Develop an ACTIVITY ON ARROW CPM diagram for the activities/relationships listed below. For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float (hint: a highlighter would be a good tool to use).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Use the legend to answer this question.

Develop an ACTIVITY ON ARROW CPM diagram for the activities/relationships listed
below. For each activity calculate the Early Start, Late Start, Early Finish, Late Finish,
Total Float, and Free Float (hint: a highlighter would be a good tool to use).
Label
A
B
с
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
Activity
Start
Procure Forms
Mobilize
Layout Footing 1
Excavate Footing 1
Form/Concrete 1
Cure 1
Set Base Plates 1
Layout Footing 2
Excavate Footing 2
Form/Concrete 2
Cure 2
Set Base Plates 2
Layout Footing 3
Excavate Footing 3
Form/Concrete 3
Cure 3
Set Base Plates 3
Finish
Duration
0
5
3
2
2
3
2
1
2
2
3
2
1
2
2
3
2
1
0
Successors
B, C
F
D
E, I
F
G
H
M
J. N
MLMROPORS
K
Q
Transcribed Image Text:Develop an ACTIVITY ON ARROW CPM diagram for the activities/relationships listed below. For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float (hint: a highlighter would be a good tool to use). Label A B с D E F G H I J K L M N O P Q R S Activity Start Procure Forms Mobilize Layout Footing 1 Excavate Footing 1 Form/Concrete 1 Cure 1 Set Base Plates 1 Layout Footing 2 Excavate Footing 2 Form/Concrete 2 Cure 2 Set Base Plates 2 Layout Footing 3 Excavate Footing 3 Form/Concrete 3 Cure 3 Set Base Plates 3 Finish Duration 0 5 3 2 2 3 2 1 2 2 3 2 1 2 2 3 2 1 0 Successors B, C F D E, I F G H M J. N MLMROPORS K Q
LEGEND:
ES
Early Start
Task ID
LS
Late Start
TF
Total Float
Duration
FF
Free Float
EF
Early Finish
LF
Late Finish
Transcribed Image Text:LEGEND: ES Early Start Task ID LS Late Start TF Total Float Duration FF Free Float EF Early Finish LF Late Finish
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.