Below is the network diagram from a project: B(2) D(5) A(2) F(3) C(5) E(3) What is the slack for activity C? Your answer will be a whole number.
Q: Discuss how a property manager would make use of a Fit Out Guide to control the tenants’ works in a…
A: Fit out guide is a handbook that provides relevant guidelines about the approval procedures and…
Q: What are the key decision criteria used in decision making under uncertainty. Briefly explain each…
A: Decision-making under uncertainty refers to a decision dilemma in which a decision-maker is…
Q: What do you mean by automation in the workplace
A: Automation is a wide term that may be applied to contemporary workplaces in a variety of ways.…
Q: What
A: Streamlining is a process of improvement of the proficiency of a specific cycle inside an…
Q: oesn't get too high, what can a system designer do? Expert opinions can be very important for a lot…
A: Reduce Short Term Memory Load
Q: CREATE A GANTT CHART USING THESE SCHEDULED TASK:
A: Task Start End Excavation 2/23/2022 2/23/2022 Backfill 3/7/2022 3/11/2022 Reinforcing…
Q: Demonstrate knowledge of the application of decision-making tools and approaches for various…
A: The decision making tools and approaches for various problems in business and management are, 1.…
Q: Explain the seven major warehousing activities.
A: Warehouse is a large empty space where raw materials or even the other manufactured goods are sored…
Q: Asking what factors affect stakeholders?
A: Stakeholders are the parties who have direct interests in the profitability,operation,sales and…
Q: The optimum solution is: Number of air conditioners to be produced Number of heaters to be produced…
A: Decision variables: x = Number of air conditioners producedy = Number of heaters produced…
Q: Define functional, matrix, and project organizations. Explain how each structure impacts project…
A: A functional organization is where the organization is organized into functional divisions primarily…
Q: Give an example of a project and determine the constraints as to time, scope, cost, risk, quality,…
A: Project limitations are restricting components that can influence the quality, conveyance, and…
Q: is known to have low risk and low control. is then the concept of this exchange between people or…
A: Supply chain management - is the managing of the flow of products & services it includes all…
Q: How can I create a project network?
A: A project network diagram that is displayed in a graphical way. It shows the interdependencies of…
Q: Give an example of a company that had employees lie on their employee engagement surveys to fake…
A: ANSWER : Employee engagement surveys may not get you a clear data :Unfortunately, your staff may not…
Q: Starbucks buying coffee from locations like Colombia and Guatemala is an example of
A: As per Bartleby's guidelines, I have solved the first question because multiple unrelated questions…
Q: Why is it important to follow the proper workflow steps for coding and billing?
A: Medical coding is the process where the medical reports are sent to coders from doctors. The medical…
Q: Problem: For the information below, first draw the network diagram and determine how long the…
A: Possible paths and duration: A-C-F = 12 B-D-F = 15 B-E = 13 The project will take 15 days to…
Q: Calculate the missing values and express the answers rounded to two decimal places. Rate of Amount…
A: Given, Profit = $340 Overhead expenses = $255 Rate of Markup on cost = 18%
Q: what are mergers and acquisitions in companies?
A: A merger is a corporate strategy to combine with another company and operate as a single legal…
Q: The entrepreneur explore opportunities. Discuss
A: In the entrepreneurial process, opportunity exploitation is a vital phase in developing a successful…
Q: Discuss the components of Quality of Work-Life according to Walton (1975).
A: Quality of work-life often called QWL can be stated as the total quality of the work-life of an…
Q: A decision maker's worst option has an expected value of $1,000, and her best option has an expected…
A: Formula:- The expected value of perfect information= Expected value with perfect information -…
Q: 1. Alpha Team received an assignment from the Company to work on a bridge construction project. Budi…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES =…
Q: According to the signaling theory of education, The level of education or training of one worker…
A: The signalling theory as developed by Spence (1973) starts from the following hypotheticals (i)…
Q: Identify and describe the major deliverables included in a Project Closure step?
A: A project possess a definite beginning and definite end. Once the project is completed, it has to be…
Q: A firm making snowblowers produces the augers for each snowblower in batches. Annual demand is for…
A:
Q: Maintaining a security perimeter is an important part of an organization’s plan to keep operating at…
A: Perimeter security is a system installed in an organization which is used in finding out threats…
Q: What is a need for a system in terms of functionality? What types of needs may be categorized into…
A: Needs are essential ways on the road that states to a good project. They set up a formal agreement…
Q: weakness of diversity at workplaces Plz do fast
A: Workplace diversity definition Diversity in the workplace is widely thought to be one of the keys…
Q: Discuss the rules for drawing networks and illustrate the above by drawing its network.
A: Project network is a visual representation of project activities and their duration to complete the…
Q: What is meant by ergonomics and how it can relate to quality of work life.
A: To be determined: what is meant by ergonomics and how it can relate to quality of work life.…
Q: What is suboptimization?
A: Operations management helps in creating the highest possible efficiency level in an organization by…
Q: Product Design In 1945, a rare and curious Volkswagen car was shipped from its bomb-damaged German…
A: given, Product Design In 1945, a rare and curious Volkswagen car was shipped from its bomb-damaged…
Q: What is the importance of manpower in operating a business?
A: Manpower planning is nothing but the basic dealing with the coordinating, encouraging or motivating,…
Q: Gainesville Cigar stocks Cuban cigars that have variable lead times because of the difficulty in…
A:
Q: What is upstream management? What isdownstream management?
A: Upstream management and downstream management are two ways of structuring your employees,…
Q: Activities/Assessments: Activity 12: Individual Given the activities of a project; their optimistic…
A: Note: - As specified in the question to answer question 4 only. We will answer question number 4…
Q: It is the physical output of the whole production process A. Prototype B. Product C. Business…
A: The production process is the process in which raw materials and resources are transformed into…
Q: What are some factors that influence employee work performance and productivity?
A: Employee is an integral part of the business and without them it's impossible for organisation to…
Q: What are the organizational implications of introducing e-procurement?
A: It is a B to B process and is helpful in purchasing, ordering etc of the goods on online platform.…
Q: How can managers adapt to each impact that revolves around their organization?
A: Managers are the key to an organisational success and a successful manager is person who has great…
Q: A company wants to produce hardware at a level rate and send 10 units to inventory. If their 6-month…
A: Forecasted demand = 110 units Inventory = 10 units Forecast months = 6
Q: Cycle counting is method of maintaining the accuracy of a company’s inventories using a sampling…
A: Cycle counting is method of maintaining the accuracy of a company’s inventories using a sampling…
Q: State mistakes are managers prone to make in the process of building a performance system?
A: State mistakes are managers prone to make in the process of building a performance system?
Q: What is adaptive Supply Chains? Discuss the future trend of Collaborative between Supply Chain and…
A: Adaptive supply chains are changing the way companies plan, execute, monitor, and control the flow…
Q: Outline some general control strategies that can reduce the number and seriousness of workplace…
A: Workplace injuries are an important matter of concern of every kind of firm whether small or large.…
Q: The Safe Zone Restaurant, a 24-hour restaurant, faces changing requirements from hour to hour. More…
A: As per the first-hour principle, the workers are added in the first hours of their duties to meet…
Q: Your supervisor wants you to work overtime every week, but you have other commitments outside of…
A: Overtime refers to a condition in which the employee performs extra hours than their usual hours of…
Q: SCRUM environments usually make use of team consultants to optimize the team’s performance. Briefly…
A: Team consultant: As the name itself speaks, a team consultant is a highly specialized subject matter…
Step by step
Solved in 2 steps with 3 images
- Use the following information in a table about the activities of an information technology project of ABC Bank and solve the given questions. Activity Activity Predecessors Time Estimate/Duration (days) ES EF LS LF Slack time A B C D E F -- A A B B, C D, E 4 5 6 5 3 7 Draw a network diagram. List all the paths and their durations Find the critical path. Calculate early start, early finish, late start and late finish Calculate the slack time of each activityConsider the activities, duration, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity Description Immediate Predecessors Optimistic weeks Most likely Weeks Pessimistic Weeks A - 4 7 10 B A 2 8 20 C A 8 12 16 D B 1 2 3 E D, C 6 8 22 F C 2 3 4 G F 2 2 2 H F 6 8 10 I E, G, H 4 8 12 J I 1 2 3 What is the expected time for activity B What is the variance for activity B Based on the calculation of estimated times, what is the critical path What is the estimated time of the critical path What is the activity variance along the critical pathA project is represented by the following diagram: 2. The critical path for the network shown is: A. 1-3-6-7. B. 1-2-4-7. C. 1-4-7. D. 1-3-4-7. E. 1-2-5-7.
- .Find the project details in the below table, draw the network activity diagram and identify the critical path for the project. Activities Predecessors Time duration A - 3B A 5C A 4D B 6E B, C 7F D, E 4The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity Activity Time (daydays) Immediate Predecessor(s) A 77 long dash— B 44 A C 55 A D 55 B, C E 55 D F 33 E G 55 E Part 2 a. Choose the correct network diagram for this project. StartFinishA7B4C5D5E5F3G5 In the diagram, there are 2 rectangles. The one on the left is labeled Start, and the one on the right is labeled Finish. There are 7 circles labeled inside the circle using the letters from A to G. There is a number below the letter inside each circle. There are arrows that indicate the flows through the circles from Start to Finish as follows: Rectangle Start has an arrow that connects to circle A 7, circle A 7 connects to…(a) The critical path for the network activities shown below is? (b) What is the completion time in weeks? Refer attached image Activity Preceding Time A - 8 B - 10 C A , B 5 D B 8 E C , D 6
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?* answer D" For the following situation draw a PERT network, and determine the following: a- Critical path b- ES,LS,EF,LF and slack time for each activity Activity Immediate predecessor(s) Optimistic time Most probabl time Pessimistic time Crashing cost/day $$ Minimum expected completion time A 1 1 1 900 1 B A 3 6 8 400 2 C A 4 5 6 700 3 D A 2 3 4 800 3 E A 9 9 15 F B 7 8 8 300 5 G B 4 7 9 500 3 H C 1 3 9 700 3 I D 5 6 7 J F,G,H 3 4 8 1100 2 K H,I 2 3 7 650 3 L H,I 7 7 8 300 4 M D 8 9 15 N M 10 15 17 1400 7 O M 3 6 9 600 4 P D 6 12 13 550 7 Q M 8 9 12 980 4 R P,Q 3 6 7 S O,R 7 8 12 T J,K,L,N 6 7 12 520 5 U J,K…Construct the network for the following project and determine the following i) Critical Path ii) ES,EF,LS,LF
- This was a three part question. Bartelby helped me get A and B. The picture for Part A is the network diagram and Part B's answer is below for the critical path. My question I need to answer is Part C which is in the second picture. Part B There are the following paths in the project network. A –> B –> D –> G –> J = 2 + 4 + 2 + 3 + 7 = 18 A –> B –> E –> G – >J = 2 + 4 + 1 + 3 + 7 = 17 A –> B –> F –> H –> J = 2 + 4 + 8 + 5 + 7 = 25 A –> C –> F –> H –> J = 2 + 5 + 8 + 5 + 7 = 27 A –> C –> F –> I –> J = 2 + 5 + 8 + 4 + 7 = 26 The longest path in all the possible paths of the project network is A –> C –> F –> H –> J with the longest time. Therefore, the project duration is 27 days.SUBJECT: SOFTWARE ENGINEERING For a particular project, consider following list of Activities, their duration in Days and their Predecessor Activity Days Precedents a 3 - b 15 A c 5 A d 60 A e 6 D f 40 B g 10 c, e h 7 F i 6 G j 12 h, i By using network schedule technique, draw a Network Diagram of above enlisted activities. Find Critical Path , earliest start, earliest finish , latest start and latest finish from Network Diagram.Construct the network for the following project and determine the following i) Critical Path ii) ES,EF,LS,LF iii) TF,FF