Gordon Miller's job shop has four work areas, A B, C, and D. Distances in foet between centors of the work aroas are A B D. 5. 9. 8. B 7. 6. Workpieces moved per week betweon work areas are: C. D. 1,000 800 400 B 400 400 800 D. It costs Gordon $3 to move 1 work piece 1 foot The weekly fotal malerial handling cost of the layout S (entor your response as a whole number)
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: Assembly line helps in assigning each task to each workstation and worker, where no machine can be…
Q: For the following network diagram answer the questions below. Build Cabin 45 65 Finish house 6 4 20…
A: Critical path: The path which determines the efficient time to complete the project i.e. minimum…
Q: The following cost information pertains to the new CD: CD package and disc (direct material and…
A:
Q: Trinity Valley Furniture Warehouse has purchased a retail outlet with six departments, as shown…
A: Given data is, Department size - 30ft height and length The present layout and load customer for one…
Q: 1. Transportation costs per ton of product vary with distance. For trucks the function is: TCt =…
A: d Trucks Rail Barge Function: 3 + 1.25d 5 + d 6 + 1.1d 1 4.25 6 7.1 2 5.5 7 8.2 3 6.75 8 9.3…
Q: Q3. Complete the following iteration tableau of Maximization problem of LPP and comment on the…
A: Given information, Cbi Basic variable 2 1 0 0 0 Solution X1 X2 S1 S2 S3 2 X1 1 0 -1…
Q: A firm is selling two products—chairs and bar stools—each at $50 per unit. Chairs have a variable…
A: Break-Even point is a point where the position of the organization is neither it incurs any loss nor…
Q: Colete Trucks, Inc., a builder of high quality road cement has about 5,000 items in its inventory.…
A: Stock-taking or "inventory checking" or "one end to the other" actual confirmation of prices and…
Q: Sketch a precedence diagram of the above activity ii. Calculate the cycle time and the minimum…
A: As per the guidelines of Bartleby, only the first three questions have been answered. For getting…
Q: Three departments- milling (M), drilling (D), andsawing (S)- are assigned to three work areas in…
A: Given data is Cost of move = $2 per piece per foot
Q: Sunny Park Tailors has been asked to make threedifferent types of wedding suits for separate…
A: Scheduling refers to organizing and managing tasks of a particular process or a system. Scheduling…
Q: Problem 6-16 (Algo) The desired daily output for an assembly line is 540 units. This assembly line…
A: Given data is Desired output = 540 units Operating time = 630 minutes
Q: Sed and there is surplus hours plus in machine centre Z? A manufacturer of baby dolls makes three…
A: The objective is to maximize profit. Let A = Number of units of doll A B = Number of units of doll B…
Q: Wonderloaf Bakery has orders for five specialty jobs A, B, C, D, and E that must be processed…
A: Given data: Job orders received Hours remaining Processing time Banking Processing time…
Q: The demand for subassembly S is 90 units in week 7. Each unit of S requires 1 unit of T and 1 unit…
A: Gross Requirement: The term gross requirement is used for the material requirement planning…
Q: 5 departments are to be assigned to locations B-F in the grid. (For technical reasons, department 6…
A: From table 2, the work flow arrangement should be there in descending order i.e. highest to lowest.…
Q: Janelle Heinke, the owner of Ha’Peppas!, is consider-ing a new oven in which to bake the firm’s…
A: GIven Information: Oven Type A - Capacity = 20 pizzas in an hour Fixed Cost = $ 20,000 Variable…
Q: Refer again to Problems( Using the information in Problem(The demand for subassembly Sis 100 units…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: A product line manufacturing shoes, has five stations in series whose individual capacities per…
A: Station No 1 2 3 4 Individual Capacity 600 650 650 550 The capacity of the system is decided…
Q: 1. Solve Graphically: Max P = 3x+6y Subject to: x+ y<8 2.x+3y 2 18
A: Given Information: Max P = 3x + 6y Subject to: x + y ≤ 8 2x + 3y ≥ 18 To solve them graphically,…
Q: The Case: GIGI'S CATERING (B) Gigi was looking forward to taking on the opportunity to serve the…
A: Quality plays a very important role when it comes to a delivery of a particular good/ service to the…
Q: Let: X1=x and X2=y Let profit=z Refer to the image: 1. What is the value of Y? 2. What are the…
A: Given Information:
Q: Which of the two products should be given priority to maximize contribution margin? How much is the…
A: Introduction: The term Business refers to an exchange of goods and services between the buyer and…
Q: 4. How many human resource needs to be determined?5. What are the possible sources of applicants for…
A: ANSWER (4) Any organization's intended output will need a deliberate deployment of human resources…
Q: Applying the 100% rule, _______________ because the total change in the contraint right-hand sides…
A: With the given report, We can see the shadow prices and allowable increase, decrease ranges for the…
Q: A compony plants for produce Go,80, and 40 uni s during the next Hime period, produces a cUstomers.…
A: Below we are formulation the transportation model as an objective function-
Q: LPP Model Maximize P = 12x + 10y Subject to : 4x + 3y 0 Which of the following points (x, y) is…
A: Linear Programming Problem refers to the issue or problem generally concerned with the discovery of…
Q: 1. There's only one best layout for this line balancing problem. * a. True b. False . 2.Which of the…
A: 1. There's only one best layout for this line balancing problem. * a. True - It is because three of…
Q: Variable cells Cell Name Final Value Reduced Cost Objective Coefficient Allowable Increase…
A: The objective function in a numerical advancement issue is the genuine esteemed function whose worth…
Q: For the following network diagram answer the questions below. Build Cabin 45 65 4 Finish house" 20…
A: AS per the Network Diagram following format used for drawing: Early Start (ES) Early Finish…
Q: 12. The stimulus above is an example of: A. Fixed position layout B. Product layout C. Process…
A: Facility layout is an ordering of various phases of manufacturing in a proper way to obtain wanted…
Q: Supertronics, Inc., would like to know how the firm’s profit-ability is altered by product mix.…
A: Given information, A B C D Price 350 320 400 500 Material Cost 50 40 125 150 Weekly…
Q: Based on the following sensitivity report, how much should the firm be willing to pay for 53 more…
A: Given, Shadow price = 1.11Resource C willing to pay = 53 units
Q: Capacity decisions often determine capital requirements and therefore a large portion of fixed cost.…
A: The potential of producing and conveying commodities in a predetermined time is known as Capacity.…
Q: Compute for the cycle time
A: Cycle time is a specific Unit time which indicating that the company must produce one product for…
Q: Exercise 6: The Good Furniture makes two products: tah les and chairs, which mustbe processed…
A: 6) The objective function Max (180X + 100Y) Subject to 4X + 2Y <= 60…
Q: lease solve D only (a) What is the cycle time necessary to achieve the desired rate of production?…
A: Demand =30,000 units per year
Q: A manager must decide which type of equipment to buy, Type A or Type B. Type A equipment cost…
A: Capacity refers to the total amount of units a firm is producing during a given period of time while…
Q: Sunny Park Tailors has been asked to make three dif-ferent types of wedding suits for separate…
A: In scheduling primary objective is to find optimal sequence for job and reduce time also reduces…
Q: Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1…
A:
Q: Exhibit 1. Solver Sensitivity Report. A B C D E F H 6 Variable Cells 7 Final Reduced Objective…
A: Find the Given details below:
Q: Refer again to Problem ( Using the information in Problem (The demand for subassembly Sis 100 units…
A:
Q: How does Goldratt’s Theory of Constraints (TOC) differ from other current approaches to continuous…
A: Note:-We are authorized to answer one question at a time, since you have not mentioned which…
Q: The balance in Supplies before adjustment is $1,900. A physical count reveals $300 of supplies on…
A: In the above question we have to put in excel in Dr and Cr under account name. Please find the…
Q: Problem (1): For a vending machine project, the site cost = 12,000 SR/month, material cost 1…
A: Here, We have received following information, these are as stated below: Fixed cost as applied to a…
Q: Alan Industries is expanding its product line to include three new products: A, B, and C. These are…
A: Formulate a spreadsheet s shown below to get the answer. note: to make sure that each month demands…
Q: James Lawson’s Bed and Breakfast, in a small his-toric Mississippi town, must decide how to…
A: Expected monetary value is the technique which is used to quantify the risks as well as compute the…
Q: The demand for subassembly Sis 100 units in week 7.Each unit ofS requires 1 unit ofT and 2 units…
