a. What is the probability the project will be finished weeks or less? b. What is the probability the project will be finished in 66 weeks or less? c. What is the probability the project will take longer than 65 weeks?
Q: The greater percentage of the project budget is spent in which stage of the project life cycle?…
A: Operation management in an organization aims at providing the highest efficiency possible. It…
Q: 34
A: Since the expected duration is 65 days and the S.D. is 9 days, hence if the value of 80 days is (80…
Q: a. What is the expected completion time of the project? The expected completion time is days. (Enter…
A: Estimated completion time is the time that shows the expected time for completing the project. It…
Q: What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on…
A: The two project performance measurements, that can be used are Sceduled performance index and Cost…
Q: Alfred Korzybski is created with the quote, “The map is not the territory.” How does this quote…
A: The cite “The outline isn't the territory” from Alfred Korzybski, pleasantly summarizes the…
Q: Which of the following is NOT essential for the success of a project? a. Completed by the due…
A: Find the answers below: The Correct answer is e) None of the above
Q: he project manager of Good Public Relations gathered the data shown in the following table for a new…
A: Below is the solution:-
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: the closest answer.
A: b. 15.8
Q: The expected finishing date for the project with 75% probability. * What is the probability of…
A: THE ANSWER IS AS BELOW:
Q: You are managing a project with a total budget of $450,000. According to the schedule, your team…
A: If you want to evaluate how the project is doing with respect to the schedule and budget, you need…
Q: cost records current and accurate?
A: COST RECORD
Q: a. Determine the probability that the project will be completed within 23 days. b. Compute an…
A: THE ANSWER IS AS BELOW:
Q: What is project management, and how is it used to control a project's scope, schedule, and cost
A: SOLUTION: PROJECT MANAGEMENT: Project management is utilization of specific knowledge, skills and…
Q: A project manager discovers that a project problem has occurred. The problem was never discussed…
A: This is a tough situation for any project manager. You’ve got a problem that’s happened, and you…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A:
Q: a) The probability of completing the critical path in 12 weeks (or less), as the client desires.…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: MODELLING AND SIMULATION 1. Is it possible to conduct all the orientation activities in a single…
A: Modeling and simulation (M&S) is the utilization of models (e.g., physical, numerical, or…
Q: Freeze Inc.’s CEO established as a goal for top management to complete the project on or before 22…
A: Activity-on-node is a project management term that leads to a precedence diagramming method that…
Q: Our company, Dawgs “R” Us, is evaluating a new project involving the purchase of a new oven to bake…
A: To calculate the cash flows, NPV, and IRR of the new oven. Cash flows = Operating Cash flows -…
Q: Dan, the project manager, has indicated in a planning meeting that the team should identify and…
A: Project management is the process of effectively utilizing the constraints and controlling a team…
Q: Exercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 ---…
A: There are three possible paths AD = 4+6 = 10 B = 8 CE = 4+7 = 11 Normal project duration…
Q: Calculate the probability that the project can be completed in 50 days or less., Calculate the…
A:
Q: The majority of the project budget is expended upon: Select one: O a. Project termination. b.…
A: A project budget is the total projected costs needed to complete a project over a defined period of…
Q: Find the total cost associated with the project as Data is given in Table 1)
A: Given that: Activity Expected Time Standard deviation Cost A 3 0.3 $2,000 B 2 0.5 $3,000…
Q: A project consists of three tasks: A, B, and C. Task A is known to take five days forsure. Tasks B…
A: Organizations plan numerous things regarding a project. It is because many things are dependent on…
Q: m- the network diagram of one of the projects and its data as in Table No. (4), so if I want to…
A: Below is the solution:-
Q: Actual Costs for a project so far are $50,000, and the Estimate to Complete is $50,000. If a…
A:
Q: Expected length of a project is 37.16 days and the variance of its length is 6.14 days. What is the…
A: Project duration is the total time incurred to finish the project successfully in measured workdays.…
Q: A) What is the critical path B) what is the expected completion time for the project? C) What is the…
A:
Q: Using PERT, Adam Munson was able to determinethat the expected project completion time for the…
A: Formula:
Q: Consider the office renovation project data in Table 7.16. A “zero” time estimate means that the…
A: According to the given information, the critical path is A-C-F. Compute total expected time:
Q: One of the following owns the Project Management Plan (PMP)? The project team. The…
A: A project management plan (PMP) is is a conventional archive that characterizes how a task will be…
Q: One of the following is NOT a part of project management? initiating monitoring…
A: Project management states to use of methods, skill, acquaintance, experience, approaches &…
Q: Project team leader (a) Runs the project day to day (b) supervises the project team (c) carries out…
A: The project team leader is the winner of the project.with different team members in generating and…
Q: Describe the advantages of using probabilistic time estimates in project management
A: A probabilistic recovery time is a forecasting technique that uses three-time estimations to…
Q: The expected number of days to completion for a different project is E(x) = 3.32 The variance of…
A: Given detail: E(x)= 3.32Var(x)= 1.22Fixed cost= $83.783 Variable cost= $9.774 Project cost ( PC)…
Q: Suppose you are a project manager of a power plant project and there is a penalty in your contract…
A: Find the Given details below: Given details: Sub Contractor A Sub Contractor B Bids…
Q: Compute the expected time and variance for each activity. What is the critical path and the expected…
A: Answer a Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time=…
Q: Given a project with the following characteristics, answer the following questions: You are the…
A: Given- No. of birdhouses to built = 20 Earned value (EV) = 20×100= $2000 CPI = 0.9091 Actual cost…
Q: A project has the following tasks and duration estimates given. These three tasks are done in…
A: Assuming a beta distribution for project activity time estimates we get the expected duration…
Q: Constraints are those factors that can limit a project. Which of the following are considered…
A: Project management is the management that requires a unique type of skills processes resources and…
Q: The amount of capital spent to get the project going a) Revenue b) Initial cost outlay c)…
A: ANSWER: OPTION (A) is the correct answer. REASON: Revenue is the addition of profit and cost that…
Q: We are planning to develop a room reservation system that is estimated to have 400 story points of…
A: It is very important for organization to take such steps that are helpful in the success of the…
Q: i). Calculate the expected time for each activity ii. Draw a Gantt Chart from the same…
A: given,
Q: You are the project manager of a project that has $142590 as the budget at completion. 65% of the…
A: Given that: Budget at Completion (BAC)= $142590 Actual Cost (AC)= $78352 Planned Value (PV)= 65% of…
Q: Given an activity's optimistic, most likely, and pessimistic time estimates of 6,7 and 14 days…
A: Energetic movement – The performing of an assignment, recorded when taken to do as such and the…
Project management is the management in which different types of knowledge and skills are needed to produce valuable products or services for customers.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)A company is considering either (1) purchasing equipment for use on a new project (purchase cost = $5,000; purchase variable cost = $50 per day) or (2) leasing this equipment from a vendor at a rate of $100 per day. An initial analysis determined that the “purchase” option break-even point is 100 days. Based on this analysis, the company should Lease the equipment if the expected project is expected to last more than 100 days Purchase the equipment if the expected project is expected to last less than 100 days Purchase the equipment if the expected project is expected to last more than 100 days No answer text provided.An engineer failed to finish its building construction contract on time. With this, a penalty of P10,000 will be paid for each day that passes beyond the date of contract. According to the engineers estimate, if the construction will continue with the same number of workers, the project will be finished 30 days after the contract date. But the engineer also has an option of hiring more workers to hasten the construction process. Every additional worker, the engineer has to pay P3,000 per day and every 3 additional workers the construction period will be lowered down by 1 day. But, the engineer can only hire 21 workers. If you are the engineer, what method are you going to follow so as to incur a lesser amount of extra construction cost? Just pay P10,000 per day for 30 days? Or just hire additional workers to lower down the construction time?
- A building contractor has a contract that will expire in 40 days. He has 80 men on the job and can finish the job in 50days. The wage per day of 40 men is P500 each and the other 40 men is P300, each for 8 hours work per day. The fine for the delay in the work is P10,000 per day. a.How many more men should the contractor add in order to complete the work on time? b.Assuming that the additional men to be added will be paid P400 per day, will the contractor save money by employing enough men to complete the work on time or by not adding more men and paying the fine? How much is the savings, if any? Note: No overtime work is permitted1.16 Given an auditing project with the following activities, please refer to the first pic find:(a) The probability of completing the critical path in 12 weeks (or less), as the client desires. (b) The probability of completing the critical path in 13 weeks (or less). c) The probability of completing the critical path in 16 weeks (or less), the client’s drop-dead date.(d) The number of weeks required to assure a 92.5 percent chance of completing the critical path, as guaranteed by the auditing firm.Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- A project has a critical path with a duration of 20 weeks and a standard deviation of 4 weeks. There is a 35% chance the project will be completed in X weeks or less. What is X? Select the closest answer. a. 18.4 b. 15.8 c. 21.6 d. 24.2 e. 19.7One of Mary's employees, Shira, has obtained a new job and given her two weeks' notice. Shira was responsible for updating the company website with information on the new bag policy. Mary gave Shira's responsibilities to another employee in the Marketing department who has similar knowledge and skills.What is the probability of this risk occurring and what is the impact on the project? a.) Low probability and medium impact b.) High probability and high impact c.) Medium probability and low impact d.) High probability and low impactThe Budget at Completion (BAC) is the sum of all budgeted values established for the work to be performed on a project. As such it is equivalent to: Select one: a. the total planned value of the project. b. the total earned value of the project. c. the total actual cost of the project. d. the total value of the work completed to date
- A building contractor has a contract which will expire in 30 days. He has 80 men on the job and can finish the job in 50 days. The wage per day of 40 men is P6.00 each and that of the other men is P4.00 each for 8 hours work per day. The fine or liquidated damages for delay in the work is P100.00 per day. How many more men should the contractor add in order to complete the work on time? Assuming that the additional men to be added will be paid P6.00 per day, will the contractor save money by employing enough men for him to complete the work on time or by not adding more men and paying the fine? How much is the savings, if any? No overtime work is permitted.9. Dana is 30 years old and owns a wedding planning business. She takes care of all wedding events details from arranging flowers, tables, theme to catering food to a high standard. She has a good reputation in the market. Recently, she discovered another food catering company with wider varieties and lower prices that her customers will love to have. Thus, she decided to write a negative letter to the current catering company to inform them about terminating their business together. Dana has to plan her negative letter very carefully and to explain the needs of her customers: * A.to avoid responsibility for the message B.to improve future performance on the part of the sender C.to avoid adding a personal message to the recipient D.to gain control of the context of the message E.to minimize damage to the business relationshipA project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)