Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds from Node 1 to Node 8. (Note that you can easily change this table to create multiple exercises.) a. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path. c. What is the critical path for this project and how long is it? d. What is the shortest possible time needed to complete this project?

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.1SC: Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing...
icon
Related questions
Question

Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network
proceeds from Node 1 to Node 8. (Note that you can easily change this table to create
multiple exercises.)
a. Draw an AOA network diagram representing the project. Put the node numbers in circles
and draw arrows from node to node, labeling each arrow with the activity letter and
estimated time.
b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8
as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time needed to complete this project?

TABLE 6-3 Network diagram data for a large project
Activity
Initial Node
Final Node
Estimated Duration
A
1
10
B
1
3
12
C
1
4
D
3
4
E
5
8.
F
3
4
6.
G
4
5
4
H
4
6.
8.
I
6.
6.
J
5
8.
12
K
7
8
L
7
8.
10
Transcribed Image Text:TABLE 6-3 Network diagram data for a large project Activity Initial Node Final Node Estimated Duration A 1 10 B 1 3 12 C 1 4 D 3 4 E 5 8. F 3 4 6. G 4 5 4 H 4 6. 8. I 6. 6. J 5 8. 12 K 7 8 L 7 8. 10
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning