Consider the following work breakdown structure: Activity Start A B C UDEF Precedes A,B C,D D E TIM F F End Time Estimates (days) Most Likely Pessimistic Optimistic 44 45 42 31 27 58 50 60 45 40 36 70 What is the estimated expected (mean) time for activity E? 56 75 48 49 39 82

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Consider the following work breakdown structure:
Activity
Start
A
BUDEE
с
F
Precedes
A, B
C,D
D
E
TIM
F
F
End
Time Estimates (days)
Most Likely
Optimistic
44
45
42
31
27
58
50
60
45
40
36
70
What is the estimated expected (mean) time for activity E?
Pessimistic
56
75
48
49
39
82
Transcribed Image Text:Consider the following work breakdown structure: Activity Start A BUDEE с F Precedes A, B C,D D E TIM F F End Time Estimates (days) Most Likely Optimistic 44 45 42 31 27 58 50 60 45 40 36 70 What is the estimated expected (mean) time for activity E? Pessimistic 56 75 48 49 39 82
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.