A vertical summit curve is having tangents which intersects at point Pl at Station 12+584.57 and 139.32 meters elevation. The grade for the forward tangent is -5.25%. Station PC is at
Q: vertical summit curve is having tange hich intersects at point Pl at Station 12 d 139.32 meters…
A: PVCSTATION=PVISTA-L212527.65=12584.57-L2L=113.84mPVCELV=PVIELV-g1L2122.32=139.32-g1×113.842g1=29.866…
Q: Slenderness ratio of a 5 m long column hinged at both ends and having a circular cross section with…
A:
Q: Determine the design moment capacity of the section. (kN-m)
A: Given Data: The data are given as: fc' = 55 MPafpu = 1350 MPaAps = 1500 mm2fpy = 1100 Mpa To…
Q: Solve
A:
Q: The uniform boom shown below weighs 656 N, and the object hanging from its right end weighs 428 N.…
A:
Q: What is the importance and role of moisture content in the construction material utilization?…
A: It is very important to determine the moisture content of the construction material for following…
Q: The speed-density relationship for a particular road was found to be : u = 42.76 - 0.22 k, where u…
A:
Q: $0 50 25 100 25
A:
Q: Find the axial forces at CG, DH, GH, BC, and BG in the truss shown below: 2m 2m 2m 2m C B D 1m E 1m…
A:
Q: Problem 2: A solid circular shaft is acted upon by the torques as shown. If G= 12, 000 ksi…
A:
Q: Question 3 The sieve analysis of soil and the liquid and plastic limits of the fraction passing…
A:
Q: 1. A steel tire has a dimensions indicated in the figure below. At 78 degrees Celsius, the said tire…
A:
Q: Get the shear and moment function and draw the shear and moment diagram for the beam. A simply…
A:
Q: Steel railroad rails 10 m long are laid with end-to-end clearance of 5 mm at a temperature of 18°C.…
A:
Q: Given are the following: fc’ = 55 MPa fpu = 1,350 MPa Aps = 1,500 mm2 fpy = 1,100 MPa Use…
A: Answer We are given f'c = 55 Mpa fpu = 1350 Mpa Aps = 1500 mm2 fpy = 1100 Mpa distance from…
Q: Get the shear and moment function and draw the shear and moment diagram for the beam. A simply…
A:
Q: A torque of magnitude T = 1000 N·m is applied at D as shown. Shaft AB and CD have an elliptical…
A:
Q: 4. Compute for the reaction at the roller B, the force components acting on the ball- and-socket at…
A:
Q: Situation 02. An evaporation pan was set-up adjacent to a reservoir. The depth of water in the pan…
A:
Q: Which of the following best gives the plastic moment capacity of the W410x68, Fy = 345 MPа? bf tf…
A:
Q: Q.2 (c) A homogeneous anisotropic embankment dam section is shown in the figure, the coefficient of…
A:
Q: A single rolling load of 40 kN rolls from left end along a simply supported girder of span 20 m. The…
A:
Q: Water flows through a pipe at 5 L/s as shown. If the gage pressure of 12.5 kPa, 11.5 kPa and 10.3…
A:
Q: Find support reactions Use method of consistent deformations by area moment method Select interior…
A:
Q: HYDRAULICS LABORATORY LABORATORY NO.4 2. The experimental results show that there is a pressure drop…
A: When we perform experimental results show that there is a pressure drop across the meter from inlet…
Q: In 28.5 secs, 35,579 L of water is collected. The length of the rectangular weir is 2.15 m, the…
A:
Q: 27. A certain machine has book value of P173,205.08 after 5 years and P82,187.59 after 8 years. The…
A:
Q: Figure shows the side view of a tank with a curved gate. The gate width into the page is 18 in. The…
A:
Q: What diameter of a standard, sharp-edge orifice will be required to produce a discharge of 1.25 cfs…
A:
Q: Steel railroad rails 12 m long are laid with end-to-end clearance of 5 mm at a temperature of 22°C.…
A:
Q: quired to displace the top plug to
A:
Q: x² + y2 + z? = 21, (1, 4, 2) (b) Find a set of symmetric equations for the normal line to the…
A:
Q: 25. A structure cost P12,000 new. It is estimated to have a life of 5 years with salvage value at…
A: Cost of structure = 12000 Estimated life = 5 years Salvage value = 1000 To Find :- Book value at the…
Q: Bar BDE is pinned to two links, AB and CD. At the instant shown, the angular velocities of link AB,…
A: Given Length of AB= 240 mm Length of CD= 180 mm
Q: What would be the effect on the results if the Venturi meter were not horizontal? Would you make any…
A:
Q: Calculate the weight of moist gravel that should be in a batch if the design mix requires concrete
A: Moisture content: - It is defined as the ratio of total weight of water by weight of solid.
Q: According to Euler's column theory, the crippling load for a column of length (I) fixed at both ends…
A:
Q: 18. Determine the capitalized cost of a bridge whose cost is P200 Million and its life is 50 years,…
A:
Q: Replace the two forces acting on the post by a resultant force and couple moment at point O. Express…
A: A=8kB=6jC=6kD=2i-3jAB=6j-8kCD=2i-3j-6kFAB=5ABABFAB=56j-8k62+82=3j-4kFCD=6CDCDFCD=62i-3j-6k22+32+62=1…
Q: 30. The excess between the selling price and total variable costs is known as?
