I) For the following precedence and determine the project duration. Highlight the critical path, and show the ES, EF, LS, LF, TF, and FF for activities B, K, and M, on the scheme. Assume a Finish-to-Start (FS) relationship with zero lag/lead time unless otherwise show
Q: What makes cost estimating such a crucial part of project planning? Discuss how it relates to the…
A: Estimation of costs: The practice of estimating the price and other resources needed to complete a…
Q: i. Discuss the concept of Critical Path in project scheduling? Outline how this is identified and if…
A: 1. Critical Path One of the most often used project planning strategies is the critical route…
Q: Calculate the critical path for this project The Critical path is _______________ and the project…
A: The critical path is the path that takes the longest time to complete the project network.
Q: As the pandemic waned, an educational institution was faced with the imperative of refurbishing and…
A: Find the Given details below: Activity ImmediatePredecessors Time(Days) A - 2 B A 5 C A 2…
Q: Typically, a project is a one-time action that must be finished within a specified time frame? why?
A: Projects are kind of company goals and objectives that are defined at a temporary stage for some…
Q: . Identify the critical path. . Develop the activity schedule for the project. If your answer is…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Consider the following project: Activity Immediate Predecessor A- B- CA, B DA, C Based on the list…
A: Given data:
Q: ffing related to each stage of the project life cycle?
A: Phases may be used by project managers or the organization as a way to better manage projects and…
Q: As the pandemic waned, an educational institution was faced with the imperative of refurbishing and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Discuss the ethical considerations associated with completting a project in the shortest possible…
A: Three things that drive ethical conduct are responsibility, honesty, and respect, which has been…
Q: Calculate the total float, free float and independent float for the project whose activities are…
A: Given data is
Q: Why are a forward pass and a backward pass needed toproduce a project schedule?
A: Project management is the process of putting processes, techniques, skills, information, and…
Q: This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: First we will draw the project network diagram. Initial activities are A, B, and C. After that we…
Q: Determine the critical path(s) and slack time for non-critical activities for the project as shown…
A: CPM stands for Critical Path Method, which was invented by DuPont and was first used in the chemical…
Q: 1- Calculate the total project time and floats 2- Identify activities on the critical path
A: In this question table data, we have activity information, for each activity, we have been given…
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Discuss the ethical considerations associated with completing a project in the shortest possible…
A: The ultimate goal of project management is to achieve all the project objectives within the given…
Q: In a group, identify the major activities involved in the project and sequence them in the proper…
A: Project activities are divided into sub-tasks that must be completed in order for the activity to be…
Q: prepar precedence are presented in the table below. Three time estimates (in weeks) are given for…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: PERT analysis computes the variance of the total projectcompletion Lime as:a) the sum of the…
A: The correct option is :
Q: Please Answer the following questions: - How does earned value give a clearer picture of project…
A: 1.) An Earned value helps in linking actual cost as well as schedule cost with the planned cost in…
Q: If the project is to be fin ished in a shorter amount of time, what is the best way to accomplish…
A: Especially if they aren't acquainted with the labor involved, people often underestimate the time…
Q: What is the critical path for the actvities and how many days will the project take?
A: Here is Your Step Wise Solution:
Q: PERT analysis computes the variance of the total projectcompletion time as:a) the sum of the…
A: Leadership style is the approach of providing direction, plans implementation, and motivating…
Q: Why should project teams take the time to determine the critical path for a project?
A: Generally critical path is using in projects because to track the project progress and budgeting By…
Q: In reference to the attached image: Draw the project network, and determine the normal time to…
A: Network diagram is prepared using the forward and backward path analysis, This diagram is presented…
Q: Calculate the slack for each activity and determine the critical path. How long will the project…
A: The critical path is shown by double arrow 1)A->B->C->F->G
Q: If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: Nhat is the overall duration of the project (in weeks)? 32 weeks Nhat is the earliest week you could…
A:
Q: If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days,…
A: Network diagram is prepared using the forward pass method and backward pass method, with having such…
Q: Why is the critical path important? Why would a task be on the critical path? 2) What is the role…
A: Hi, we are supposed to answer one question at a time. Since you have not mentioned which question to…
Q: i. Draw the network of the project. ii. Determine the slack/floats of each sensitivity iii. As a…
A: THE ANSWER IS AS BELOW:
Q: · Construct the project network comprised of activities A to P that satisfies the following…
A: Given data is
Q: Identify and elaborate on the problems experienced with the project described in the article.
A: project issue is an occasion or condition that has adverse results for an undertaking. The term…
Q: The business case is critical in project management; explain what that means.
A: A business case generally provides the justification for undertaking a project through evaluating…
Q: Which activities or tasks are crucial to the project-that is, which activities will cause the entire…
A: In project management, the critical path analysis enables us to find the most effective schedule for…
Q: critical path is __________ and the project duration is _____________
A: A network diagram is a graphical representation of a project which helps to identify the project…
Q: Discuss the necessity of project scheduling as well as the obstacles that come with it. As…
A: Project scheduling:- A schedule is a plan that helps organize and control tasks, resources, and…
Q: Discuss the ethical consideration associated with completing a project in the shortest possible…
A: The eventual aim of project management is to successfully accomplish all project objectives within…
Q: If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And…
A: Given data is
Q: Find the project's total duration, and described the completion of the project activities after the…
A: ANSWER IS AS BELOW:
Q: What is the ES for Activity D? What is the LF for Activity E? What is the slack for the start of…
A: Below is the solution:-
Q: 1. When is the earliest project completion? 2. Which activities are critical (should not be…
A: This question is related to the topic of project management and this topic falls under the…
Q: Which activities can be delayed?
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Step by step
Solved in 2 steps with 1 images
- 114. Duration Task Estimates A ABCDE F 2 5 1 2 3 12 Click here for the Excel Data File Req B1 b-1. Identify the critical path. b-2. Identify the earliest start and finish. Task b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely? OUM TI Complete this question by entering your answers in the tabs below. D days days day F E F E F C days days days B A Immediate Predecessors None Identify the slack for each task. Note: Leave no cells blank - be certain to enter "0" wherever required. None A B A B and D E and C C, E B, D Immediate Successors Req B2 Req B3 Req C Latest Completion Latest Start (LS) SlackPlease complete the ES, EF, LS, LF, and slack for the project below. Activity Description Duration (weeks) Immediate predecessors ES EF LS LF Slack A Contract negotiation with selected vendors 3 - B Decide on the best data extraction platform and begin software coding 5 C C Contract negotiation with package and label manufacturers 2 - D Screen and hire transportation personnel 3 - E Market logistic arrangements 1 A F Organize advertising brochures and campaign print ads 4 D G Logistical arrangements for sales representatives 1 E H Target market final arrangements 3 C, D I Finish the final production process 5 F, H J Hire additional sales staff, and make sales demonstration arrangements 4 E, B, H K Distribute media advertising packages and arrange for commercial distribution 5 G L Arrange sales tracking and monitoring 2 FTask Predecessor Duration A Start 3 B Start 5 C B 8 D A, C 12 E C 7 F D, E 9 Given the requisite information above, what is the critical path duration? What are some mechanisms for “crashing” a project.
- 1. What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and discuss how it can be determined? 3. What are the three time estimate used in the Critical Path Method? Why is it important to have three different time estimates?#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…
- (Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached chart and diagram. 1. Set the Project start on Monday 11/1/20. Thursday 11/26/20, Friday 11/27/20, 12/25/20, and 1/1/21 are holidays. 2. Determine critical path and its duration. When the project will end (date)? 3. There is a possibility that the starting task K may be delayed by 3 days. Will this impact the project completion date? If yes, when will be the new finish date? (After checking this out, please restore the project to its original schedule). 4. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first).Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…Using the information in Table-1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (WorkingDays) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H (i) Determine the critical path of the project (ii) Calculate the planned duration of the project in weeks (iii) Identify any non-critical tasks and the float (free slack) on each.
- 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?Show the project schedule by drawing Gant Chart in Microsoft excle for the given data:- (10) Activity Name Preceding activity Activity Time (Hours) B - 18 A B 8 C A,B 2 D A,C 6 E D 5 F C 9 G D,C 4 H F,G 11As the pandemic waned, an educational institution was faced with the imperative of refurbishingand retrofitting its premises to facilitate reopening for blended modality in learning. Essential tasksincluded expanding certain spaces, fitting canteen tables with partitions and acquiring andinstalling equipment. A project manager was engaged to ensure readiness in three weeks.Information compiled on the project scope, such as activity times and relationships, is presentedbelow: Activity Immediate Predecessor Time (Days) A - 2 B A 5 C A 2 D A 6 E B 6 F C, D 3 G D…