Find the cycle time required to meet the desired output rate. Note: Round your answer to 1 decimal place.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

The following tasks are to be performed on an assembly line:

TASK SECONDS TASKS THAT MUST PRECEDE
A 30
B 16 A
C 21 B
D 15 B
E 17 C
F 14 D
G 20 E, F
H 9 G

The workday is 8 hours long. The demand for completed product is 900 per day.

  1. Find the cycle time required to meet the desired output rate.

    Note: Round your answer to 1 decimal place.

     

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,