a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot (L4L). (Leave no cells blank - be certain to enter "O" wherever required.) Gear Box Requirements 7 8 Week: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release 2 3 4 5 6 9 10 11 12 Input Shaft Requirements Week: 2 3 5 6 7 8 9 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release
Q: Planning orders using a lot-for-lot (L4L) technique is commonly done because it is simpleand…
A: Materials Requirement Planning (MRP) refers to the planning of inventory requirements of a…
Q: Given an order cost of $100, a, per period holding cost of $.50, and the following requirements…
A: In this arrangement, the serial requirements of an item beginning from the shortage or deficit date…
Q: Given the following data, calculate the projected available balance and the plannedMPS receipts. The…
A: A master production schedule (MPS) is a schedule for the production of individual goods in each…
Q: Daily demand for an item is shown here. Assume a holdingcost of $0.50 per unit per day, a setup cost…
A: Solution Ch = $0.50 per unit per year Setup Cost Cs= $100 Lead time = 1 day On hand Inventory = 70…
Q: m/mod/quiz/attempt.php?attempt%3D1600595&cmid%3813581&page=14 stem (Academic) ons Management ||…
A: Inventories are important for suppliers, manufacturers, retailers, warehouses, and distribution…
Q: 1) Gunakan strategi lima pekezja tetan dengan sokoABAn kecia lebih masa dan sub-kontrak tidak lebik…
A: Chase strategy of aggregate planning uses all the options i.e. subcontracting, hiring, firing,…
Q: One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of…
A: Develop a spreadsheet as shown below to get the desired answers.
Q: Anticipated demands for a four-period planning horizon are 23, 86, 40, and 12.The setup cost is $300…
A:
Q: 8. Which best defines the gross requirements for a component items a) The forecast customer demand…
A: Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: The current inventory levels and lead times of the input materials needed are shown in the table…
A: For making an order of 300 items, Number of circuit boards needed = 1×3000-223=2777 Number of bare…
Q: (a) Give examples of independent and related dependent demand
A: Note:- We are authorized to answer one question at a time, since you have not mentioned which…
Q: i. the minimal number of orders per year. Explain whether the nearest integer number of orders per…
A: The answer is as below:
Q: A machine shop uses the Silver–Meal heuristic to schedule production lot sizes for computercasings.…
A: Demand information (r): r1 = 18 r2 = 30 r3 = 42 r4 = 5 r5 = 20 Setup cost (k) = $80 Holding…
Q: c.What is the average inventory of elements, assuming each production cycle begins when there are…
A:
Q: The time-phased net requirements for the base assembly in a table lamp over the next six weeks are…
A: The Least Unit Cost (LUC) arrangement is a dynamic lot-sizing procedure that combines ordering and…
Q: Based on the following Master Production Schedule, the ATP of the first week is: Week: 1 2 3 4 FC…
A: Given data is Beginning inventory = 145
Q: 2. The time-phased net requirements for the base assembly in a table lamp over the next six weeks…
A: Since you have submitted questions with multiple sub-parts, as per guideline we have answered the…
Q: The stock in the second bin in a two-bin system is equal to Select one: O a. 50% of the order…
A: Inventory management refers to the process including ordering, storing, and using a company's…
Q: Quantity of a raw material listed in a purchase order counts as demand when you check the…
A: Inventory management is all about managing the inventory of a company which is the quantity of stock…
Q: 1. Which of the following statements about lot-sizing rules for MRP is true? a) The periodic order…
A: Systems maintain inventory in small lot sizes because small lot sizes enable schedules to use…
Q: A part is produced in lots of 1,000 units. It is assembled from 2 components worth $50 total. The…
A: Formulas:
Q: Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on- hand…
A: MPS L4L is done when on hand inventory is lower than the maximum value of forecasted demand and…
Q: 6-27
A: Note- Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: Product Inventory Holding Cost ($/unit-mo) A 1.0 B 3.0 Demand Forecast May June July Product A 300…
A: since here, only about ending inventory in June period for product B is asked, the solution is wrt…
Q: Semans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 131…
A: Master Production Scheduling is the process that helps manufacturers plan which products and related…
Q: The inventory control models discussed in Chapters 4 and 5 are often labeledindependent demand…
A: Independent demand is obtained via forecasting of end items which at the top or level 0 of Bill of…
Q: Economic order quantity (Q*) is 6,000 units. Annual demand (D) is 12,000 units. Find number of…
A: To determine the number of orders we simply divide the total demand (D) of units per year by Q, the…
Q: Irvine Consolidated Closets (ICC) builds and sells shelving for homes and offices. For a certain…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Master production schedule (MPS) A kite manufacturer produces the most popular model, the Long kite.…
