create a PERT/CPM chart for this project and identify the overall project duration and critical path.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%

We are the project manager for an IT project in our company. We identified the following top-level project tasks and estimated durations to standup a small test lab for the project:

  • Identify test lab building/space requirements and possible locations(8days)
  • Select best location for lab (1day)
  • Once the best location is selected, immediately start the next two tasks:
    • Prepare lab space with power and cabling (3days)
    • Identify/procure required specialized test lab hardware/software(5)
  • Once the lab space is prepared, install/check out available infrastructure hardware/software(1day).
  • Once the specialized software/hardware is received and the infrastructure hardware/software is installed/checked out, install/checkout specialized software/hardware (2days)
  • Once all tasks are completed, conduct the final inspection (1 day).

Let's create a PERT/CPM chart for this project and identify the overall project duration and critical path.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.