a. Construct the network diagram for this project. b. Determine the earliest and latest start times for each activity. c. Determine the slack (float) of each activity. d. Calculate the critical path and duration of the project.
Q: Which activity should be crashed to reduce the project completion time by one day? -Activity E…
A: In this given problem, first, calculate the project completion time. There are two possible paths.…
Q: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C.…
A: Network diagram as per given information:
Q: Which of the following questions regarding a project CANNOT be answered even if the critical path of…
A: The difficulty that someone encounters while accomplishing something is referred to as a problem.…
Q: What project scheduling tool expands and contracts to share the right information to the right…
A: Schedule Variance An Schedule Variance denotes how much ahead or behind schedule a project is. By…
Q: To obtain reasonable assurance about the completion of the project within the timeline, the best…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Three recent college graduates have formed a partnership and have opened an advertising firm. Their…
A: Precedence DiagramThe precedence diagram is as shown in the diagram below:
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: With the use of a diagram, show (illustrate) the typical levels of project staffing related to each…
A: A project is initiated with an objective and to fulfill the objective the company defines the…
Q: Which of the following is an individual who acts as a liaison between the org. & project team.…
A: The way into a fruitful association is to have a culture dependent on a firmly held and broadly…
Q: This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: First we will draw the project network diagram. Initial activities are A, B, and C. After that we…
Q: Which among the following is not a software generally used for project management O a. Primavera O…
A: C. ERP- it is Enterprise resource planning refers to plan and manage all the core organization…
Q: I need a detailed explanation and assistance on how to solve this problem: The company decided that…
A: Since the project network diagram is not given we are assuming the following network diagram in AOA…
Q: The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE…
A: Given Information:
Q: 1.What’s the maximum amount of time that activity F can be delayed without delaying the whole…
A: Activity Immediate Predecessors Duration A - 2 B - 3 C A 2 D B 4 E C 4 F C 3 G D,E 5…
Q: This exercise tests your ability to come up with a detailed and elaborate Business Case for a…
A: Project management is the process of leading the work of a team or a group to achieve goals and meet…
Q: Identify the order in which a Project manager does his job a. Planning, Organizing,…
A: A project manager is the responsible person for the whole project and is the person who makes proper…
Q: 1.Estimating the type and quantities of resources required to perform each schedule activity…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: 27. Consider a project with six activities: G, B, C, D, E, and F. Assume G and F can be started as…
A: The right option is the second choice. i.e., G--> B, G--> C, B --> D, C--> D,…
Q: This unit examines the project execution process with emphasis on dealing with project durations. As…
A: Project Scope is everything you need to complete in order to achieve delivery of the project.…
Q: You own a software development company that has been hired to build an online classified ads website…
A: As per Bartleby guidelines, we are only allowed to do the first question or the first three subparts…
Q: a.To set clear guidelines as to how the project schedule will be developed, managed and controlled…
A: A project schedule is a plan which enables the project manager to make schedules about the speed of…
Q: What was the first major project management information system that is now commonly used for…
A: Primavera was the first major project management information system that is now commonly used for…
Q: Which one of the following is NOT a tool/technique for developing a project schedule? a.…
A: A project schedule is a timeline that outlines the start and end dates of all project tasks, how…
Q: refers to how the project is expected to work and solve the stated problem in project or proposal…
A: OPTION D is correct - project activities
Q: Using a suitable example each, describe what the following project planning process activities…
A: The purpose of the project planning phase is to establish a resource plan, cost, schedule, list of…
Q: n the project management plan's work that has to be done section?
A: Effective project management is crucial to the smooth operation of any business. Revenues and costs…
Q: project manager's job is to make sure that project is properly planned, implemented and complete
A: It is the duty of the manager to act as a bridge between the top management and employees and to…
Q: challenges in assessing the scope of a project? What is “scope creep” and how do you ensure that it…
A: Scope of project is set of work which is necessary to complete the project. Project might be a to…
Q: (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File no file…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Describe what is a Schedule Management Plan and state why it is necessary to have such a plan.
