estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At At At 12/31/20 12/31/21 12/31/22 Contract costs incurred to date $327,800 $ 1,180,000 $2,090,400 Estimated costs to complete the contract 1,162,200 820,000 -0- Billings to Gumbel 300,000 1,110,000 1,870,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using eithera negative sign prececeding the number e-g. -45 or parenthesis es. (45).)

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 25E: Koolman Construction Company began work on a contract in 2019. The contract price is 3,000,000, and...
icon
Related questions
Question
Current Attempt in Progress
On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of
$ 1,910,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022,
the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the
contract, and accumulated billings to Gumbel for 2020, 2021, and 2022.
At
At
At
12/31/20
12/31/21
12/31/22
Contract costs incurred to date
$ 327,800
$ 1,180,000
$2,090,400
Estimated costs to complete the contract
1,162,200
820,000
-0-
Billings to Gumbel
300,000
1,110,000
1,870,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this
contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any
field blank. If an amount should be deducted then enter the amount using eithera negative sign prececeding the number e.g. -45 or parenthesis
eg. (45).)
Transcribed Image Text:Current Attempt in Progress On July 1, 2020, Crane Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $ 1,910,000. On July 1, Crane estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At At At 12/31/20 12/31/21 12/31/22 Contract costs incurred to date $ 327,800 $ 1,180,000 $2,090,400 Estimated costs to complete the contract 1,162,200 820,000 -0- Billings to Gumbel 300,000 1,110,000 1,870,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. If an amount should be deducted then enter the amount using eithera negative sign prececeding the number e.g. -45 or parenthesis eg. (45).)
2021
Costs to date (12/31/21)
24
1180000
Estimated Costs to Complete
820000
Estimated Total Costs
2000000
Contract Price
Total Profit/Loss
2$
Total Profit/Loss
2$
Gross Profit Recognized in 2020
Profit / (Loss) Recognized in 2021
$4
2022
Costs to date (12/31/22)
2$
2090400
Estimated Costs to Complete
Contract Price
Total Profit/Loss
$4
Total Profit/Loss
24
Profit/(Loss) Recognized in 2021
%24
Profit/(Loss) Recognized in 2020 v
Profit/(Loss) Recognized in 2022
%24
Transcribed Image Text:2021 Costs to date (12/31/21) 24 1180000 Estimated Costs to Complete 820000 Estimated Total Costs 2000000 Contract Price Total Profit/Loss 2$ Total Profit/Loss 2$ Gross Profit Recognized in 2020 Profit / (Loss) Recognized in 2021 $4 2022 Costs to date (12/31/22) 2$ 2090400 Estimated Costs to Complete Contract Price Total Profit/Loss $4 Total Profit/Loss 24 Profit/(Loss) Recognized in 2021 %24 Profit/(Loss) Recognized in 2020 v Profit/(Loss) Recognized in 2022 %24
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Essntl Tax Individ/Bus Entities 2020
SWFT Essntl Tax Individ/Bus Entities 2020
Accounting
ISBN:
9780357391266
Author:
Nellen
Publisher:
Cengage