a. Draw the AOA network. b. Calculate the Early Event Time and Late Event Time for every node in the resulting AOA network. c. Determine Total Float and Free Float for every activity (arc) in the result@ling AOA network.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter6: Optimization Models With Integer Variables
Section: Chapter Questions
Problem 100P
icon
Related questions
Question

M.

Consider the following the House Construction Project:
Task
Label
Duration Prerequisite
(weeks) Tasks
A
7
B
C
D
E
F
G
H
I
J
Task
Masonry
Carpentry for roof
Roof
Pipe and Electrical Installations
Front of House
Windows
Garden
Ceiling
Painting
Moving In
a. Draw the AOA network.
3
1
8
2
1
1
3
2
1
A
B
A
D, C
D, C
D, C
F
H
E, G, I
b. Calculate the Early Event Time and Late Event Time for every node in the resulting AOA
network.
c. Determine Total Float and Free Float for every activity (arc) in the resulting AOA network.
d. Determine a Critical path in the resulting AOA networ
Transcribed Image Text:Consider the following the House Construction Project: Task Label Duration Prerequisite (weeks) Tasks A 7 B C D E F G H I J Task Masonry Carpentry for roof Roof Pipe and Electrical Installations Front of House Windows Garden Ceiling Painting Moving In a. Draw the AOA network. 3 1 8 2 1 1 3 2 1 A B A D, C D, C D, C F H E, G, I b. Calculate the Early Event Time and Late Event Time for every node in the resulting AOA network. c. Determine Total Float and Free Float for every activity (arc) in the resulting AOA network. d. Determine a Critical path in the resulting AOA networ
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS