1. Compute the most probable or mean time, t. Indicate your answers in the table above. 2. Construct the Network Diagram. Determine the Early Start and Early Finish of each of the activities. Determine the total duration of the project.
Q: Construct a network diagram for this project?
A: Find the Duration Calculation below:
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A:
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: The Figure 1 below shows the activities on the nodes, while the table shows the normal time, crash…
A: There are two separate paths. The duration of the paths is: Start–A–B–F–End = 18 days…
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Activity Description Preceded bDy Time (WKS) Feasibility Study Estimate production volumes Market…
A: i) the AOA format, the possible path activities would look like:
Q: a) Create an activity network diagram that shows the sequential logic the project tasks. b) Identify…
A: The critical path method (CPM) is a method for determining schedule flexibility and identifying…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: a. Determine the expected activity completion times, te. b. Identify the critical path. c. What's…
A: The first four subparts (a), (b), (c), and (d) are answered below.
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: From the network diagram, The possible paths and their duration are: A-D-G-H = 3+3+1+3 = 10B-E-F =…
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde…
A: 3.8) Given Activity Immediate Predecessor(s) Time(Days) A ______ 2 B ______ 5 C ______ 1…
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given data is
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A: a. The network diagram is as follows:
Q: [6 marks] Carefully draw an AON network diagram for the project, and perform both the forward and…
A: THE ANSWER IS AS BELOW:
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: a. Determine the expected time (t,) for each activity. 5. Identify the critical path(s) c. What is…
A: Answer is as below:
Q: Table 1 Activities Immediate Predecessors Time (In Days) A 9. -- В A C A 9. B,C 6. E В, С 7 F 10 G E…
A:
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the…
A: Given that, Activity Description Duration (days) 1 Building Road to the site 6 2 Materials…
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: 4. Using below data for an army practice : A. Construct a project network B. Determine the length or…
A: A project network diagram gives the sequential and logical relationship between various task…
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A:
Q: a. Develop a network diagram for the project using AON convention. b. Determine the project…
A: Here, in the question, we have the activity id, a description of each activity, immediate…
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: The diagram in Figure was developed for the project launch of Kitty Condo, a new product in the…
A:
Q: Answered all given questions as below. Value for A and B will be determined by your unique id as per…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: PERT-CPM 1. Consider a project involving the following activities and precedence relationship. The…
A:
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: Crash the project until no more crash can be performed How much it would cost The new critical…
A: Proect crashing is one of the techniques used in the calculation of the duration of the critical…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: Project Evaluation and Review Technique (PERT) may be a technique utilized in project management…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: 4. For each of the following network diagrams, determine both the critical path and the expected…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent,…
A: Below is the solution:-
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Construct a network diagram b. State the expected finish time and critical path of the project
A: A network diagram is a graphical representation of a project which visualizing the activity…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: G E, F 6. 11 16 a. Construct the PERT network diagram for this project. b. Compute the mean and…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Step by step
Solved in 2 steps with 7 images
- Jabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the projectand identify the activities that neeD to be prioritised by the project manager. (Nodiagram is required) TABLE- PROJECT INSTALLATION Activity Predecessor optimistic Most Likely Pessismistic Estimated time A - 4 7 10 7 B - 2 9 10 8 C A,B 2 5 8 5 D C 16 19 28 20 E C 6 9 24 11 F E 1 7 13 7 G C 4 10 28 12 H D,F 2 5 14 6 I G 5 8 17 9 J H,I 2 5 8 5The project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistakeThe VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 5
- This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc. PERT Formula: TE = (O + 4T + P) / 6 TE = Pert Expected Time Duration, O = Optimistic estimate, P = Pessimistic estimate, T = Most Likely (Typical) estimate Activity Predecessor Optimistic Most Likely Pessimistic Duration Duration in Weeks A — 2 3 4 B — 4 5 7 C B 1 2 3 D C & E 0.5 1 1.5 E B 0.5 1 1.5 F C 2 3 4 G F 2 3 4
- Follow up to previous question: 3) A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 Questions: 1) What method should be used? Compute the mean and variances for each activity and add them to the table above. 2)Draw the project network and label the arcs with the activity name. 3) Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. 4) Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.Critically assess and comment on the success of the project from the followingviewpoints aline with a project To enhance Sports development by providing assistance to sports clubs and teams in St. Catherine North Central by providing them with the necessary gears and equipment for whichever Sporting disciple that they may part-take in. a. Level or degree of alignment of end results and outcomes to the organization’sstrategic goals.b. Level of success in the management of the triple constraints of time, cost, andscope.This was a three part question. Bartelby helped me get A and B. The picture for Part A is the network diagram and Part B's answer is below for the critical path. My question I need to answer is Part C which is in the second picture. Part B There are the following paths in the project network. A –> B –> D –> G –> J = 2 + 4 + 2 + 3 + 7 = 18 A –> B –> E –> G – >J = 2 + 4 + 1 + 3 + 7 = 17 A –> B –> F –> H –> J = 2 + 4 + 8 + 5 + 7 = 25 A –> C –> F –> H –> J = 2 + 5 + 8 + 5 + 7 = 27 A –> C –> F –> I –> J = 2 + 5 + 8 + 4 + 7 = 26 The longest path in all the possible paths of the project network is A –> C –> F –> H –> J with the longest time. Therefore, the project duration is 27 days.
- General Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000To be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeksJordanne King, the project manager for Webjets International, Inc., compiled a table showing time estimates for each of the activities of a project to upgrade the company’s Web page, including optimistic, most likely, and pessimistic.a. Calculate the expected time, te, for each activity.b. Calculate the variance, s2, for each activity.Activity Optimistic (days) Most Likely (days) Pessimistic (days)A 3 8 19B 12 15 18C 2 6 16D 4 9 20E 1 4 7