A custom motor cycle shop is experiencing high demand from its customers for its services. The owner performs all tasks relating to customization. Assume each customer brings one motor cycle for customization. The owner needs to determine if he needs to add more help to meet customer demand. A week has 40 hours (maximum amount of time available for the owner to work) . The maximum number of customizations that can be done per week is 8 bikes ( if there is no wasted time ). The following is the data collected from observations for a typical week: Every Friday the shop is cleaned by the owner. This takes 5 hours 15 % of the customization needs rework which takes 75 % more time than regular customization 15 % of the customers will be called by the owner to reschedule completion by the owner. This takes 2 hours per customer. Determine OEE. How should the owner handle the business ? Show all formulas, calculations and results.
Q: What is the main purpose of the Product Structure Tree?
A: Product structure tree is a hierarchical classification of items that are required to form a…
Q: A) What is the critical path B) what is the expected completion time for the project? C) What is the…
A:
Q: Your firm uses the continuous review system to manage a product, and operates 52 weeks a year. The…
A: Given data: Ordering cost = $ 40/order weeks operational (D)= 52 weeks Holding cost = $5 per…
Q: Draw a diagram that illustrates all phases of the business process life cycle and their key…
A:
Q: When crashing a project, the general guideline is to concentrate on the path with? a. The least…
A: A project crashing is the process of reducing the total duration of the project completion based on…
Q: What characteristic(s) of the critical path times makes them critical? What two factors are compared…
A: Critical path activities are those that, if delayed, will cause the project's completion to be…
Q: To what extent can firms be expected to extend their workplace responsibilities to employees in…
A: Workplace responsibility is described as responsibilities imparted to the employees which include…
Q: Determine the maximin and minimax strategies for the two-person, zero-sum matrix game. 45-1 The row…
A:
Q: Machines Jobs 1 3 Р 50 P 70 P 90 140 100 120 3 150 130 160 1.
A: The question is related to Assignment Problem. The Problem is solved to Hungarian Rule.
Q: Operating decisions can include: A.measuring performance against benchmarks B.deciding whether to…
A: Operational decisions are also called operating decisions, these decisions are made to handle…
Q: Given the following MRP matrix for Item D, the planned order receipt for period 4 is ITEM: D Period…
A: An MRP table helps to plan the ordering process and manage the receiving process of materials. The…
Q: For the following data, construct a fraction defective chart by using 3 sigma. Is the process under…
A: P chart is a model of control chart which helps to identify the process controllability with a…
Q: Strategic Supply Chain Question (a) What is the bullwhip effect, what are the main causes of the…
A: Supply chain management - is the oversight of the flow of products & services & it…
Q: 1- What may be the main factors considered in such layout from your study of layout principles 2-…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: In quality assurance, we use P-charts for discrete defects when there can be more than one defect…
A: Quality is the ability to manufacture the products and services as set standards and increase…
Q: Describe how your mastery of project management and the concepts in this textbook will enhance at…
A: The three employability skill that can mastery the project management concepts are:
Q: (d) A company has three factories. Each factory produces three different products (A, Band C).…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: 7. A bank uses a certain form at a uniform rate of 60 pads per week during each of the 52 weeks per…
A: Since you have submitted a question with multiple subparts, as per the guideline we have answered…
Q: Analyse the advantages and disadvantages of using process layout in a manufacturing plant. Provide…
A: Process layout is the layout of the plant that helps the business to increase efficiency by…
Q: What combination of abilities is appropriate for the job of your dreams? Do you possess those…
A: In order to carry out a job in the company, an individual must have enough expertise, knowledge, and…
Q: Green Carpet Inc. produces and markets different products for lawn care. Two well known fertilizers…
A: Part (A): Decision Variables:Suppose-X1 be the per kg production of fertilizer U-SmileX2 be the…
Q: ACME Corporation is developing a new innovative product. To launch the product, monthly fixed costs…
A: The Break-even point is the point at which the production cost and production revenue of an…
Q: The production process shown below consists of five stages. The numbers in parentheses are the times…
A: a.
Q: Please fill out this simple chart
A:
Q: Compare and contrast descriptive, predictive, and prescriptive analytics.
A: Analytics is described as the process of communicating, interpreting, and discovering patterns in…
Q: Discuss the related critical success factors for a investment film engaged in asset management,…
A: CSFs (Critical Success Factors) are as vital and accessible as they seem! They're the aspects of…
Q: How should budgeting, scheduling, and resource loading or leveling be most logically accomplished in…
A: Making a strategy for how you will indeed spend your money is part of the budgeting process. This…
Q: Activity Duration(days) Construct the network and find critical path. 1-2 1-3 2-4 3-4 3-5 4-9 5-6…
A: A project network diagram is formed with the help of boxes and arrows. It shows the analytical…
Q: Which one of the following perils would be covered under the commercial property policy broad form…
A: Commercial property insurance covers the repair or replacement of building and building property…
Q: What are the characteristics of the operation of consulting agencies ?
A: Operations consulting is described as advising and/or implementation services that help a firm…
Q: Toyco produces a line of Bonnie dolls and accessories at its plants in New York and Baltimore that…
A: Find the Given details below: From/To Pittsburgh Denver Chicago Los Angeles Supply New York 182…
Q: 70 b. Mаximin? c. Laplace? d. Minimax regret? uly the ualysis NEXT YEAR'S DEMAND Alternative Low…
A: Minmax regret model of table which identify the lowest regression from regressions. Using the given…
Q: How do you think benchmarking improves a company’s performance? Justify your answer with suitable…
A: Benchmarking is a practice of establishing baselines, defining best practices, identification of the…
Q: Examine the many quantitative risk analysis methodologies available.
A: Quantitative risk analysis primarily focuses on evaluating the influence of project risks on the…
Q: A research report contains a comparision between project leader and manager Where best use …
A: A project leader is a expert who chiefs people & makes certain a mission is carried over.
Q: Describe 5 advantages and disadvantages of financial technical model
A: FINANCIAL MODELLING : Financial modelling is the process of creating an abstract representation of a…
Q: Quetion in picture
A: A benefit-cost ratio (BCR) defined as a ratio which is use in cost benefit analysis and its…
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Why is forecasting important and is forecasting reliable?
A: Production is the process of manufacturing raw materials and resources into finished products in an…
Q: The Demand for the 50 Kg Maize meal bag at Shoprite is 4000 units per month, Shoprite incurs a fixed…
A:
Q: A retail. Store stocks two types of shirts A and B. These are packed in attractive cardboard boxes.…
A:
Q: What is achieved when multiple methods are used in combination with one another yielding more…
A: Marketing communication often called Marcom can be stated as the messages and media that the…
Q: ssess the attractiveness of the Philippines as a location site for multinational corporations using…
A: Philippines has an overall a large population size of over 109 million people. The industries that…
Q: 8-22 (Portfolio selection problem) Daniel Grady is the financial advisor for a number of…
A: Given data is Desired expected return = more than or equal to 11% Maximum investment for each stock…
Q: Ritz Products's materials manager, Tej Dhakar, must determine whether to make or buy a new…
A: given,
Q: Given the soft constraint X, + X2 +d* - d" = 45, which was originally the hard constraint X, + X2 =…
A: Slack and surplus variables are referred to as Deviational Variables (di — and di +) in general…
Q: Identifies the common Production Planning methods that companies can use to control purchasing,…
A: Production planning is described as the process of developing a guide through which a service or a…
Q: What do you think is the most important shift in thinking that a project manager needs to make to…
A: An agile workplace can be stated as the type of work environment sketched around entire flexibility.…
Q: A brewery produces regular beer and a lower-carbohydrate "light" beer. Steady customers of the…
A: Decision Variable: Suppose- R be the no. of units of regular beer to be producedL be the no. of…
Q: LM.61 Boxmart needs to set up a new hub to distribute to a number of stores in four cities. The…
A:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- A final assembly plant for a certain automobile model is to have a capacity of 240,000 units annually. The plant will operate 50 weeks/yr, two shifts/day, 5 days/week, and 8.0 hours/shift. It will be divided into three departments: (1) Body shop, (2) paint shop, (3) trim-chassis-final department. The body shop welds the car bodies using robots, and the paint shop coats the bodies. Both of these departments are highly automated. Trim-chassis-final has no automation. There are 15.5 hours of direct labor content on each car in this department, where cars are moved by a continuous conveyor. Determine: (a) Hourly production rate of the plant, (b) number of workers and workstations required in trim-chassis-final if no automated stations are used, the average manning level is 2.5, balancing efficiency = 93%, proportion uptime = 95%, and a repositioning time of 0.15 min is allowed for each worker.A company is in the business of machining parts that go through various work centers. Suppose work center A feeds work center B with parts. The following times (in minutes) are given for each work center. Work Center Setup time Run time (per part) Move time A 3 0.5 6 B 2 0.1 8 A standard kanban container holds 50 parts that are transferred from work center A to work center B. The demand rate at work center B is four parts per minute. How many kanban containers are needed for this situation? 2. If move time is cut in half, what does this do to the number of containers needed? How much will this change reduce inventory?A bank recently finished construction of a new building in the downtown business district. You have been asked to help them arrange the various departments of its check processing division to minimize the workflow (Summation LxD) in its operations. The movement of checks between departments is shown in the table below. Department 4 (the check distribution department) must be in the room with the elevator. Only lateral movement is allowed (no diagonal movement allowed) from the center of one department to the center of the destination department. Each department is 50 feet x 50 feet. What is the Summation LxD of the recommended layout? 10,640 feet 15,960 feet 26,600 feet 38,800 feet None of the above Which of the potential layouts shown above should be recommended to the bank management? (Below is the potential layouts) Layout A Layout B Layout C Layout D None of the above
- You work for a small shipping company and warehouse. The owners have decided to update the software used for tracking, shipping, receiving, and inventory. Fifteen computers need to be updated. Hours of operation are 7 a.m. to 7 p.m. Monday through Saturday. Each computer must be updated manually by one of two trained employees, both of whom must be borrowed from other managers. The update procedure consumes 4 hours of the updater's time and generates an additional 1.5 hours of computer downtime. The work must be performed at a central loading station, away from the current location of the computer. How does the project portfolio management approach lead to enhanced strategic management for an organization and give an example how you woulduse this in a work place?Which is most likely true about theory of constraints? a. The theory of constraints does not apply to companies with multiple products because of capacity measurement difficulties. b. In any profit-seeking company, there must be at least one constraint. c. Constraints or bottlenecks stop organizations from selling an infinite number of units or services. d. b & c e. All of the above f. None of the aboveFurniture Face Lift refinishes old wood furniture. Their process for refinishing chairs has 9 workers and 4 stations. Each chair starts at the Stripping station, then goes to Priming, then to Painting and finally to Inspection. Where there are multiple workers within a station, each worker works independently on his/her own chair. Assume inventory buffers are allowed between each station. Station Staffing Processing time (hours per chair per worker) Stripping 3 2.5 Priming 2 1.5 Painting 3 1.75 Inspection 1 0.8 A truck loaded with 10 chairs arrives. How many hours will it take them to complete these 10 chairs?(The accuracy should be of two digits after the decimal places.)
- An automated machine runs for an 8-hr shift and requires an operator to run it. There are a few planned breakouts such as a 45-minute lunch break and a 10-minute production update break in the morning and a15-minute break during the shift. There are unplanned breakdown reports that have shown a repeatable average of 50 minutes per shift. The machine requires 25 minutes of tooling changeover and 25 minutes for adjustments to get a good product yield. Idling & minor stoppages account for an average of 10 minutes per shift. The machine only produces 3% defective product which includes any start-up adjustment losses. Calculate the Overall Equipment Effectiveness (OEE) for the equipment given the data.Mack’s guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 80 percent are considered good enough to sell. The other 20 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $300. Because some of the production process is automated, each guitar only requires 10 labor hours. Labor is paid at $10/hour, materials cost is $40/guitar, and overhead is $2,000. a) Calculate the labor and multifactor productivities. b) After some study, the operations manager recommends 3 options to improve the company’s multifactor productivity: (1) increase the sales price by 10 percent, (2) improve quality so that only 10 percent are defective, or (3) reduce labor, material, and overhead costs by 10 percent. Which option has the greatest impact on the multifactor productivity measure?. Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used to make a single housing. A computer numerically controlled (CNC) machine drills into the block to make the metal “frame” of the housing. Each block requires 15 minutes of drilling. The frame is then chemically treated in a series of baths. There is ample capacity in the treating stage. Finally, a worker must manually attach the various buttons and components to the metal housing. This assembly takes 120 minutes per housing per worker and Aquatica has 6 workers trained to do this task. The CNC machine requires a 30-minute setup time before the production of a batch can begin. a. If the CNC machine produces 14 housings between setups, what would be its capacity (in housings per hour)? b. Assuming the process is supply-constrained, what is the utilization (as a number between 0 and 1) of the CNC machine if it operates in batches of 14 housings? c. Assuming…
- The magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two kinds of patients, "regular" patients and "contrast" patients. The regular patients don't need any special preparation before imaging but the contrast patients receive an injection of "dye" that enables the physicians to see the images more clearly. Regular patients require 15 minutes in an MRI machine whereas contrast patients take on average 25 minutes in an MRI machine. Over an 8-hour day, the MRI unit receives an average of 25 regular patients and 5 contrast patients. (a) What is the implied utilization (as a %) of the MRI unit? % (b) What are the actual and maximum flow rates through the MRI (patients per day)? regular contrast Actual flow rates Max flow rates.The magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two kinds of patients, “regular” patients and “contrast” patients. The regular patients don’t need any special preparation before imaging but the contrast patients receive an injection of “dye” that enables the physicians to see the images more clearly. Regular patients require 15 minutes in an MRI machine whereas contrast patients take on average 25 minutes in an MRI machine. Over an 8-hour day, the MRI unit receives an average of 25 regular patients and 5 contrast patients. Convert the demand and capacity into "hours of work per day" to answer the following questions: (a) What is the implied utilization (as a %) of the MRI unit? % (Round your answer to whole number) Hint: First calculate the demand in hours of work per day: If there are 5 Contrast patients per day and each Contrast patient takes 25 minutes to 'process', how many 'minutes of work' are demanded every day from…Pickson Luthiers Corporation makes four models of electric guitars, ScarCT, Dela Mort, Warax, and Invazen. Each guitar must flow through five departments, assembly, painting, sound testing, inspection, and packaging. The table below shows the relevant data. Production rates are shown in units/hour. (ScarCT is assembled elsewhere). Pickson wants to determine how many guitars to make to maximize monthly profit. Pickson Luthiers Corporation Data Guitar Model Selling price/Unit Variable cost/Unit Min Sales Max Sales ScarCT 750.00 660.00 0 2500 Dela Mort 788.00 680.00 0 2000 Warax 800.00 700.00 100 1000 Invazen 850.00 800.00 80 500 Production rates (units/hour) ScarCT Dela Mort Warax Invazen Hours Available Assembly - 35 25 20 220 Painting 35 20 15 10 220 Sound Testing 20 10 20 18 220 Inspection 10 12 8 5 220 Packaging 9 10 5 8 220 Use a linear optimization model based on the data to answer the following…