A: Find the Given details below: Week 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 55 Customer…
Q: Given the forecast and booked orders shown in the table, and a beginning inventory of 0, what is the…
A: Find the Given Details below: Given Details Period 1 2 3 4 Forecasted Demand 100 100 90 90…
Q: ave’s local college football team is playing for the national championship in next month’s bowl…
A: Given that: Following payoff Matrix Alternatives Wins Loses Ties Order No Shirt 0 0 0 Order…
Q: Can the optimal stocking level in the single-period model ever be less than expected demand?Explain…
A: The main objective of a single period model is to determine the order quantity that can minimize the…
Q: CYCLE COUNTING AT COLE’S TRUCKS, INC. Cole’s Trucks, Inc., a builder of high-quality refuse trucks,…
A: Below is the number counted per day –
Q: Tomlinson Furniture has a single lathe for turning the wood for various furniturepieces, including…
A: Given data, Piece Requirement Time Cost Rate J-55R 125 1.2 $20 140 H-223 140 0.8 35 220…
Q: requirements over a typical six-month periou are as TUIIOW 1 3. 4. 5. Requirement 750 800 750 600…
A: Find the Given details below: Period 1 2 3 4 5 6 Total Requirement 750 700 800 750 600 900 4500
Q: 1. Speedy, Inc. is a company that produces automotive electrical components. AISI is a common part…
A: Answer: Calculation and formula are shown below:
Q: a. What run quantity should be used to minimize total annual costs? b. How many days does it take to…
A: Note: As per the Bartleby guidelines, only the first three parts have been answered. Given-…
Q: A plant manager of a chemical plant must determine the lot size for a particular chemical that has a…
A: Since you have asked multiple questions, we will solve first question for you ( a, b and c). If you…
Q: Discuss why order-point systems aren’t compatible with MRP
A: To illustrate the point, why the order-point systems and ,MRP cannot work together without any…
Q: a) How many units should be the safety stock? b) What's the product's inventory status? c) How many…
A: Weekly demand = 770 units Average daily demand, d = 770/7 = 110 units Standard deviation of daily…
Q: Reorder Point Ordering: Average demand per day (7) is 25 units, with a std. dev. of (od) 15 units.…
A: Demand during lead time (DDL): The lead demand (also known as lead time demand) is the complete…
Q: Material requirements planning (MRP) is a useful for all of the following except O a. independent…
A: The correct option is a independent demand items
Q: Master production schedule (MPS) A kite manufacturer produces the most popular model, the Long kite.…
A: Find the Given details below: Week 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 55 Customer…
Q: c. Complete the last three rows of the record by using the POQ lot-sizing rule, with P = 2. (Enter…
A: Material requirements planning (MRP) is an inventory management system that uses a number of…
Q: 43. Pies 'R'Us bakes its own pies on the premises in a large oven that holds 100 pies. They sell the…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: Inputs Average demand per unit time, D = Lead time, L= 300 SD of demand per unit time, oD = Target…
A: (a) Safety inventory is to cover demand fluctuations during the lead time. The formula to find the…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- 1. In an assemble-to-order company, at which level should master scheduling take place? a. The end item level b. The raw material/component level c. None of the above levels d. It does not matter, any level will do e. The component/subassembly level 2. The final assembly schedule (FAS) a. Schedules customer orders as they are received based on components planned in the MPS b. None of the above c. Is used with make-to-stock products d. Is used with make-to-order products e. A and b above 3. The functions of a master production schedule are to: I. Plan material components. II. Plan capacity requirements. III. Keep priorities valid a. II, III and not I b. None of the above is a function of the MPS c. I, II and III d. I, II and III e. I, III and not II 4.The information needed to develop a master production schedule will be got from a. Inventory levels for individual end items b. None of the above c. The production plan d. The forecast of individual end…SpikLock makes several lines of metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and faceplate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table. Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes A quick look at the amounts available confirms that SpikLock does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each…1.a. The typical PM work order is normally generated by a computer and then issuedA. directly to the machine operator.B. to the purchasing department to get the parts ready.C. directly to a back-up maintenance technician who will double-check the work.D. by the program administrator to the shop foremen. 1.b. Proper record keeping is important to a PM program. From a task scheduling perspective, why is recordkeeping important?A. Management will know how much work is being done.B. Those tasks that weren’t completed can increase in priority on the next downtime period.C. Management will know what employees are putting out the best effort.D. The quality of work can be evaluated.
- What is Work Breakdown Structure (WBS) and state 3 advantages of WBS. Arrange the following activities into the WBS to show how the work items decompose into activities. Software System Requirements Document Architecture Document Front End Middleware Back End Site templates Web Pages SQL Shema DB Data Admin Data Dynamic Pages Static PagesA #2 pencil (P) is made from a wood subassembly (WS), a band (B) to hold the eraser on and an eraser (E). The wood subassembly is made from 2 wood halves (WH) and a piece of lead (L), the wood halves are made from wood blanks (WB). (For this question we will ignore the need for glue and paint.) The lead times for each of these are given below Lead Time (Weeks) P 2 WS 4 B 6 E 2 WH 2 L 2 WB 1 If nothing is in inventory (that is, all on hand quantities are equal to zero), and it is now the beginning of period 20, then when is the earliest that we can promise to ship No. 2 pencils?One unit of A is made of three units of B, one unit of C, and two units of D. B is composedof two units of E and one unit of D. C is made of one unit of B and two units of E. E ismade of one unit of F.Items B, C, E, and F have one-week lead times; A and D have lead times oftwo weeks.Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have onhand(beginning) inventories of 10, 50, and 150, respectively; all other items have zerobeginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of Ein Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If30 units of A are required in Week 8, use the low-level-coded bill-of-materials to i nd thenecessary planned order releases for all components.
- Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there were 64 pumps in inventory at the beginning of week 1. A production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)The project manager of the gas station project shown inFigure 7.3 needs to change the project’s WBS so that itcan be compared with cost and productivity informationcollected by the company. Level II should be changedto General Field Administration, Earthwork, ConcreteWork, Masonry Work, Metal Work, Carpentry, and Others.Complete the WBS of this project using this new arrangementfor Level II.XYZ is famous for homemade pizzas which are crisp with thin crust and varied toppings giving the pizzas fabulous tastes. XYZ· is revamping its order processing and pizza-making process. In order to deliver fresh pizza fast, six work elements must be completed as shown in the table below :Element Description Precedence Time (in min)A Receive order - 2·0B Shape dough A 1·0C Prepare toppings A 2·0D Assemble pizza B, C 3·0E Bake pizza D 3·0F Deliver pizza E 3·0Construct a precedence diagram for the process.If the demand is 120 pizzas per night (5:00pm to 1:00am), compute the cycle time for the process. Compute the lead time for the process.What is the theoretical minimum number of workstations needed to achieve the required production?How will you balance the production line to produce and deliver 120 pizzas per night? What is the actual minimum number of workstations needed?
- XYZ Company is a multinational company which exports ladies dresses to European countries. For the month of January, the total ordered quantity amounts to 14,400 pieces and lead time of 5 days is given to the company to finish the goods. Based on the time study conducted by the Senior Industrial Engineer, the standard time for this particular style of ladies dress is 5.0 mins/piece. Being an Industrial Engineer of the same plant, you were given the task to provide your superior of the following information given the additional data below: Salary per person = 400.00/day Working time = 7.5 hours/day Material Cost = 10,000.00 Miscellaneous Cost = 5,000.00 REQUIRED: Compute for the Production Cost 2. GIVEN: WARRANTY COST = P 30,000.00 DEVELOPMENT COST = 40,000.00 PRODUCTION COST = 60,000.00 COMPUTE FOR TOTAL COSTUpdike Upholstery cuts and sews fabric for customordered chairs, ottomans, and sofas. Often, the more com-plicated patterns are for the smaller pieces, where cuttingis more time consuming than sewing. Thus, cutting andsewing times vary. Today’s list of jobs, shown below, arefor an important customer who needs them shipped out(in one shipment) as soon as possible. Determine thesequence of jobs that will complete the customer’s orderas quickly as possible, and notify the customer when theorder is expected to ship.From the perspective of the development of manufacturing support systems, the "Product Management Integration" phase includes all of the following systems EXCEPT: Question 19 options: MRP II (Manufacturing Resource Planning) MRP (Materials Requirements Planning) CL MRP (Closed Loop Material Requirements Planning) LIS (Logistics Information System) Previous PageNext Page