bama pie company's assembly line operations (the assembly line operates for six hundred minutes per day) comprise of eleven tasks, with the longest task time being 2.4 minutes and the shortest task time being 0.4 minutes; the sum of the task times is eighteen minutes. the firm is working on balancing its assembly line operations. the firm needs to produce 200 pies per day; to achieve this, the firm calculates the required cycle time as ---- minutes?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

bama pie company's assembly line operations (the assembly line operates for six hundred minutes per day) comprise of eleven tasks, with the longest task time being 2.4 minutes and the shortest task time being 0.4 minutes; the sum of the task times is eighteen minutes. the firm is working on balancing its assembly line operations. the firm needs to produce 200 pies per day; to achieve this, the firm calculates the required cycle time as ---- minutes?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,