Empire Polymer Development produces three products using three different continuous processes. The products are Yarex, Darol, and Norex. Projected sales in gallons for the three products for the years 20x2 and 20x3 are as follows: Yarex Darol Norex 20x2 127,000 87,000 57,000 Raw Material Gamma Murad Islin Tarden 20x3 137,000 77,000 67,000 • Inventories are planned for each product so that the projected finished-goods inventory at the beginning of each year is equal to 6 percent of that year's projected sales. Because of the continuous nature of Empire's processes, work-in-process inventory for each of the products remains constant throughout the year. The raw-material requirements of the three products are shown in the following chart. Units pounds pounds gallons gallons Unit Price $ 7.00 5.00 4.00 9.00 Yarex 0.4 0.6 1.2 0 Darol 0.6 0 0.9 0.5 Norex 0 0.7 0.7 0.7 Raw-material inventories are planned so that each raw material's projected inventory at the beginning of a year is equal to 15 percent of the previous year's usage of that raw material. The conversion requirements in hours per gallon for the three products are Yarex, 0.06 hour; Darol, 0.09 hour; and Norex, 0.15 hour. The conversion cost of $20 per hour is considered 100 percent variable. Required: 1. Determine Empire Polymer Development's production budget (in gallons) for the three products for 20x2.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter2: Basic Cost Management Concepts
Section: Chapter Questions
Problem 4CE: Refer to Cornerstone Exercises 2.2 and 2.3. Next year, Pietro expects to produce 50,000 units and...
icon
Related questions
Question
Empire Polymer Development produces three products using three different continuous processes. The products are Yarex, Darol, and
Norex. Projected sales in gallons for the three products for the years 20x2 and 20x3 are as follows:
.
.
.
Yarex
Darol
Norex
Raw Material
Gamma
Murad
20x2
127,000
87,000
57,000
Inventories are planned for each product so that the projected finished-goods inventory at the beginning of each year is equal to 6
percent of that year's projected sales.
Because of the continuous nature of Empire's processes, work-in-process inventory for each of the products remains constant
throughout the year.
The raw-material requirements of the three products are shown in the following chart.
Islin
Tarden
20x3
137,000
77,000
67,000
Units
pounds
pounds
gallons
gallons
Unit Price Yarex
$ 7.00
0.4
5.00
0.6
4.00
1.2
9.00
0
Darol
0.6
0
0.9
0.5
Norex
0
0.7
0.7
0.7
Raw-material inventories are planned so that each raw material's projected inventory at the beginning of a year is equal to 15
percent of the previous year's usage of that raw material.
The conversion requirements in hours per gallon for the three products are Yarex, 0.06 hour; Darol, 0.09 hour; and Norex, 0.15 hour.
The conversion cost of $20 per hour is considered 100 percent variable.
Required:
1. Determine Empire Polymer Development's production budget (in gallons) for the three products for 20x2.
Transcribed Image Text:Empire Polymer Development produces three products using three different continuous processes. The products are Yarex, Darol, and Norex. Projected sales in gallons for the three products for the years 20x2 and 20x3 are as follows: . . . Yarex Darol Norex Raw Material Gamma Murad 20x2 127,000 87,000 57,000 Inventories are planned for each product so that the projected finished-goods inventory at the beginning of each year is equal to 6 percent of that year's projected sales. Because of the continuous nature of Empire's processes, work-in-process inventory for each of the products remains constant throughout the year. The raw-material requirements of the three products are shown in the following chart. Islin Tarden 20x3 137,000 77,000 67,000 Units pounds pounds gallons gallons Unit Price Yarex $ 7.00 0.4 5.00 0.6 4.00 1.2 9.00 0 Darol 0.6 0 0.9 0.5 Norex 0 0.7 0.7 0.7 Raw-material inventories are planned so that each raw material's projected inventory at the beginning of a year is equal to 15 percent of the previous year's usage of that raw material. The conversion requirements in hours per gallon for the three products are Yarex, 0.06 hour; Darol, 0.09 hour; and Norex, 0.15 hour. The conversion cost of $20 per hour is considered 100 percent variable. Required: 1. Determine Empire Polymer Development's production budget (in gallons) for the three products for 20x2.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 1 images

Blurred answer
Knowledge Booster
Theory of Constraints (TOC)
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning