A manufacturer receives a batch of 1, 500 components daily and decides to institute an acceptance sampling scheme. Two possible plans are considered: PLAN A: A sample of 30 components to be tested -- accept the batch if 2 or fewer non-conforming components are found, otherwise reject.
NEED ASAP.
Remarks: Input values up to 3 decimal places only
A manufacturer receives a batch of 1, 500 components daily and decides to institute an acceptance sampling scheme. Two possible plans are considered:
PLAN A: A sample of 30 components to be tested -- accept the batch if 2 or fewer non-conforming components are found, otherwise reject.
PLAN B: A sample of 40 components to be tested -- accept the batch if 1 or fewer non-conforming components are found, otherwise reject.
The risk is set at 5% at an AQL of 2% defective, and the risk is set at 10% at LTPD of 10% defective.
* Answer the following questions:
For PLAN A, what is the probability of accepting batches containing 2% non-conforming? Blank 1
For PLAN A, what is the probability of accepting batches containing 10% non-conforming? Blank 2
For PLAN B, what is the probability of accepting batches containing 2% non-conforming? Blank 3
For PLAN B, what is the probability of accepting batches containing 10% non-conforming? Blank 4
Which plan would be most appropriate if there should be a high probability of accepting batches containing 2% non-conforming? Blank 5 Options -- Acceptable inputs: { A, B, None }
Which plan would be most appropriate if there should be a high probability of rejecting batches containing 10% non-conforming? Blank 6 Options -- Acceptable inputs: { A, B, None }
Which plan protects both the supplier and the customer? Blank 7
Options -- Acceptable inputs: { A, B, None }
Step by step
Solved in 3 steps