a) What are the activities on the critical path (using the letters provided) b) What is the shortest amount of time (in days) that this project can finish c) Can activity C be delayed without impacting the end date of the project? yes or no d) If activity C can be delayed, by how many days can it be delayed before the project is delayed? o Craching activi by 1 day will cost ¢100 should vou do this? Why or why pot?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
A 4
D 8
Start
B 5
E 3
Finish
Key
C 2
F 2
Activity Duration
Using the network diagram above, answer each of the 5 questions below:
a) What are the activities on the critical path (using the letters provided)
b) What is the shortest amount of time (in days) that this project can finish
c) Can activity C be delayed without impacting the end date of the project? yes or no
d) If activity C can be delayed, by how many days can it be delayed before the project is
delayed?
e) Crashing activity B by 1 day will cost $100, should you do this? Why or why not?
Transcribed Image Text:A 4 D 8 Start B 5 E 3 Finish Key C 2 F 2 Activity Duration Using the network diagram above, answer each of the 5 questions below: a) What are the activities on the critical path (using the letters provided) b) What is the shortest amount of time (in days) that this project can finish c) Can activity C be delayed without impacting the end date of the project? yes or no d) If activity C can be delayed, by how many days can it be delayed before the project is delayed? e) Crashing activity B by 1 day will cost $100, should you do this? Why or why not?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.