A: Factual definition based question is asked please refer step 2 for detailed explanation and…
Q: In a violent construction place where there is presence of rebels or criminals, what safety…
A: Construction site has many equipments and material that can be stolen, also violence can a break out…
Q: For a data of maximum recorded flood of a river, the mean standard deviation are 4200 m3/s and 1705…
A:
Q: Angular Velocity of disk C
A: Data Given: ωA = 400 RPM Asked: Angular velocity of disk C
Q: a
A: Given open cylindrical tank, with diameter d= 605 mm thickness t = 3.02 mm a= 40.10 MPa, b =…
Q: The tank shown in the accompanying figure is being filled by Pipes 1 and 2. If the water level is to…
A: For no change in water level in tank. The discharge entering the tank must be equal to discharge…
Q: Design a column to support an axial load of 700 kN. The <olumn has an effe<tive length of 7 m with…
A:
Q: Problem Solving: 1. The details of the cantilever beam are shown below. Use f'c = 28 MPa, fy = 415…
A: As per bartleby's guidelines, we are supposed to answer only first three questions. Kindly repost…
Q: In the figure shown, if wa=300rpm, solve for (a) the angular velocity of disk C (in rad/s) (b) the…
A: Figure is as given in the question
Q: pint A?
A: Velocity always acts tangential to the surface. Therefore the velocity at A is upwards.
Q: A beam having a width of 500 mm and a total depth of 800mm is reinforced with 6-32mm dia bars.…
A: Hi! Thank you for the question, As per the honor code, we are allowed to answer three sub-parts at a…
Step by step
Solved in 2 steps
- The length of curve at side of PC is 45 while on the PT is 50m. A sewer line with its top having an elevation of 108.6 is found at station 6+826. A parabolic curve is to be constructed having a back tangent of 5.5% and forward tangent of - 8.5% with PC stationed at 6+785 having an elevation of 111m. Determine the height of fill from sewer line.A -6% grade and a +2% grade intersect at STA 12+200 whose elevation is at 25.632m. Two grades are to be connected by a parabolic curve, 160m long. A. Find the grade of the first quarter point on the curve. In decimal form B. Find the stationing of the lowest point of the curve.CONNECT A FORWARD TANGENT OF 3% AND A BACK TANGENT OF-15% BY A 300 M SYMMETRICAL PARABOLIC CURVE. IT WAS DISCOVERED THAT THE GRADE INTERSECTION AT STA 10+100 with ELEVATION 50 M FALLS ON ROCKY SECTION WITH THE EXPOSED BOULDER AT ELEVATION 102.67. TO AVOID ROCK EXCAVATION, IT WAS DECIDED TO ADJUST THE VERTICAL PARABOLIC CURVE THAT THE CURVE WILL JUST CLEAR THE ROCK WITHOUT ALTERING THE POSITION OF PC AND THE GRADE OF EACH TANGENTS. DETERMINE THE ELEVATION AND STA OF THE NEW PT.
- 3. A grade descending at the rate of -4% intersects another grade ascending at the rate of +8% at station 2+000, elevation 100m. A vertical curve is to connect the two such that the curve will clear a boulder located at station 1+980, elevation 101.34. Determine the necessary length of the curve. Sketch the curve.The tangents of a sag curve connects at the point of intersection having Station 18+410.48 and elevation 155.94 meters. Point PT at the end of the curve lies at Station 18+533.71 and elevation 172.06 meters. The grade of the back tangent is -5.19% . Determine the elevation of the lowest point in meters. Plot and show solutionA. Horizontal curve has R=780 ft. what is the degree of curvature? B Ahorizontal ccurrve has a rradius of 780 ft if the tangent is 220 ft what is the length of the curve? CC a horizontal ccurve starts at STA(100+00.00) the PI is at STA(107+50.00). If the inclined aangel l is 36 degree where is PT Pleeasee help
- A horizontal curve with P.C is stationed at 3+025.42 and having a radius of 120 m. A property line with an azimuth of 300° intersects the curve at point B. Then a random line was run from the P.C of the simple curve towards the property line which intersects at point A, with an azimuth and distance of 190° and 42.50m respectively. Determine the stationing of B, knowing that the back tangent of the curve has an azimuth of 220°. Show a Clear and Organized solution:topic: fundamentals of surveying A 3% ascending grade meets a descending grade at the vertex at station 2+050 and elevation 100m with a curve elevation of 97.333m below it. The tangents are connected by an unsymmetrical parabolic curve and the vertical offset of the point of tangency from the back tangent is 9.60m. If the length of the second curve is 80m, determine: A.) Length of the 1st Curve = [L1] B.) Stationing of the Highest Point = [StaHP] C.) Elevation of the Highest Point = [ElevHP]A symmetrical parabolic curve passes through point A whose elevation is 23 23m at a distance of 54 meters from PC The elevation of the P.C. at station 4+100 is 22.56m. The grade of the back tangent is +2% and the length of the curve is 120m. Determine the grade of the forward tangent a. -2.3% b. -1.4% c. -3.3% d. 2.5%
- Two tangents having an azimuth of 235° and 277° meet at station 30+28.212 are connected by a 330ft spiral curvewith a 5° circular curve used for light rail transit.a) Determine the difference between the external distance of the spiral and the central curve.b) Determine the minimum super-elevation of the curve at the two-thirds of the spiral with the railway width of 15ft. If g= 32.2 ft/s^2c) Determine the stationing of the S.T.. A grade line AB having a slope of +5% intersect another grade line BC having a slope of –3% atB. The elevations of pointsA,BandCare 95 m, 100 m and 97 m respectively. Determine the elevation of the summit of the 100 m parabolic vertical curve to connect the grade lines. Resolve using equations for a parabola. (y=Ax^2+Bx+C)the three courses AB, BC and CD have bearing N56°30'E, N80°30'E and S32°17'E, respectively. if BC= 57.80m, determine the radius of the curve that shall be tangent to three courses