Develop an ACTIVITY ON ARROW CPM diagram for the activities/relationships listed below. For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float (hint: a highlighter would be a good tool to use).
Q: Can finishing a stage stop the operation? Justify your replies
A: Yes, finishing a stage can stop an operation in certain contexts. It depends on how the operation is…
Q: Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one…
A: Engineering Costs imply costs for planning, finding, marking, investigating, or some other…
Q: How does the latency of interruptions impact the time it takes to move between tasks?
A: The successful completion of tasks is essential for any firm in the field of operations management.…
Q: 2 ERP articles review.
A: Article 1: "ERP Implementation Challenges: A Review and Future Directions" by Gao, Pan, and Xu…
Q: You are given the demand and forecast history for Apple iPhone 12. According to this, what is the…
A: Here, I have been given the actual demand and forecasted demand for each week, I would apply the…
Q: Which of the following factors is associated with small span of management/control? Group of answer…
A: When supervisors are only responsible for a small number of workers, they are said to have a "narrow…
Q: U.S. Airfilter has hired you as a supply chain consultant. The company makes air filters for…
A: Find the Calculation methods below: Average Inventory Turnover = Annual cost of Goods SoldAggregate…
Q: A project can be defined as which of the following a. A temporary endeavor with unlimited time or…
A: A project is described as a series of tasks that must be completed to achieve a specific outcome, A…
Q: Calculate the economic order quantity. From which vendor is the optimal order quantity and what is…
A: The EOQ is the level at which total cost is the lowest.
Q: Integrated Health was a large private, nonprofit health care system located in Tempe,Arizona. A year…
A: A change agent plays a crucial role in managing organizational change. This person is responsible…
Q: Week Actual Forecast 1 20.2 40.1 2 44.5 58.1 3 40.2 47.5 4 60.6 61.6 5 56.3 65.7 6 71.5 91.4 7 80.2…
A: Given-
Q: Week Actual Ft Tt 1 2 3 FIT 27.9 47.6 8.67 56.27 32.2 51.9 9.77 61.67 51.5 71.2 7.77 78.97 57.6 63.7…
A: Given: Alpha = 0.4 Beta = 0.15 To be determined: To find the Double Exponential forecast for week…
Q: How many kanban card sets are needed?
A: Average Units Demanded (D) = 3 units Lead Time (L) = 2 hours Safety Stock (S) = 0.50 Container Size…
Q: Describe the phenomena known as "Bring Your Own Device" (BYOD).
A: Bring Your Own Device (BYOD) is a work environment pattern that permits employees to utilize their…
Q: b. What would the utilization of the bed capacity become if the new beds were added and the hospital…
A: Given bed occupancy plan-
Q: Chan purchased a new bedroom set for $4,000. The interest rate is 18%. Chan paid $540 in interest.…
A: There are many financing options, and one of them is getting the products on EMI. While the product…
Q: In the area of the management plan devoted to the project's work that has to be done, what are the…
A: The three most important components to remember for the area of the management plan devoted to the…
Q: The forecast is already given to you. What will be the Bias for the table below? (Round your answer…
A: Bias refers to the arithmetic mean of difference in actual values and forecast
Q: Who should be in charge of documenting the results of the JAD session? a. Alex b. Tom c.…
A: Here, for the given MCQ question, I would describe the responsibilities of a recorder, and then come…
Q: Cherylene Brown has asked you to help her determine the best ordering policy for a new product. The…
A: Formulae used to determine the EOQ: EOQ (Q) = 2×D×SH Where, (D)=Annual Demand(S) = Ordering Cost…
Q: Answer the given question with proper explanation and step-by-step solution.
A: The critical Path Method is a concept of operations management that is used to determine which tasks…
Q: Describe the technique or method used to select the project. (4) Identify and describe at least five…
A: The above project comes with multiple purposes, and it could offer multiple results/outcomes term…
Q: IBM Sametime is IBM’s telepresence and collaboration environment. Formerly known as Lotus Sametime,…
A: IBM Sametime supports collaboration by providing a platform for real-time social communications and…
Q: Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most…
A: Formulae used: Expected time(te) =a+4m+b6where,a= optimistic timem= most likely timeb= pessimistic…
Q: The employee credit union at State University is planning the allocation of funds for the coming…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: c. Level or degree of customer/user satisfaction of results and outcomes d. Value created for the…
A: To improve sports development in St. Catherine North Central by giving sports clubs and teams…
Q: Q3. You borrowed $150,000 with a 30-years payback term and a variable APR that starts at 9% and can…
A: Ans) Data Given in Question: Loan Amount = A = 150,000 Time = t = 30 years = 30*12 = 360 months a)…
Q: U.S. Airfilter has hired you as a supply chain consultant. The company makes air filters for…
A: Given-
Q: Week Actual Forecast 26.2 39.8 2 26.4 46.3 3 53.2 54.2 4 63.2 72.6 5 57.8 63.0 6 79.0 94.7 7 77.8…
A: 3 period weighted moving average forecast means treating the resultant of sum product of weights and…
Q: a) Using simple linear regression, the forecast for the number of disk drives 240.2 disk drives…
A: Here, for each year, I have been given the number of disk drives, I would apply the simple linear…
Q: For the network shown below, the project indirect cost for each day is $1,000. The following is the…
A: Here two paths are being formed i.e. ABF and CDEF ABF duration = 7+10+2 = 19 days CDEF duration =…
Q: Santa Fe 855 Cx Cy 550 16,000 Use the centroid method to recommend a location for the new bottling…
A: The general formula of the centroid method will be: Cx= Total of (X coordinate*no.of cases)total of…
Q: Which of the following reasons explains the presence of missing data in survey research?…
A: To be determined: Choose the right reason that explains the presence of missing data in survey…
Q: A small bank is trying to determine how many tellers toemploy. The total cost of employing a teller…
A: Service rate is the rate at which customers are being served in an organisation.
Q: What hinders m-commerce? How to beat them?
A: The mobile commerce revolution has changed the game for how businesses interact with and sell to…
Q: How do you describe the patterns of manufacturing decisions?
A: Manufacturing decisions include a range of activities that are intended to optimize production…
Q: what do you learn from ERP, Leadership and business process.
A: Every business is implementing new technology to improve its working conditions. New technological…
Q: In the case it was mentioned that ‘One of the conventional risks, political, regulatory and…
A: Tesco plc (Tesco), a food retailer which is the largest supermarket chain in the Unified Realm and…
Q: The local supermarket buys lettuce each day to ensure really fresh produce. Each morning, any…
A: Cost of box = $7 Selling price per box = $18 Selling price of old product = $2 Average demand = 255…
Q: How do transaction processing, customer relationship management, and supply chain management systems…
A: A project management life cycle is a process with different stages like initiating, planning,…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: Given data: No. of task 1 2 3 4 5 6 7 8 9 Time in seconds 80 50 30 25 55 15 45 105 40
Q: a-1. If the inspector position is eliminated, what will the hourly cost of defects be? Note: Round…
A: Production is a process that turns raw materials into finished products while utilizing a variety of…
Q: Tesco relies heavily on, ‘localization’ in Japan. Based on the international business strategies…
A: Tesco is the Uk's largest retail store. The organization started its international expansion…
Q: Could you briefly discuss any two quality regulatory process results to increase project quality
A: As per the Q, I would describe two quality regulatory processes along with expected benefits or…
Q: What distinguishes project management from software project management?
A: In order to reach certain goals and objectives, a project must be planned, carried out, and…
Q: Answer the given question with a proper explanation and step-by-step solution. Use the…
A: answering first three subparts as per guidelines Average arrival rate, λ = 2.5 per minute Average…
Q: Based on the PERT diagram, where the numbers indicate days required between events, how many days…
A: The project duration is equal to the maximum time taken by one of multiple possible paths.
Q: 1) What is the estimated expected (mean) time for activity C? A. 48 days B. 72 days C. 44 days D. 60…
A: A network diagram shows the sequence of the task that is done to complete a project. It usually…
Q: Marketing and Distribution of Mushroom Sachin and Virag are two enterprising youth. They have passed…
A: Mushroom Promotion and Retailing Both Sachin and Virag are young and ambitious. Instead of working,…
Q: Month# Forecast# Starting inv.# Net requirement# Prod. rate# Ending inv.# Stockout Jan 1000 772 638…
A: level plan means similar production every period. lost sales means backorders cant be fulfilled.
Use the legend to answer this question.
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 4 images
- A student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 5This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .
- please help, project management. I need part D,Eand 2 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited…Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chart
- Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…Solve asap! To develop a WBS structure for a project “Design and Manufacturing of shaft in the Mechanical workshop”, (b) select resources, and (c) develop a Linear responsibility chart.For the next project: | | TIME ESTIMATE (WEEKS) TASK DESCRIPTION a m b A foundations 2 3 4 B framework 4 7.5 8 C roofs 3 5.5 11 D plumbing 2.5 4 5.5 E electrical wiring 2 3 4 F doors and windows 3 5 7 G interior finish 3 3.5 7 H exterior finish 2 5 8 I inspection 1 1 1 a. I made the network diagram. b. Calculate the parameters corresponding to expected time, variance, nearest and farthest start times and farthest c. What is the probability of meeting a specific project completion date? For example, what is the probability of building the house in 32 weeks? Topic: stochastic processes
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managers1. Represent the contents of a project charter with your own example. 4. Give your own example of WBS in Chart Form.Entrepreneur Andrew Field bought a print shop and used his selling skills to boost sales to about $1 million annually. The high fixed cost structure of his business resulted in only a break-even situation, however, and Field saw no hope for improvement given his relatively small local markets. The idea for a Web site finally struck. Field devised an interactive Web site system to fill his idle capacity. Customers design and submit their orders through a simple program. The company then e-mails a project number and link to a proof of the order, and once approved by the customer, a production, shipping, and delivery date are established. Field filled his idle capacity and then took his company to the next level by soliciting more work and subcontracting that to competitor companies. Word of the ease and reliability of Fields system has spread, and the company now averages about 7,000 visitors to its site each day, generating sales of $8 to $9 million. Q1. Would Fields strategy for…