A: Annual demand (D) = 2000 * 2 = 4000 Ordering cost (O) = 40 Holding/Carrying cost (C) = 20% per…
Q: A firm making snowblowers produces the augers for each snowblower in batches. Annual demand is for…
A:
Q: ETHICAL SOURCING FOR WOOLWORTHS HERE'S HOW WE'RE SOURCING RESPONSIBLY: Woolworths is a member of…
A: Supplier management is described as the process through which maximum value is achieved from the…
Q: 1. The R&D department is planning to bid on a large project for the development of a new…
A: A project network is the visual representation of the project activities and their respective…
Q: In the Melitz (2003) model, competition takes the form of free entry of firms to the market at a…
A: The Melitz model is a world of regular countries which contains one factor which is labor and one…
Q: 5. Consider a bank with three tellers. An average of 90 customers per hour arrive at th bank and…
A: s: The number of servers in the system, which is 3 hereμ: Mean Service Rate, which is 60/2.0 = 30…
Q: Use the graphical solution procedure to find the optimal solution. b. Assume that the objective…
A:
Q: It's important to know what manual testing is and what its benefits are.
A: Manual testing:- GManual testing and automation testing can both be effective tools in software…
Q: What country has the most vessel calls? A. Japan B. Brazil C. U.S. D. China
A: Vessel calls refers to a like a halt where the passenger or cargo can be loaded or unloaded before…
Q: That One Book sells its books through The Witch and the Wardrobe bookstores. It costs That One Book…
A: Cost price for The witch and the wardrobe book store = $1.00 Selling price for The witch and the…
Q: The BMW Group sees diversity as a strength and this factor in its workforce is one of the keys to…
A: given,
Q: Ada is running a store to sell soft-drink and snacks. For one soft-drink, given the daily demand is…
A: according to you, we are answering the options 4,5 and 6 in the option 4 given, daily demand = 32…
Q: How will you manage your time as a supply chain manager? Please do fast ASAP fast
A: Supply chain manager:- As a supply chain manager, there are always tasks that need to be…
Step by step
Solved in 2 steps
- Assume the demand for a companys drug Wozac during the current year is 50,000, and assume demand will grow at 5% a year. If the company builds a plant that can produce x units of Wozac per year, it will cost 16x. Each unit of Wozac is sold for 3. Each unit of Wozac produced incurs a variable production cost of 0.20. It costs 0.40 per year to operate a unit of capacity. Determine how large a Wozac plant the company should build to maximize its expected profit over the next 10 years.A retailer uses the order-up-to model to manage inventory of an item in a store. The leadtime for replenishments is four weeks and it can place orders weekly. Weekly demand isPoisson with mean 0.10 unit. Its order-up-to level is five and unfilled demand is backordered. What is the coefficient of variation of its orders?A company is using a continuous review system for its inventory. Due to the contracts made with the customers, the weekly demand is constantly 40 units. The average lead time of orders is 2 weeks and the standard deviation of lead time is 1 week. The current service level is 95%. In order to reduce inventory holding costs, the company wants to reduce its reorder point. To achieve this, there are two options that have approximately the same cost for the company: reduce the standard deviation of lead time to 0.5 weeks or reduce the service level to 90%. A) Which option is more advantageous for the company? B) How much reduction does this option bring in the reorder point as opposed to the current situation? Show your calculations
- Daily demand of a chemical at an oil refinery is normally distributed with a mean of 60 litres and a standard deviation of 7. The supplier reliably delivers the chemical by maintaining a constant lead time of 1 week. There are no delivery charges from the supplier. Sales occur throughout the year. An order placement requires one hour of an administrative employee who is paid $20 per hour. Receiving and storing a chemical shipment requires two workers to work for half an hour. Workers are paid $12 per hour each. Chemical’s purchase price is $500 per litre. Annual cost of capital is 5%. Other holding costs are estimated to be $0.5 per litre. Find the order quantity and the reorder point to satisfy a 95% service level during the lead time. (Round answers to 2 decimal places.)Ray wishes to determine the optimal order quantity for its best-selling bike in his bike store. Ray pays the supplier a wholesale price of $118 each for this bike. Ray has estimated the average daily demand for this bike is 23 units. The store opens 304 days a year. The cost to carry one bike in the store for a whole year is 8% of the unit bike cost. Ray has estimated that, on average, the order processing cost, i.e., ordering cost, with the bike supplier each time is $152, and it roughly takes 20 working days to receive the order from the supplier. Ray wishes to avoid the stock-out situation with a probability of 95%, and this requires Ray to carry a safety stock of 30 bikes in the store. What is the optimal order quantity (EOQ value) that Ray should order each time from the bike supplier to minimize his long-run inventory cost?E - Max uses the basic EOQ model to determine the order quantity . They used to buy electronics from a Korean supplier in Dubai with a lead - time of 5 days . Recently , the supplier has decided to close the warehouse in Dubai and deliver all items from Korea directly to customers in Oman with a lead time of 10 days . Under this situation , the economic order quantity will (Q^ * ) 1)double 2)None of these 3)increase , but not double 4)decrease by a factor of two 5)do remain the same
- The materials manager of a tire manfacturer must predict periodically place order for a key chemical one of the raw materials used in manufacturing uses the chemical at a rate of 300lbs each week and the lead time of delivery is 4 days. Assume that the manufacturing operation runs 5 days a week. At what point should the chemical be reorderedd a. when 1200lbs are remaining b. where 0lbs are remaining c. where 375lbs are remaining d. when 240lbs are remVallie Enterprise sells a product that cost $200 per unit and has a monthly demand of 500 units. The annual holding cost per unit is calculated as 2% of the unit purchase price. It costs the business $30 to place a single order. The maximum number of units sold for any one week is 150 and minimum sales 80 units. The vendor takes anywhere from 2 to 4 weeks to deliver the merchandise after the order is placed. The EOQ model is appropriate. i) What is the cost minimizing solution for this product each year? ii) Determine the re-order level, minimum inventory level and maximum inventory level for the product.Acta Metals manufactures safes of different sizes and models. One of the models has a demand of 20,000 safes/year. The company can produce at a rate of 4,000 safes a month and it cost $30 to initiate each production run. The actual production cost for each safe is $5.37 and the holding of each unit could be charged a nominal annual interest rate of 15%, if it were to be invested elsewhere. Determine the optimal batch size and the cycle time Determine the maximum on-hand inventory and the average annual holding and setup cost, Determine the production uptime and downtime.
- A newsvendor pays $.30 for each paper and sells each paper for $.50. From past data ,it shows the average demand of 90 papers with standard deviation of 10 papers and demand follows the normal distribution. So, how much newspaper should he stock?At Dot Com, a large retailer of popular books, demand is constant at 32,000 books per year. The cost of placing an order to replenish stock is $10, and the annual cost of holding is $4 per book. Stock is received 5 working days after an order has been placed. No backordering is allowed. Assume 300 working days a year.a. What is Dot Com’s optimal order quantity?b. What is the optimal number of orders per year?c. What is the optimal interval (in working days) between orders?d. What is demand during the lead time?e. What is the reorder point?f. What is the inventory position immediately after an order has been placed?COMPUTING REORDER POINTS (ROP) FOR IPHONES WITH AND WITHOUT SAFETY STOCKAn Apple store has a demand (D) for 8,000 iPhones per year. The firm operates a 250-day working year.On average, delivery of an order takes 3 working days, but has been known to take as long as 4 days. Thestore wants to calculate the reorder point without a safety stock and then with a one-day safety stock.APPROACH c First compute the daily demand and then apply Equation (12-6) for the ROP.Then compute the ROP with safety stock.