F A A Start Finish Start Finish 3 G 8 3 8 b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity (days) A В E F G E3

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Need help with part C, please. 

The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel:
Activity
Activity Time (days)
Immediate Predecessor(s)
A
В
1
A
3
A
В, С
E
3
5
E
G
8
E
Transcribed Image Text:The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity Activity Time (days) Immediate Predecessor(s) A В 1 A 3 A В, С E 3 5 E G 8 E
В
1
F
В
1
F
A
8
A
8
D
E
D
5
E
Start
Finish
Start
Finish
C
G
8
8
b. Determine the critical path and project duration.
The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.)
c. Calculate the slack for each activity. (Enter your responses as integers.)
Slack
Activity
(days)
A
В
E
F
G
Transcribed Image Text:В 1 F В 1 F A 8 A 8 D E D 5 E Start Finish Start Finish C G 8 8 b. Determine the critical path and project duration. The critical path is path A-C-D-E-G and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity (days) A В E F G
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Ownership
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.