For a given work, minimum possible time under certain condition is 20 mins, most likely time is 32 mins. Assuming work to follow same probability distribution as PERT activity, expected time of work is calculated as 34 mins. Maximum time of work for this under worst condition would be mins.

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter12: Forecasting Travel Demand
Section: Chapter Questions
Problem 19P
icon
Related questions
Question
Please solve this scheduling problem
For a given work, minimum possible time under certain condition is 20 mins, most likely time is 32 mins. Assuming work to follow same
probability distribution as PERT activity, expected time of work is calculated as 34 mins. Maximum time of work for this under worst
condition would be.
_mins.
Transcribed Image Text:For a given work, minimum possible time under certain condition is 20 mins, most likely time is 32 mins. Assuming work to follow same probability distribution as PERT activity, expected time of work is calculated as 34 mins. Maximum time of work for this under worst condition would be. _mins.
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Types of Scheduling Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning