Homework3: Draw the network diagram by using AOA technique for the following activities, define the located activities on the critical path, define the total project duration, and find all of ES, EC, LS, LC, TF, and FF. Activity Precedent Activity Time (Week) A ---- A, D, H B, D, H C 4 D A 6. E A 5 C. D,E C, F G 4 H A H J G, I

Algebra & Trigonometry with Analytic Geometry
13th Edition
ISBN:9781133382119
Author:Swokowski
Publisher:Swokowski
Chapter9: Systems Of Equations And Inequalities
Section9.3: Systems Of Inequalities
Problem 15E
icon
Related questions
Question
i need the answer quickly
Homework3: Draw the network diagram by using AOA technique for the following
activities, define the located activities on the critical path, define the total project
duration, and find all of ES, EC, LS, LC, TF, and FF.
Activity
Precedent Activity
Time (Week)
A
7
A, D, H
B, D, H
B
5
C
4
D
6
E
A
5
C, D, E
C, F
F
6.
G
4
H
A
8
I
H
J
G, I
9.
Transcribed Image Text:Homework3: Draw the network diagram by using AOA technique for the following activities, define the located activities on the critical path, define the total project duration, and find all of ES, EC, LS, LC, TF, and FF. Activity Precedent Activity Time (Week) A 7 A, D, H B, D, H B 5 C 4 D 6 E A 5 C, D, E C, F F 6. G 4 H A 8 I H J G, I 9.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage
Big Ideas Math A Bridge To Success Algebra 1: Stu…
Big Ideas Math A Bridge To Success Algebra 1: Stu…
Algebra
ISBN:
9781680331141
Author:
HOUGHTON MIFFLIN HARCOURT
Publisher:
Houghton Mifflin Harcourt