How much must be shown as current asset (cost of uncompleted contract in excess of billings) in the balance sheet of SM Development as of December 31, 2018?

SWFT Comprehensive Volume 2019
42nd Edition
ISBN:9780357233306
Author:Maloney
Publisher:Maloney
Chapter16: Accounting Periods And Methods
Section: Chapter Questions
Problem 40P
icon
Related questions
Question
To answer, please refer to the picture. Question: How much must be shown as current asset (cost of uncompleted contract in excess of billings) in the balance sheet of SM Development as of December 31, 2018?
COst to
7. SM Development commenced doing business on January 1, 2018. Construction
activities for the first year of operations are shown below:
All contract costs are with different customers and any work remaining at
December 31, 2018, is expected to be completed in 2019.
Cash
Contract
costs incurred additional
through
12/31/2018
Estimated
Billings
through
12/31/2018 12/31/2018
P2, 000,000 P1, 800,000 P2, 480,000
1,130,000
2,800,000
350,000
2.050.000
P8.300.000
collection
Total
Contract
Price
through
costs to
Project
complete
P 670,000
2,712,000
-0-
P3, 000,000
3,500,000
2,800,000
2,000,000
2,400.000
P13,700,000
How much must be shown as current asset (cost of uncompleted contract in
1,050,000
2,550,000
1,230,000
2.000.000
P7.650,000 P8,098.000
678,000
1,860,000
1,230,000
1.850.000
870,000
150.000
P4.402,000
excess of billings) in the balance sheet of SM Development as of December 31, 2018?
a. РО
b. P880,000
c. P 1,280,000
d. P400,000
PABCDE
Transcribed Image Text:COst to 7. SM Development commenced doing business on January 1, 2018. Construction activities for the first year of operations are shown below: All contract costs are with different customers and any work remaining at December 31, 2018, is expected to be completed in 2019. Cash Contract costs incurred additional through 12/31/2018 Estimated Billings through 12/31/2018 12/31/2018 P2, 000,000 P1, 800,000 P2, 480,000 1,130,000 2,800,000 350,000 2.050.000 P8.300.000 collection Total Contract Price through costs to Project complete P 670,000 2,712,000 -0- P3, 000,000 3,500,000 2,800,000 2,000,000 2,400.000 P13,700,000 How much must be shown as current asset (cost of uncompleted contract in 1,050,000 2,550,000 1,230,000 2.000.000 P7.650,000 P8,098.000 678,000 1,860,000 1,230,000 1.850.000 870,000 150.000 P4.402,000 excess of billings) in the balance sheet of SM Development as of December 31, 2018? a. РО b. P880,000 c. P 1,280,000 d. P400,000 PABCDE
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage