Capital Budgeting Methods Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive? Calculate the two projects' IRRs. Do not round intermediate calculations. Round your answers to two decimal places. Project S:   % Project L:   % Which project would be selected, assuming they are mutually exclusive? Calculate the two projects' MIRRs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to two decimal places. Project S:   % Project L:   % Calculate the two projects' PIs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to three decimal places. Project S : $ Project L : $

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 10P: Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year...
icon
Related questions
Question

Capital Budgeting Methods

Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years.

Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent.

Project S: $  

Project L: $  

Which project would be selected, assuming they are mutually exclusive?

Calculate the two projects' IRRs. Do not round intermediate calculations. Round your answers to two decimal places.

Project S:   %

Project L:   %

Which project would be selected, assuming they are mutually exclusive?

Calculate the two projects' MIRRs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to two decimal places.

Project S:   %

Project L:   %

Calculate the two projects' PIs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to three decimal places.

Project S : $

Project L : $

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Fundamentals of Financial Management, Concise Edi…
Fundamentals of Financial Management, Concise Edi…
Finance
ISBN:
9781305635937
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Fundamentals Of Financial Management, Concise Edi…
Fundamentals Of Financial Management, Concise Edi…
Finance
ISBN:
9781337902571
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning