You are given the activity information below and the activity-on-node precedence diagram for a project at your company. (a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. (b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack LS- ES or LF- EF. Activity Immediate Time (days) Predecessor(s) A 7. --- 20 --- A А, В С, D E 8. F Е, F 9. H. F 8. C G Start Finish B D F H

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question
100%

Need help don't understand. Please include answers and explanation.

a) Fill in the table with each path and show your work by calculating the time
for each path in the table to determine the critical (longest) path(s).
Add/delete rows in the table as needed.
Path
Time
b) Fill in the ES & EF times in the table below working from Start to Finish.
Then, fill in the LS & LF times working backwards from Finish to Start.
After determining the ES, EF, LS, & LF times, calculate the Slack time for
each activity using both Slack = LS – ES and Slack = LF – EF. Note: Both
calculations must give you the same answers.
Activity
ES
EF
LS
LF
Slack
A
B
E
F
G
H
Transcribed Image Text:a) Fill in the table with each path and show your work by calculating the time for each path in the table to determine the critical (longest) path(s). Add/delete rows in the table as needed. Path Time b) Fill in the ES & EF times in the table below working from Start to Finish. Then, fill in the LS & LF times working backwards from Finish to Start. After determining the ES, EF, LS, & LF times, calculate the Slack time for each activity using both Slack = LS – ES and Slack = LF – EF. Note: Both calculations must give you the same answers. Activity ES EF LS LF Slack A B E F G H
You are given the activity information below and the activity-on-node precedence diagram for a
project at your company.
(a) Determine the critical path and its duration. What is your initial estimate for project
completion time? Show your work on the next page.
(b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest
finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack
for each project activity. Slack = LS - ES or LF - EF.
Activity
Immediate
Time (days)
Predecessor(s)
A
7
20
А, В
С, D
E
8.
F
4
Е, F
H
F
A
E
Start
Finish
В
F
H
Note: This page with the precedence diagram is posted as a separate
pdf also.
Continued on next page
98
Transcribed Image Text:You are given the activity information below and the activity-on-node precedence diagram for a project at your company. (a) Determine the critical path and its duration. What is your initial estimate for project completion time? Show your work on the next page. (b) Fill in the table on the next page to determine the earliest start (ES) time, the earliest finish (EF) time, the latest start (LS) time, the latest finish (LF) time, and the Slack for each project activity. Slack = LS - ES or LF - EF. Activity Immediate Time (days) Predecessor(s) A 7 20 А, В С, D E 8. F 4 Е, F H F A E Start Finish В F H Note: This page with the precedence diagram is posted as a separate pdf also. Continued on next page 98
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Social media marketing
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON