a. Develop a network diagram for the project using AON convention. b. Determine the project completion time, the critical path, and the slack time for each activity. c. Suppose the plant manager has been given only 12 weeks to install the new pollution control equipment. Determine which activities are to be crashed, and by how much, to meet the 12-week due date. Use the information in the following table for crashing.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Milwaukee Paper Manufacturing will install an advance computerized air pollution
control equipment in its facility. It had identified eight activities that needs to be
performed for the project to be completed. Refer to the table below for the details of
the activities.
Activity
Description
Immediate
Duration
Predecessor
(Weeks)
S
A
Build internal component
2
B
Modify roof and floor
3
с
Construct collection stack
A
D
Pour cement and install frame
A, B
E
Build high-temperature burner
с
F
Install pollution control system
с
G
Install air pollution device
D, E
5
H
Inspect and test
F, G
2
Do the following:
a. Develop a network diagram for the project using AON convention.
b. Determine the project completion time, the critical path, and the slack time
for each activity.
c. Suppose the plant manager has been given only 12 weeks to install the
new pollution control equipment. Determine which activities are to be
crashed, and by how much, to meet the 12-week due date. Use the
information in the following table for crashing.
Activity
Normal time
Crash time
Crash cost per
week(s)
A
2
1
750
B
3
1
2,000
с
2
1
1,000
D
4
3
1,000
1,000
500
1,500
3,000
TIM
E
F
G)
H
4
3
5
IN
2
IN
2
2
2
1
NI
2
4
3
Transcribed Image Text:Milwaukee Paper Manufacturing will install an advance computerized air pollution control equipment in its facility. It had identified eight activities that needs to be performed for the project to be completed. Refer to the table below for the details of the activities. Activity Description Immediate Duration Predecessor (Weeks) S A Build internal component 2 B Modify roof and floor 3 с Construct collection stack A D Pour cement and install frame A, B E Build high-temperature burner с F Install pollution control system с G Install air pollution device D, E 5 H Inspect and test F, G 2 Do the following: a. Develop a network diagram for the project using AON convention. b. Determine the project completion time, the critical path, and the slack time for each activity. c. Suppose the plant manager has been given only 12 weeks to install the new pollution control equipment. Determine which activities are to be crashed, and by how much, to meet the 12-week due date. Use the information in the following table for crashing. Activity Normal time Crash time Crash cost per week(s) A 2 1 750 B 3 1 2,000 с 2 1 1,000 D 4 3 1,000 1,000 500 1,500 3,000 TIM E F G) H 4 3 5 IN 2 IN 2 2 2 1 NI 2 4 3
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.