A part structure, lead time (weeks), and on-hand
quantities for product A are shown in Figure 14. 14. From the
information shown, generate:
a) An indented bill of material fo r product A
b) Net requirements for each part to produce I0 As in week 8
using lot-for-lot. IP
Figure 14.14
INVENTORY
ON HAND
Information for Problems
PART
PART STRUCTURE TREE
14.14, 14.15, 14.16, and 14.17
LT = lead time in weeks
(1) = All quantities = 1
A
A LT = 1
B
10
B(1) LT = 1
F(1)| LT = 1
D
4
C1 LT =2
D(1) LT = 1
G1 LT = 3
Hu LT = 1
F
G
1
H
10
E1) LT = 1
E LT = 1 C(1) LT = 2
Transcribed Image Text:Figure 14.14 INVENTORY ON HAND Information for Problems PART PART STRUCTURE TREE 14.14, 14.15, 14.16, and 14.17 LT = lead time in weeks (1) = All quantities = 1 A A LT = 1 B 10 B(1) LT = 1 F(1)| LT = 1 D 4 C1 LT =2 D(1) LT = 1 G1 LT = 3 Hu LT = 1 F G 1 H 10 E1) LT = 1 E LT = 1 C(1) LT = 2
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,