Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks No Tasks Predecessors Duration Cost ($) Real cost ($) % complete (Weeks) 1 A 3 300 300 100 A 2 4 350 360 100 3 C А;B В 3 5 300 300 90 4 D B+1 4 6. 800 720 90 5 E C; D 4 300 250 30 6. F E+2 120 50 30 7 G D, E 3 4 150 8 F; G 2 180 Identify ETG, EAC, and Cost variation and Schedule delay at completion

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
Give data of a project. Project manager checks the project at the end of week 10th
Tasks
Duration
Manpowers/
weeks
Cost ($)
Real cost ($)
% complete
No
Predecessors
(Weeks)
1
A
3
3
300
300
100
2
В
A
4
350
360
100
3
C
А; В
3
5
300
300
90
4
B+1
4
6.
800
720
90
E
C; D
3
4
300
250
30
6.
F
E+2
2
120
50
30
7
G
D, E
F; G
3
4
150
8
H
180
Identify ETG, EAC, and Cost variation and Schedule delay at completion
Transcribed Image Text:Give data of a project. Project manager checks the project at the end of week 10th Tasks Duration Manpowers/ weeks Cost ($) Real cost ($) % complete No Predecessors (Weeks) 1 A 3 3 300 300 100 2 В A 4 350 360 100 3 C А; В 3 5 300 300 90 4 B+1 4 6. 800 720 90 E C; D 3 4 300 250 30 6. F E+2 2 120 50 30 7 G D, E F; G 3 4 150 8 H 180 Identify ETG, EAC, and Cost variation and Schedule delay at completion
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,