Determine the tonnage or capacity/truck using the following parameters: Ore hauling Cycle time = 30 minutes hauling time = 18 hrs/day Production target = 30,000 tons per day Truck Capacity = 100 tonner Truck factor = 85 %
Determine the tonnage or capacity/truck using the following parameters: Ore hauling Cycle time = 30 minutes hauling time = 18 hrs/day Production target = 30,000 tons per day Truck Capacity = 100 tonner Truck factor = 85 %
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 8RQ
Related questions
Question
Determine the tonnage or capacity/truck using the following parameters:
Ore hauling Cycle time = 30 minutes
hauling time = 18 hrs/day
Production target = 30,000 tons per day
Truck Capacity = 100 tonner
Truck factor = 85 %
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,