A:
2
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Green Grass’s plant manager just received marketing’s latest forecasts of Big Broadcaster sales for the nextyear. She wants its production line to be designed to make 2,400 spreaders per week for at least the nextthree months. The plant will operate 40 hours per week.a. What should be the line’s cycle time?b. What is the smallest number of workstations that she could hope for in designing the line for thiscycle time?c. Suppose that she finds a solution that requires only five stations. What would be the line’s efficiency?You have just been hired as the director of operationsfor Reid Chocolates, a purveyor of exceptiona lly finecandies. Reid Chocolates has two kitchen layouts under considerationfor its recipe making and testing department. The stra tegyis to provide the best kitchen layout possible so that foodscientists can devote their time and energy to product improvement,not wasted effort in the kitchen. You have been asked toevaluate these two kitchen layouts and to prepare a recommendationfor your boss, Mr. Reid, so that he can proceed to placethe contract for building the kitchens. [See Figure 9.20(a), andF igure 9.20(b).)Th e town barber shop can accommodate 35 customers perday. Th e manager has determined that if two additional barbersare hired, the shop can accommodate 80 customers per day. Whatare the design and eff ective capacities for the barber shop?
- The Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats for240 minutes per day. Given the information in the table,a) Draw the precedence diagramb) Fins the minimum number of workstations needed to produce the required daily demand.c) What is the efficiency of the assembly lined) What is the idle time per boat producede) Assign the tasks to workstations using the most follower methodf) What is the maximum theoretical capacity this line can achieve in 240 minutesGordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A − 4 10 8 B − − 5 9 C − − − 9 D − − − − Workpieces moved per week between work areas are: A B C D A − 900 700 600 B − − 400 300 C − − − 600 D − − − − It costs Gordon $3 to move 1 work piece 1 foot. The weekly total material handling cost of the layout =....... $nothing (enter your response as a whole number). The weekly total material handling cost of the layout =....... nothing dollars (enter your response as a whole number).Table 10-23 shows the tasks required to assemble analuminum storm door and the length of time needed to completeeach task. (a) Calculate the cycle time needed to produce 480 doors inan eight-hour work day.(b) What is the minimum number of workstations that can beused on the line and still achieve the desired productionrate? Balance the line and calculate its effi ciency.(c) What is the maximum output possible with these data?Th e minimum?
- A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table iden-tifies the work elements, times, and immediate predecessors: a. What is the desired cycle time (in seconds)?b. What is the theoretical minimum number of stations?c. Use trial and error to work out a solution, and show your solution on a precedence diagram.d. What are the efficiency and balance delay of the solution found?1. There's only one best layout for this line balancing problem. * a. True b. False . 2.Which of the potential layouts shown above should be recommended? * a. Layout A b.Layout B c.Layout C d. Layout D e. None of the above . 3.What is the efficiency of the production line? * a. 100% b. 85% c. 95.83% d. Cannot be determined e. 76.67%Adam Munson Manufacturing, in Gainesville, Florida, wants to arrange its four work centers so as to minimize interdepartmental parts handling costs. The flows and existingfaci lity layout are shown in Figure 9.1 9. For example, to move a part from Work Center A to Work Center C is a 60-foot movement distance. It is 90 feet from A to D. a) What is the " load X distance," or "movement cost," of the layout shown?b) Provide an improved layout and compute its movement cost.
- (a) What is the cycle time necessary to achieve the desired rate of production?(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance?(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.Subject: Logistic management calculate efficiency? If Design capacity is 180 cars per shift And they are producing 65 cars per shift 9 hours shift which include 1 hour break for lunch n NamazWhat is ment by hybrid layouts explain.?