Given an order cost of $100, a, per period holding cost of $.50, and the following requirements schedule: Period 1 3. 4 6. Demand 150 90 60 70 100 60 What is the part-period method lot size for the order for the first period?
Q: What is the difference between a requirements philosophy and a replenishment philosophy of inventory…
A: Philosophy is the study of general and fundamental questions about existence, its knowledge,…
Q: Item X is a standard item stocked in a company’s inventory of spare parts. Each year, the firm uses…
A:
Q: Explain the impact of ignoring carrying cost on the stock size in DRP process ?
A: Distribution Resource Planning or the DRP system - is the method of discovering the requirement to…
Q: Complete the material requirements plan (enter your responses as whole numbers). Week 1 2 4 5 Gross…
A:
Q: Given the following data, calculate the projected available balance and the plannedMPS receipts. The…
A: A master production schedule (MPS) is a schedule for the production of individual goods in each…
Q: Challenge 5: For a given item, suppose these are our net requirements over the coming 6 weeks: Week…
A: given,
Q: Anticipated demands for a four-period planning horizon are 23, 86, 40, and 12.The setup cost is $300…
A:
Q: Project A: Reduction of ordering cost to $18.00. Project B: Reduction of holding cost to $1.50 per…
A: THE ANSWER IS AS BELOW:
Q: Demand for a power steering gear assembly is given by Period 1 2 3 4 5 6 7 8 9 10 Gear…
A: We are using the lot-sizing rule to solve the above given problem. The lot-sizing rule utilized is…
Q: 7. The following were taken from the records of Sauyo Company: Year Cost of Beginning Ending Good…
A: The given data is as follows Cost of goods sold 600700 Average Inventory…
Q: It is Monday morning, and you have just arrived at work. Complete the followingMRP record as it…
A:
Q: A single inventory item is ordered from an outside supplier. The anticipated demand for this item…
A: Given - Demand = (6, 12, 4, 8,15, 25, 20, 5, 10, 20, 5, 4) Starting inventory = 4 Ending inventory =…
Q: The annual demand of Bulldogs Inc. sole product totaled 450,000 units. Due to uncertainty in supply…
A: Given- Annual Demand = 450,000 unitsMax lead time = 2 weeks and 1 day = 14 days + 1 day = 15…
Q: The inventory control models are often labeled independent demand models and MRP is often labeled a…
A: Demand is said to be independent when the demand for one product is not dependent on the demand for…
Q: 2. Suppose demand for a power steering gear assembly is given by Week 1 2 3 4 6. 7 8. 9 10 Demand |…
A: Given: Week 1 2 3 4 5 6 7 8 9 10 Demand 45 65 35 40 0 0 33 0 32 25 Projected on…
Q: a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order…
A: Instructions and formula used: Projected on hand = Planned order receipts + ending inventory…
Q: Based on the following Master Production Schedule, the ATP of the first week is: Week: 1 2 3 4 FC…
A: Given data is Beginning inventory = 145
Q: a. What run quantity should be used to minimize total annual costs? b. What is the length of a…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The requirements of local motor bikes for a company are given as [25,5,25,30, 20] for week 1, 2, 3,…
A: Silver meal heuristic: difference in silver mean and LUC: silver meal caters to average…
Q: Assume that you are the manager of Assembly, Inc. You have just received an order for 40 units ofan…
A:
Q: Quantity of a raw material listed in a purchase order counts as demand when you check the…
A: Inventory management is all about managing the inventory of a company which is the quantity of stock…
Q: A single inventory item is ordered from an outside supplier. The anticipateddemand for this item…
A: Cost comparison of three methods. 1. Silver Meal method Total cost = $ 295 2. Least Unit Cost method…
Q: Suppose we are formulating a Master Production Schedule (MPS) for an item. Week 0 projected on- hand…
A: MPS L4L is done when on hand inventory is lower than the maximum value of forecasted demand and…
Q: Discuss the following statement: “Since we use a rolling production schedule, Ireally don’t need to…
A: The production activities are normally planned over two horizons. The first horizon is a fixed…
Q: Consider the product structure diagram given. Assume that the MPS for the end item for weeks 10…
A: Given information Week 10 11 12 13 14 15 16 17 Net requirement 100 100 40 40 100 200 200 200…
Q: What is meant when we say that the least total cost (LTC) and least unit cost (LUC) methods are…
A: The Least total cost method is based on lot sizing technique which calculates the order quantity by…
Q: tem X is a standard item stocked in a company’s inventory of spare parts. Each year, the firm uses…
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: Economic order quantity (Q*) is 6,000 units. Annual demand (D) is 12,000 units. Find number of…
A: To determine the number of orders we simply divide the total demand (D) of units per year by Q, the…
Q: 1. Which of the following quantities has no effect on the first period’s ATP calculation? a)…
A: ATP relies on a selected MPS, DRP or MRP arrange and is non-cumulative. Changes to on-hand…
Q: Master production schedule (MPS) A kite manufacturer produces the most popular model, the Long kite.…
A: Find the Given details below: Week 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 55 Customer…
Q: Given the forecast and booked orders shown in the table, and a beginning inventory of 0, what is the…
A: Find the Given Details below: Given Details Period 1 2 3 4 Forecasted Demand 100 100 90 90…
Q: The annual demand of Bulldogs Inc. sole product totaled 450,000 units. Due to uncertainty in supply…
A: Normal lead time indicating the average duration between maximum possible lead time demand and…
Q: This question is based on the following information pertaining to material Pogi: Usage 50 – 100 lbs.…
A: The question is related to Inventory Management. 1. Re-ordering level = (Maximum usage per week ×…
Q: requirements over a typical six-month periou are as TUIIOW 1 3. 4. 5. Requirement 750 800 750 600…
A: Find the Given details below: Period 1 2 3 4 5 6 Total Requirement 750 700 800 750 600 900 4500
Q: Company S offers the follow discount schedule for its she Company K orders sheet from
A: Given that: Annual Demand(D) = 100 sheets Carrying cost(I)= 20% Ordering cost (S) = $45 Unit cost…
Q: A single inventory item is ordered from an outside supplier. The anticipateddemand for this item…
A: Part Period Balancing: In this method, we set the order cycle time equal to the number of periods to…
Q: 1. Speedy, Inc. is a company that produces automotive electrical components. AISI is a common part…
A: Answer: Calculation and formula are shown below:
Q: Item X is a standard item stocked in a company’s inventory of spare parts. Each year, the firm uses…
A: The ordered quantity of item X should be 94 units.
Q: A plant manager of a chemical plant must determine the lot size for a particular chemical that has a…
A: Since you have asked multiple questions, we will solve first question for you ( a, b and c). If you…
Q: Given an ordering (setup) cost of $150, a per-period holding cost of $0.25 (per unit), and the…
A: Given data is
Q: Reorder Point Ordering: Average demand per day (7) is 25 units, with a std. dev. of (od) 15 units.…
A: Demand during lead time (DDL): The lead demand (also known as lead time demand) is the complete…
Q: Economic order quantity (Q*) is 4,000 units. Annual demand (D) is 12,000 units. Find number of…
A: Economic order quantity (Q*) is 4,000 units Annual demand (D) is 12,000 units
Q: Master production schedule (MPS) A kite manufacturer produces the most popular model, the Long kite.…
A: Find the Given details below: Week 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 55 Customer…
Q: c. Complete the last three rows of the record by using the POQ lot-sizing rule, with P = 2. (Enter…
A: Material requirements planning (MRP) is an inventory management system that uses a number of…
Q: Item X is a standard item stocked in a company’s inventory of spare parts. Each year, the firm uses…
A:
Q: Inputs Average demand per unit time, D = Lead time, L= 300 SD of demand per unit time, oD = Target…
A: (a) Safety inventory is to cover demand fluctuations during the lead time. The formula to find the…
Step by step
Solved in 2 steps
- A single inventory item is ordered from an outside supplier. The anticipateddemand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5,12. Current inventory of this item is 4, and ending inventory should be 8. Assume aholding cost of $1 per period and a setup cost of $40. Determine the order policyfor this item based onc. Part period balancingA single inventory item is ordered from an outside supplier. The anticipateddemand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5,12. Current inventory of this item is 4, and ending inventory should be 8. Assume aholding cost of $1 per period and a setup cost of $40. Determine the order policyfor this item based ond. Which lot-sizing method resulted in the lowest cost for the 12 periods?It is Monday morning, and you have just arrived at work. Complete the followingMRP record as it would appear Monday morning. Lead time is 2 weeks, and the lotsize is 100. During the week, the following events occur. Enter them in the MRP record.a. The planned order for 100 in week 1 is released.b. Thirty of the scheduled receipts for week 1 are scrapped.c. An order for 30 is received for delivery in week 3.d. An order for 50 is received for delivery in week 6.e. The gross requirements of 70 in week 1 are issued.
- If the the Net Requirement for a product for a particular time period in a MRP problem is 78 and the organization uses a policy of ordering in multiples of 100, what would be the Planned Order Receipt?The inventory control models discussed in Chapters 4 and 5 are often labeledindependent demand models and MRP is often labeled a dependent demandsystem. What do the terms independent and dependent mean in this context?A single inventory item is ordered from an outside supplier. The anticipateddemand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5,12. Current inventory of this item is 4, and ending inventory should be 8. Assume aholding cost of $1 per period and a setup cost of $40. Determine the order policyfor this item based ona. Silver–Meal.
- A single inventory item is ordered from an outside supplier. The anticipateddemand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5,12. Current inventory of this item is 4, and ending inventory should be 8. Assume aholding cost of $1 per period and a setup cost of $40. Determine the order policyfor this item based onb. Least unit costDave’s local college football team is playing for the national championship in next month’s bowl game, and he’s thinking about having “We’re number one” T-shirts imprinted in honor of the team. It’s too late to get the shirts before game day, but if he orders today, he can get them within a few days after the game. The shirts must be ordered in multiples of 1000, and Dave has estimated the amount of profit he will make for possible outcomes of the game. Given the following payoff table, what will Dave do if he uses the maximin criterion? The maximax criterion? The minimax regret criterion? Order no shirts $0 wins $0 loses $0 ties Order 1000 shirts $800 wins $-200 loses $200 ties Order 2000 shirts $1600 wins $-400 loses $300 tiesElectro Fans has just received an order for one thousand 20˝ fans due in week 7. Each fan consists of a housing assembly, two grills and a fan assembly. The housing assembly consists of a frame, two supports and a handle. The following table gives lead times, on-hand inventory, and scheduled receipts. Table 1.1: Lead time and quantity on hand Item Lead Time Qty on hand Lot size# Scheduled receipt 20˝ Fan Housing Frame Supports (2) Handle Grills (2) Fan Assembly 1 1 2 1 1 2 3 80 90 - 50 400 200* 150 - - - 100 400 450 - 50 fan assembly in week 2 * In week 3 it was found that 50% of the on hand inventory of the grills was damaged. # Items without any lot size given should be considered as lot-for-lot. (i) Construct a product structure. (ii) Construct a time-phased product structure. (iii) Prepare a net requirement plan.
- A initially assume that Phi wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using a lot-for-lot (L4L). Gear box requirements Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order release Input shaft requirements Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipt Planned order releaseSemans is a manufacturer that produces bracket assemblies. Demand for bracket assemblies (X) is 125 units. The following is the BOM in indented form: ITEM DESCRIPTION USAGE X Bracket assembly 1 A Wall board 4 B Hanger subassembly 2 D Hanger casting 4 E Ceramic knob 1 C Rivet head screw 3 F Metal tong 4 G Plastic cap 2 Below is a table indicating current inventory levels: Item X A B C D E F G Inventory 22 15 75 24 202 139 1,000 95 What are the Net Requirements for X, A, B, and C respectively?The table below provides demand data for 6 weeks (weeks 31-36 for the current year) for one product. Inventory is managed with a periodic review system where T = 5 weeks and M = 280. The previous order was for 120 units at the end of week 28. The lead time is a constant 4 weeks. At the beginning of week 31 the inventory level is 130 units. Orders are made at the end of a week. 1. When is the next order? end of week __________ 2. How large is the next order? ___________ Week Demand Inventory 31 30 32 40 33 45 34 30 35 30 36 30