  • Duration and requirement of workforce for each activity is tabulated below for a network

Activity

Duration

Number of men

1-2

3

5

2-4

2

3

2-3

3

7

3-4

0

0

3-5

3

2

4-5

7

2

3-6

2

1

5-6

6

6

4-6

5

5

 

 (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce

(ii) Indicate the maximum crew size in each case

(iii) Re-schedule the activities for smooth development

(iv)  Find the project schedule if only 4 men are available

Expert Solution
steps

Step by step

Solved in 6 steps with 2 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,