Assume you are managing a one-year project and have listed the project earned management value as below. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $25,000 EV = $22,000 AC = $27,000 BAC = $122,500 Review the project and answer the following to find your project status. a. Calculate the following for the project. i. Cost variance ii. Schedule variance iii. Cost performance index (CPI) iv. Schedule performance index (SPI) b. Discuss the project status whether it is ahead of schedule or behind schedule and whether it is under budget or over budget. c. Use the CPI to calculate the estimate at completion (EAC) for this project.
Assume you are managing a one-year project and have listed the project earned management value as below. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $25,000 EV = $22,000 AC = $27,000 BAC = $122,500 Review the project and answer the following to find your project status. a. Calculate the following for the project. i. Cost variance ii. Schedule variance iii. Cost performance index (CPI) iv. Schedule performance index (SPI) b. Discuss the project status whether it is ahead of schedule or behind schedule and whether it is under budget or over budget. c. Use the CPI to calculate the estimate at completion (EAC) for this project.
Managerial Economics: A Problem Solving Approach
5th Edition
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Chapter5: Investment Decisions: Look Ahead And Reason Back
Section: Chapter Questions
Problem 5MC
Related questions
Question
QUESTION TWO (2)
Assume you are managing a one-year project and have listed the project earned management
value as below. Note that PV is the planned value, EV is the earned value, AC is the actual cost,
and BAC is the budget at completion.
PV = $25,000
EV = $22,000
AC = $27,000
BAC = $122,500
Review the project and answer the following to find your project status.
a. Calculate the following for the project.
i. Cost variance
ii. Schedule variance
iii. Cost performance index (CPI )
iv. Schedule performance index (SPI)
b. Discuss the project status whether it is ahead of schedule or behind schedule and whether it
is under budget or over budget.
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project
performing better or worse than planned?
d. Use the SPI to estimate how long it will take to finish this project.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Recommended textbooks for you
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning