A project has the following list of relevant activities and time estimates in weeks: Time Estimates (weeks) Likely 4 Activity Description Predecessors Optimistic 3 Pessimistic 11 A Contract signing None Questionnaire design Target market ID Survey Sample Develop presentation Analyze results Demographic analysis В A 8 A D В 8 12 20 E B 12 F D, C 2 7 G C 14 H Presentation to client E, F, G 1 2 4

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Can you solve this problem please

Question
A project has the following list of relevant activities and time estimates in weeks:
Time Estimates (weeks)
Optimistic
3
Activity Description
Predecessors
Likely
Pessimistic
A
Contract signing
None
4
11
Questionnaire design
Target market ID
Survey Sample
Develop presentation
Analyze results
Demographic analysis
B
A
8
C
A
3
D
В
8
12
20
E
В
12
F
D, C
2
4
7
C
9
14
H.
Presentation to client
Е, F, G
4
a
Construct an A-O-A (Activity on Arrow) or network diagram.
b.
Determine t, for each activity, and Tg for each event.
Which path is the critical path.
с.
Compute the probability that the project will be completed within 28 weeks.
Compute the probability that the project will be completed within 32 weeks.
d.
е.
f.
Construct an A-O-N (Activity on Node) diagram.
g.
Using forward pass and backward pass calculate ES, EF, LS, LF and slack times for each activity.
h.
If Activity D is delayed 2 weeks and Activity E is delayed 3 weeks what will be the effect of these
delays to the project completion time? (What will be the project completion time in this case?)
Transcribed Image Text:Question A project has the following list of relevant activities and time estimates in weeks: Time Estimates (weeks) Optimistic 3 Activity Description Predecessors Likely Pessimistic A Contract signing None 4 11 Questionnaire design Target market ID Survey Sample Develop presentation Analyze results Demographic analysis B A 8 C A 3 D В 8 12 20 E В 12 F D, C 2 4 7 C 9 14 H. Presentation to client Е, F, G 4 a Construct an A-O-A (Activity on Arrow) or network diagram. b. Determine t, for each activity, and Tg for each event. Which path is the critical path. с. Compute the probability that the project will be completed within 28 weeks. Compute the probability that the project will be completed within 32 weeks. d. е. f. Construct an A-O-N (Activity on Node) diagram. g. Using forward pass and backward pass calculate ES, EF, LS, LF and slack times for each activity. h. If Activity D is delayed 2 weeks and Activity E is delayed 3 weeks what will be the effect of these delays to the project completion time? (What will be the project completion time in this case?)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.