levelling network has been carried out from BM2530 (Reduced level: 49.11m) to BM2528 (Reduced level: 49.540m). Based on Table 4, find the final reduced level using rise and fall method.      Table 4 LINE BS IS FS

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter13: Slope Stability
Section: Chapter Questions
Problem 13.16P
icon
Related questions
Question
  1. A levelling network has been carried out from BM2530 (Reduced level: 49.11m) to BM2528 (Reduced level: 49.540m). Based on Table 4, find the final reduced level using rise and fall method.

     Table 4

LINE

BS

IS

FS

Remarks

1

2

3

4

5

6

7

8

9

10

1.717

 

2.918

 

0.816

1.436

1.246

 

 

 

1.432

 

2.272

 

 

 

1.353

1.462

 

 

 

1.716

 

0.953

3.005

1.391

 

 

0.628

 

BM 2530

A

B

C

D

E

F

G

H

BM 2528

 

Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Instruments for Surveying
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning