Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in its manufacturing operation from a variety of different suppliers. One particular supplier provides a part where the assumptions of the EOQ model are realistic. The annual demand is 5000 units, the ordering cost is $80 per order, and the annual holding cost rate is 25%. a. If the cost of the part is $20 per unit, what is the economic order quantity? b. Assume 250 days of operation per year. If the lead time for an order is 12 days, what is the reorder point? c. If the lead time for the part is seven weeks (35 days), what is the reorder point? d. What is the reorder point for part (c) if the reorder point is expressed in terms of the inventory on hand rather than the inventory position?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in its manufacturing operation from a variety of different suppliers. One particular supplier provides a part where the assumptions of the EOQ model are realistic. The annual demand is 5000 units, the ordering cost is $80 per order, and the annual holding cost rate is 25%.
a. If the cost of the part is $20 per unit, what is the economic order quantity?
b. Assume 250 days of operation per year. If the lead time for an order is 12 days, what is the reorder point?
c. If the lead time for the part is seven weeks (35 days), what is the reorder point?
d. What is the reorder point for part (c) if the reorder point is expressed in terms of the inventory on hand rather than the inventory position?
Trending now
This is a popular solution!
Step by step
Solved in 3 steps