A: A Schedule Management Plan is a part of project management. Schedule Management Plan is the plan of…
Q: 8. You are in charge of organizing a dinner-dance concert for a local charity. You have reserved a…
A: A good scope statement and priorities include- Project objectives Deliverables Milestones Technical…
Q: Suppose that you are assigned to a construction project which is planned to be build as early as…
A: A Gantt chart:It is a project management mechanism helping in the outlining & scheduling of the…
Q: Reasons why estimating time and cost are important include all of the following EXCEPT a. to…
A: The objective of estimating is to define the cost of a project before you truly perform the task.…
Q: , and PDM. Look for projects (1 for each method) that have implemented successfully using these…
A: It is possible to describe project management as a methodical approach to organising and managing…
Q: 1). Based on the below table: (a) Construct a network for this problem. (b) Determine the expected…
A: Since you have submitted multiple questions with multiple subparts, as per guidelines we have…
Q: A well designed WBS helps the project manager in that: a) It defines all the elements of the project…
A: WBS Project management and system engineering WBS or Work Breakdown Structure is the main project…
Q: i). Calculate the expected time for each activity ii. Draw a Gantt Chart from the same…
A: given,
Q: A. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the…
A: Given data is
Q: Which of the following is/are not part of the three main responsibilities of a project manager?a.…
A: A project manager is a professional who manages a project in an organization. He has the…
Q: 1. What’s the maximum amount of time that activity G can be delayed without delaying the whole…
A: Given: Activity Immediate Predecessors Duration A - 2 B - 3 C A 2 D B 4 E C 4 F C 3…
Q: Mr. Ali being an enthusiast player wants to remain in good relation with his employer, Mr. Mohamed.…
A: 1. No, Mr. Ali's action is not acceptable within an organization's climate as an employee should…
Step by step
Solved in 2 steps with 3 images
- To be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeksProject 1-3: Creating a Project Schedule for Hiring a New EmployeeIn this project, you will create a project schedule for the process of hiring a new employee for your department. GET READY. OPEN a new blank project schedule. Set the project start date to be October 21, 2019.Enter the following tasks and durations:Task DurationWrite job description 2dNotify departmental recruiter 1dPost job internally 5dPost job externally 5dCollect résumés 10dReview résumés 5dSet up interviews 3dConduct interviews 8dSelect candidate 1dMake offer milestoneAssign a finish-to-start relationship to all the tasks.Change the relationship between tasks 3 and 4 to a start-to-start relationship.Auto-fit all the columns and rows.Change all tasks to the Automatically Scheduled mode.Use the statistics button on the Project Information dialog box to determine the current project duration.SAVE the project schedule in the solutions folder for this lesson as Hiring Employee xxd where…a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities of a project and their durations. Table 1Activity Preceding Activity Duration (Days)A – 9B – 3C A 8D A 2E A 3F C 2G C 6H C 1J B,D 4K F,J 1L E,H,G,K 2M E,H 3N L,M 4 i. Draw the project network.ii. Determine its critical path and completion time.iii. Calculate the total float for the non-critical chains. 2. a) Outline FOUR different types of stockholding casts. b) i) Explain the periodic review system of inventory control.ii) State TWO disadvantages of the periodic review system. c) Explain FOUR major functions of an office. d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team. 3. a) State FOUR objectives of maintenance in a manufacturing plant. b) Explain the purpose of the…
- 8. Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 11 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A ___ 7 Activity ES EF B ____ Activity ES EF C _____ Activity ES EF D ___ Activity ES EF E ___ Activity ES EF F __ Activity ES EF G ____…#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Please assist in detailed explanation on the following question in Project Scheduling: 1) - A company decides to plan a project, with activities, precedence and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F Questions: 1.1) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. 1.2) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). 1.3) Draw a Gantt chart of the schedule, based on earliest starting times 1.4) Which activities must be completed by day 60 to ensure that the project is not delayed?
- 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…1. Define what a WBS is relative to project planning, and the importance of the WBS in a project plan.
- a) Construct a network for this project b) Find a project schedule to minimize the completion time of the project14. The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 1 B, C $400 B 1 E $100 C 4 F $200 E 2 F $300 F (end) 2 — $400 Part 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (days) A (start) _________ week(s) B _________ week(s) C _________ week(s) D _________ week(s) E F _________ week(s) _________ week(s) What is the total crashing cost ?114. Duration Task Estimates A ABCDE F 2 5 1 2 3 12 Click here for the Excel Data File Req B1 b-1. Identify the critical path. b-2. Identify the earliest start and finish. Task b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely? OUM TI Complete this question by entering your answers in the tabs below. D days days day F E F E F C days days days B A Immediate Predecessors None Identify the slack for each task. Note: Leave no cells blank - be certain to enter "0" wherever required. None A B A B and D E and C C, E B, D Immediate Successors Req B2 Req B3 Req C Latest Completion Latest Start (LS) Slack