Assignment 2: The details of the project network are given in table below, if indirect cost is 150 $/week determines: 1- Draw the project network, find the critical path and the project completion time. 2-2- Calculate the total cost of the project with a time of 24 weeks Activity Normal duration 4 (weeks) Normal cost (*1000$) Crash duration (weeks) Crash cost (*1000$) 1-2 2-3 2-4 2-5 5 500 100 3 4 750 2 2 200 600 2 300 200 4 3-6 4-8 5-7 6-9 4 7 4 6 700 5 200 3 760 830 300 140 5 200 200 2 7-8 8-9 2 80 2 300 80 1 100 1 100 9-10 7 600 6 670

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Assignment 2:
The details of the project network are given in table below, if indirect
cost is 150 $/week determines:
1- Draw the project network, find the critical path and the project
completion time.
2- 2- Calculate the total cost of the project with a time of 24 weeks
Activity
Normal duration 4
(weeks)
Normal cost
(*1000S)
Crash duration
(weeks)
Crash cost
(*1000S)
1-2 2-3 2-4 2-5
2
4
500 100
3
2
750 300
200
2
200
5
er
4
3-6
600 700
760
6
5
830
4-8 5-7 6-9 7-8 8-9
4
7
1
200
3
140
5
300 200
4
200
2
300
2
80
2
100
1
80 100
9-10
7
600
6
670
Transcribed Image Text:Assignment 2: The details of the project network are given in table below, if indirect cost is 150 $/week determines: 1- Draw the project network, find the critical path and the project completion time. 2- 2- Calculate the total cost of the project with a time of 24 weeks Activity Normal duration 4 (weeks) Normal cost (*1000S) Crash duration (weeks) Crash cost (*1000S) 1-2 2-3 2-4 2-5 2 4 500 100 3 2 750 300 200 2 200 5 er 4 3-6 600 700 760 6 5 830 4-8 5-7 6-9 7-8 8-9 4 7 1 200 3 140 5 300 200 4 200 2 300 2 80 2 100 1 80 100 9-10 7 600 6 670
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.