Determine the risk adjusted Net Present Value of the following Projects: - Particulars Project A Project B Project C Net Cash Outlays (Rs) 100,000.00 120,000.00 210,000.00 Project Life 5 Years 5 Years 5 Years Annual Cash Inflow (Rs) 30,000.00 42,000.00 70,000.00 Coefficient of Variation 0.40 0.80 1.2 The company selects the risk-adjusted rate of discount on the basis of the coefficient of variation. Coefficient of Variation Risk Adjusted Rate of Discount Present Value factor 1 to 5 years at risk adjusted rate of discount 0.0 10 % 3.791 0.4 12 % 3.605 0.8 14 % 3.433 1.2 16 % 3.274 1.6 18 % 3.127 2.0 22 % 2.864 More than 2.0 25 % 2.689
Determine the risk adjusted Net Present Value of the following Projects: - Particulars Project A Project B Project C Net Cash Outlays (Rs) 100,000.00 120,000.00 210,000.00 Project Life 5 Years 5 Years 5 Years Annual Cash Inflow (Rs) 30,000.00 42,000.00 70,000.00 Coefficient of Variation 0.40 0.80 1.2 The company selects the risk-adjusted rate of discount on the basis of the coefficient of variation. Coefficient of Variation Risk Adjusted Rate of Discount Present Value factor 1 to 5 years at risk adjusted rate of discount 0.0 10 % 3.791 0.4 12 % 3.605 0.8 14 % 3.433 1.2 16 % 3.274 1.6 18 % 3.127 2.0 22 % 2.864 More than 2.0 25 % 2.689
Chapter16: Country Risk Analysis
Section: Chapter Questions
Problem 20QA
Related questions
Question
Determine the risk adjusted
Particulars |
Project A |
Project B |
Project C |
Net Cash Outlays (Rs) |
100,000.00 |
120,000.00 |
210,000.00 |
Project Life |
5 Years |
5 Years |
5 Years |
Annual |
30,000.00 |
42,000.00 |
70,000.00 |
Coefficient of Variation |
0.40 |
0.80 |
1.2 |
The company selects the risk-adjusted rate of discount on the basis of the coefficient of variation.
Coefficient of Variation |
Risk Adjusted Rate of Discount |
Present Value factor 1 to 5 years at risk adjusted rate of discount |
0.0 |
10 % |
3.791 |
0.4 |
12 % |
3.605 |
0.8 |
14 % |
3.433 |
1.2 |
16 % |
3.274 |
1.6 |
18 % |
3.127 |
2.0 |
22 % |
2.864 |
More than 2.0 |
25 % |
2.689
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Recommended textbooks for you
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub