Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 48 B 4 22 52 C 1 30 70 D 10 14 28 E 7 12 56 F 5 20 62 Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule. Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule. Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 48 B 4 22 52 C 1 30 70 D 10 14 28 E 7 12 56 F 5 20 62 Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule. Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule. Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
Related questions
Question
Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table.
Job |
Time Since Order Arrived (days ago) |
Processing Time (days) |
Due Date (days from now) |
A |
6 |
18 |
48 |
B |
4 |
22 |
52 |
C |
1 |
30 |
70 |
D |
10 |
14 |
28 |
E |
7 |
12 |
56 |
F |
5 |
20 |
62 |
- Develop a
schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule. - Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule.
- Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,