Draw the project network ii. Compute the expected time and variance for each activity Compute slack for each event and find the critical path i. iii.
Q: 1- Total project finishing time. 2- Critical path 3- Free float for each task. • 4- If Activity B is…
A: The critical path method is a project management technique that identifies the sequence of tasks…
Q: The nine activities A to I whích make up a project are subject to the following precedence…
A: Disclaimer- Since you have posted a question with multiple sub parts , we will solve first three sub…
Q: Q2: For the activities shown below determine: . The duration of project . The critical path by using…
A: ANSWER IS AS BELOW:
Q: From the above table, determine the critical path? and what is the total project completion time…
A: In this question, I have to prepare the network diagram, based on this network diagram, we could get…
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: 1. Draw the network diagram for the above project. 2. What is the critical path? 3. What is the…
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers…
A: Critical path examination is an undertaking arranging technique that spotlights on recognizing…
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: The conditions and pert times for constructing a network diagram are given below. -Creation…
A: Given data is
Q: A project's activities must be completed in the sequence indicated below. Activity Immediately…
A: Here, It is CPM or critical path method problem, for this problem, I have following data like…
Q: 11. Building a backyard swimming pool consists of nine major activities. The activities and their…
A: As you have posted multiple questions, we will provide the answers to the first question. Kindly…
Q: (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for booking a…
Q: (1) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: I need help for number 12, please. Based on question number 11, which I already know the answer,…
A:
Q: The following activities are part of a project to be scheduled using CPM: АсTIVITY IMMEDIATE…
A: This question is related to the topic - Project Management and this topic fall under the operations…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: A manager wants to put in a computer data system within the company. The activity, immediate…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: Given Information:
Q: i. Draw the network diagram linking all the activities in a way that it shows if there exist any…
A:
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: lease complete the ES, EF, LS, LF, and slack for the project below. Activity Description
A: Early start (ES) indicates the earliest time of the beginning of the activity. Early finish (EF)…
Q: Draw the network and identify the critical path of following data and total slack time in the…
A: Find the given details below:
Q: The estimated times and immediate predecessors for the activities in a project at George Kyparis's…
A: Activity Imm Pred a m b Expected timee = (a+4m+b)/6 SD(b - a) / 6 Variance A 9 10 11 10 0.333…
Q: The aritical path for the network activities shown below is with completion time of weeks. Activity…
A: Answer: For determining the critical path, we have to draw the network diagram of the mentioned…
Q: A project manager has compiled a list of major activities that will be required to install a…
A:
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: (a) Construct the AON network for the project. (b) Determine all paths that run from the start to…
A: Activity-on-node is a project management term that directs to a precedence diagramming technique…
Q: Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: For the project data in Table below, answer the following questions: a) Draw AON & AOA networks of…
A: Below is the solution:-
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: Draw a network representation of the project (nodes = activities, arrows = precedence constraints).…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: The Industrial and Systems Engineering Department at Sun University is moving from its old building…
A: Project management is the management in which different kinds of skills, techniques, processes, and…
Q: The estimated times and immediate predecessorsfor the activities in a project at George Kyparis’s…
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: From the following information, develop an AON project network. Complete the forward and backward…
A: Given Information:
Q: You are provided with the following information for a project, with activity durations given in…
A: The question is related to Programme Evaluation Review Technique (PERT). The expected duration will…
Q: Part 1: Building a backyard swimming pool consists of nine major activities. The activities and…
A: From the given data the network diagram is drawn below-
Q: The following table contains a list of activities, with precedence requirements and crash costs. All…
A: a.
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: (i) Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Project ALPHA has 6 activities from A to Fas follows: Activity Duration Preceded By B A D Legend:…
A: Given data is
Q: Immediate Estimated Activity Predecessors Duration A t+5 months В t+1 month C В t+2 months A, C t+4…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for planning a…
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: Suppose that the project team has arrived at the following time estimates for activity B (Select…
A: a = 7 weeks, m = 8 weeks, b = 15 weeks
Q: For the project data in Table below, answer the following questions: a) Draw an AOA network of the…
A: ANSWER IS AS BELOW:
Q: a) Calculate each activity duration using the last digit of your student number. For example, if…
A: THE ANSWER IS AS BELOW:
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent,…
A: Below is the solution:-
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: • Draw the Network diagram. • Calculate expected time and variance for each activity. • Find the…
A: Let: a= OPTIMISTIC TIME b= PESSIMISTIC TIME m= MOST LIKELY TIME Te = EXPECTED TIME = (a+4m+b)/6…
Q: Using information provided to draw a Project Network. Nodes in your Project Network must organize…
A: Critical path is the path with the shortest possible duration which a project can take to complete…
Kindly help
Step by step
Solved in 3 steps with 2 images
- Question 2 Given the information of a project in the Table 2 below. Note that the project is completed when activity F and G are completed. Table 2 Activity Dependency Time (months) A - 4 B - 6 C A 2 D A 6 E C,B 3 F C,B 3 G D,E 5 1. Find the activity schedule for the project. Fill Earliest Start (ES), Earliest Finish (EF) and Latest Start (LS) and Latest Finish (LF) times in the empty boxes of the diagram below. 2. Find the critical path of the project. 3. Find out project time. 4. In many practical situations, activity times are not known exactly. Explain how you may deal with situations where activity times are…Question 3 Given the information of a project information is given in Table 2 and the project diagram showing precedence relationships of the activities. Table 2 Activity Dependency Time (weeks) A - 3 B - 3 C A 2 D A 8 E C,B 5 F C,B 5 G D,E 7 1. Find the activity schedule for the project. Fill Earliest Start (ES), Earliest Finish (EF) and Latest Start (LS) and Latest Finish (LF) times in the empty boxes of the diagram below. 2. How long the activity G can be delayed without delaying the project? 3. Can activity B be delayed without delaying the project? If so for how long?QUESTION 1 Your organization has signed a new project contract to install 12 electric generators. The Budget of the project is $120,000 ($10K per electric generator). The duration of the project is 12 weeks (1 electric generator per week). First scenario: At week 2: •3 electric generators installed. •$28,000 spent to date. Second scenario: At week 6: •5 electric generators installed. •$57,500 spent to date. According to the above scenarios, how are you going to answer the following questions? 1.Are you ahead or behind schedule? 2.How efficiently are you using your project’s time? 3.When is this project likely to be completed? 4.Are you currently under or over budget? 5.How efficiently are you using your resources? 6.What is the remaining work likely to cost? 7.What is the entire project likely to cost? 8.How much will you be under or over budget at the end?
- Question 3 Given the information of a project information is given in Table 2 and the project diagram showing precedence relationships of the activities. Table 2 Activity Dependency Time (weeks) A - 3 B - 3 C A 2 D A 8 E C,B 5 F C,B 5 G D,E 7 1. Find the activity schedule for the project. Fill Earliest Start (ES), Earliest Finish (EF) and Latest Start (LS) and Latest Finish (LF) times in the empty boxes of the diagram below.QUESTION 1 The following information is available for a large fundraising project. Activity Activity Time (days) Activity Cost ($) Immediate Predecessor(s) A 3 100 -- B 4 150 -- C 2 125 A D 5 175 B E 3 150 B F 4 200 C, D G 6 75 C H 2 50 C, D, E I 1 100 E J 4 75 D, E K 3 150 F, G L 3 150 G, H, I M 2 100 I, J N 4 175 K, M O 1 200 H, M P 5 150 N, L, 0 Determine the critical path and the expected completion time of the project. Plot the total project cost, starting from Day1 to the expected completion date of the project, assuming the earliest start times for each activity. Compare the result to a similar plot for the latest start times. What implication does the time differential have for cash flows and project scheduling?Question content area Part 1 The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 8 10 13 — C 8 10 11 A B 5 10 16 — D 4 8 14 B This exercise contains only parts a, b, c, d, and e. Part 2 a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):…
- Question: A firm is planning a project which consists of the following ten jobs and precedence relations are identified with their node numbers: Jobs (i-j) 1-2 1-3 2-3 2-4 2-5 3-5 4-7 5-6 6-7 7-8 Durations (days) 9 5 12 7 8 11 10 3 4 6 a. Draw an arrow diagram representing the project.b. Determine the critical pathc. What is the duration of the project?Question 5transaction processing system is an ICT project being undertaken to enhance organizational performance. the following as a Project Manager:a) How would the project manager identify the project scope and organize your work breakdown structure? b) How would the project manager make use of the Gantt-Chart to facilitate your project delivery? c) How would the project manager make use of critical path analysis to identify the project critical activitiesQuestion 39 Given the following activity network: (3 activities - A1, A2 & A3; arrows point from A1 to A2 and A1 to A3) 39-1.docx Actions Activity A1 takes 6 weeks, A2 takes 9 weeks, and A3 takes 3 weeks. What is the slack of A3? Group of answer choices 8 weeks 6 weeks 7 weeks 0 weeks
- Question 42 Given the activities, time estimates and dependency relationships: Duration (days) Activity Predecessor Optimistic Most Likely Pessimistic A *** 3 5 13 B *** 4 7 10 C A 5 7 15 D B 8 9 22 What is the estimated slack time for activity A? Group of answer choices 0 4 6 1SIMPLE PERT question Expected Time fot the critical path on a PERT network is 18.2 weeks, and the critical path variance is 4. 1. The project was supposed to be done in 16 weeks. How do I find probability that the project will be finished on or 16 weeks? 2. Suppose I can adjust the project to set a deadline so that 98% of the time, it would be on time. How do I find deadline required to reach that level? 3. Ignoring 1 and 2, use original numbers of 18.2 weeks expected time and Variance of 4.. The company will pay $100,000 fine if project is not done in 21 weeks. How much would the ocmpany be willing to pay (in terms of insurancE) given their chances of having to pay that $100,000 fine?Question content area Part 1 A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed: Activity a m b A 10 16 19 B 26 31 41 C 18 18 18 D 8 14 20 E 17 18 20 F 16 20 23 Part 2 Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places): Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Based on the activity time estimates, standard deviation for each of the activities is (enter your responses rounded to two decimal…