a. For each activity, calculate: ESD, EFD, LSD, LFD, FF, and TF. (Report your answers in the table above) b. Find the critical path(s), and the project duration.
Q: Table 1: Expected time, standard deviation and cost associated with each activity of a project…
A: From the above network diagram and table: a) critical path is the path with maximum expected time:…
Q: For the activities shown in the table using PERT, draws the network diagram and determine the…
A: Find the Duration calculations below:
Q: __________2a) What steps comprise the “critical path”? __________2b) What is the minimum completion…
A: A project network is a graphical network that shows the duration of project activities and their…
Q: Explain
A: The above project matrix is a planned approach to focus on important tasks which are important for…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Identify the critical path in the project. b. Determine the length of the project. Using the data,…
A: The critical path method is a process that helps to identify tasks that are essential for project…
Q: Ql: For activities shown in table below, find the new time of project after upd project manager…
A: Given that:Activities A-J What to do:First: Find the Critical path of the activities.Second:…
Q: 1- Data for small project are given, determine the following 1- ES for Activity C. E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. Using the information in this section, write a project plan for NIBCO. 2. Why is change…
A: Nibco focuses upon the big bang approach. The project will be achieved by NIBCO workers and IBM…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: please help, project management 1) Given the following information for a one-year project, answer…
A: This question is related to the topic Project Management and This topic falls under the…
Q: Find out the following: a. Sketch the whole network. b. Find out critical path by analyzing and…
A: Below is the solution:-
Q: a) Draw an ACON diagram of the project, including activity durations. b) Define the critical path,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: What is the most important points that must be included in the analysis performance of the…
A: The analysis of the project performance is the procedure of contrasting the actual cost of the…
Q: Draw the AON project network using the following information: How long would it take to complete…
A: The diagram of the AON project network is shown below
Q: Describe approach to tracking a project. What kinds of issues would you focus on if you were a…
A: Keeping track of a project is a difficult task. A project manager may use this method to track down…
Q: A. Draw a project network. B. What are the critical activities? C. Will the project be completed…
A:
Q: a. Determine the expected activity completion times, te. b. Identify the critical path. c. What's…
A: The first four subparts (a), (b), (c), and (d) are answered below.
Q: Subject: Critical Path Method as a Project Management Technique Please answer the following…
A: Given data is
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the path in the project network that takes the highest time to complete the…
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given data is
Q: Two international banks are integrating two financial processing software systems as a result of…
A: Activity Immediate Predecessors Activity Time A - 3 B A 1 C A 2 D…
Q: nd throughout a project. 2. For each project phase identified in 1(a) above, identify and describe…
A: The project life cycle contains the processes necessary for project managers to effectively manage a…
Q: Find out the following: 1.Sketch the whole network. 2.Find out critical path by analyzing and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: 1- Data for small project are given, determine the following 1- ES for Activity C, E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance…
A: WE ARE ALLOWED TO DO THREE SUB-PARTS ONLY. THE ANSWER IS AS BELOW:
Q: QI: Draw the arrow diagram for the following activities and show the critical path: activity…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES = maximum…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Component of the project activities described in the following table, the critical path of the…
A:
Q: The network diagram for a new project your company is undertaking is as shown: Start +Einish a.…
A: Given data is
Q: Consider the below project information for questions 1-4. Activity Immediate Duration (days)…
A: Answer: A project consists of different activities. The project mentioned in the question is having…
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: a. Draw a CPM network for the project. b. Provide an overview for the project by computing the…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: F A A Start Finish Start Finish 3 G 8 3 8 b. Determine the critical path and project duration. The…
A: The concept used here is calculating slack and critical path using Project evaluation and review…
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given data is
Q: d. What is the expected project length? e. What is the slack time for individual activity? f.…
A: The AON diagram as per the given information is as follows:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Suppose that the following estimates of activity times (in weeks) were provided for the network…
A: From the given data, the expected project completion time is 21.5 weeks. Formulas:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Find the project details in the below table, draw the network activity diagram and identify the…
A: Critical path can be defined as the path which is having the longest duration.
Q: Immediate Estimated Activity Predecessors Duration A t+5 months В t+1 month C В t+2 months A, C t+4…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for planning a…
Q: Roger Ginde is developing a program in supplychain management certification for managers. Ginde…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: Ql: For activities shown in table below, find the new time of pro project manager decided to update…
A: Given that: Activities A-J What to do: First: Find the Critical path of the activities. Second:…
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the path that takes the longest time to complete the whole project…
Q: Analyze the cost variance metric, and include the equation and what the acronyms stand for
A: Note: As per the Bartleby guidelines, only the first question has been answered.
Q: Using the information in Table-1, assuming that the project team will work a standard working week…
A: Given data is Working days = 5
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and and complete the performance indexes table. Calculate the EACf, and the VACfActivityPredecessorDuration (days)a-10b-15ca17db5eb4fc15gd7he8if12jg,h,i10 Draw the network (AON) and calculate and calculate the Critical PathGeneral Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000
- Develop a CPM diagram for the activities/relationships listed below (assumedurations are in months). For each activity calculate the Early Start, Late Start, EarlyFinish, Late Finish, Total Float, and Free Float. Clearly identify the critical path forthe project (hint: a highlighter would be a good tool to use) How do you solve this? I don't understand how it's done.Critically assess and comment on the success of the project from the followingviewpoints aline with a project To enhance Sports development by providing assistance to sports clubs and teams in St. Catherine North Central by providing them with the necessary gears and equipment for whichever Sporting disciple that they may part-take in. a. Level or degree of alignment of end results and outcomes to the organization’sstrategic goals.b. Level of success in the management of the triple constraints of time, cost, andscope.Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table attached as an image. Determine the minimum cost-schedule for this project to be completed in 18 weeks. Assume a linear relationship between crash cost and crash time. For example, crash cost per week for activity A can be calculated as: ($650 - $200)/(4-2) = $225. 2. What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum cost-schedule you found in part 1?
- Use the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionOld MathJax webview Write a summary of "World Bank -Innovation in Solar Power Hybrid Technology Project in India". The summary should be in paragraphs containing the facets of Project Analysis as applicable. *The answer should be in detail*Given the following information, compute the required items: Florida Power & Light is attempting to modernize the meters placed at people houses. The company Operations Manager, Mr. Jacob Marina, has asked for your assistance in preparing part of the project plan. Mr. Marina has identified the tasks, durations (in days), and predecessor relationships, and provides them in the following table: Activity Immediate Predecessor(s) Most Optimistic Likely Pessimistic A -- 1 2 4 B A 2 4 8 C B 3 5 15 D C 3 5 12 E D 4 5 11 F D 4 6 17 G E 2 3 8 H E 1 2 4 I E 1 3 6 J G, H, I 2 4 12 K J 2 3 7 L H 2 4 9 M L 2 4 9 N K, M 3 4 12 O E, F 5 10 22 P N, O 1 2 5 Required: 1. Draw the Activity on Node (AON) network. 2. Determine the expected completion time and variance for each activity. 3.…
- please help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach?please help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited references.This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .