Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 3.00 During the year the company worked a total of 146,000 machine-hours on all jobs and incurred actual manufacturing overhead costs of $1,350,000. What is the amount of underapplied or overapplied overhead for the year? (Round your intermediate calculations to 2 decimal places.)
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Moody Corporation uses a |
Machine-hours required to support estimated production | 100,000 | |
Fixed |
$ | 650,000 |
Variable manufacturing overhead cost per machine-hour | $ | 3.00 |
During the year the company worked a total of 146,000 machine-hours on all jobs and incurred actual manufacturing overhead costs of $1,350,000. What is the amount of underapplied or overapplied overhead for the year? (Round your intermediate calculations to 2 decimal places.) |