Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follovs. Activity Time A 3 6 2 D 5 4 3 G 3 A E Start H Finish D B G
Q: - The mean number of air conditioning units assembled per month by Freeze, Inc. is 750 and the stand...
A: Given Information :- Mean (μ) =750, Standard Deviation (σ)=100 Break even point (BEP) = 500
Q: Cutey Barber Salon Cutey Barber Salon is a trendy barber salon that is located in a densely populate...
A: As lengthy as servicing times comprise an adverse impact for both client and service providers, Decr...
Q: - percent change in productivity for or no month thir vanr a multi nctor bn
A: Multifactor productivity indicating the proportion between total output and total input. Here, we wi...
Q: A manager is quite concerned about the recent deterioration of a section of the roof on a building t...
A: The decision tree is a strong and well-known method for separating and foreseeing. A decision tree i...
Q: 44. US Airlines receives an average of 500 calls per hourfrom customers who want to make reservation...
A: The following information is provided: The arrival rate is 500/hr The service rate is 20/hr Wage rat...
Q: 6.3) CASE STUDY: The last half decade has been an interesting one for General Motors (GM). Once a se...
A: Change management is described as a process that allows the introduction of transformation and trans...
Q: Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a) Toda...
A: The given information can be used as follows in order to prepare the gantt chart.
Q: The current date is day 275 and the following jobs are waiting to be processed at the same equipment...
A: Given-
Q: 1. A computer repair shop had received several complaints on the length of time it took to make repa...
A: As specified, I have solved the first question for you. Kindly find the solution from Step 2 onwards...
Q: Susan has just been hired as a professional SCUBA diver at a resort in Bali. She is a certified dive...
A: Productivity training is tied in with gaining more headway, significantly quicker. To accomplish you...
Q: Question attahed in image
A: Note: - As we can answer only up to three subparts we will answer the first three(a, b, and c) subpa...
Q: Malburn Construction Ltd. Manufactures and distributes window frames. The company uses 600,000 metal...
A: Note: - Since we can answer only up to three subparts we will answer first three subparts(1, 2, and ...
Q: John Doe, a fraud examiner, has been hired by ABC Corporation to investigate a shortage of cash, whi...
A: Business frauds are often called illegal activities or operations. Business fraud can be stated as a...
Q: data outright. As the purchaser you will have to utilize reverse price analysis, describe the formul...
A: For reverse pricing analysis, there is no one-size-fits-all method for determining the cost.
Q: How can robotics and automation improve the supply chain efficency in warehousing, distribution and ...
A: During the COVID-19 epidemic, enterprise warehouses struggled to keep up with the tremendous growth ...
Q: A newspaper stand operator has the following sales data for one- year sales of Fine magazine. Quanti...
A: Given below some of the calculations. Quantities sold per day No. of days quantity sold Profit fo...
Q: Chapter 8. In Problem Set 6, we worked on a problem for Flor’s Flours, a small business that produce...
A: From the given data: Let the decision variables be as shown below (all in lbs): Wheat Garba...
Q: A company makes two products, X and Y, using two machines, 1 and 2. Each unit of X that is produced ...
A:
Q: 4- George Kyparisis makes bowling balls in his Miami plant. With recent increases in his costs, he h...
A:
Q: Given the following list of items,(a) Calculate the annual usage cost of each item.(b) Classify the ...
A: The ABC analysis is the technique of inventory management that is used to identify the value of inve...
Q: A paper published in the Harvard Business Review points out a new way to calculate economic profit t...
A: An individual's productivity is how much work they can do in a given measure of time. It's a straigh...
Q: 5-17 Data collected on the yearly demand for 50-pound bags of fertilizer at Wallace Garden Supply ar...
A: Forecasting is the process of determining the estimated forecast for the future using the previous y...
Q: 1. Discuss project cost relative to project planning.
A: Project management is the management in which different types of skills and knowledge for the delive...
Q: The Average Lead Time is 10 days and the Average Daily Usage of widgets is 20. The company has deter...
A: Reorder point is described as the minimum number of units that any business or inventory needs to ha...
Q: ss how we, as construction manager, can avoid the delays in the construction. Use all theories neces...
A: You can frequently follow wild construction project costs back to a certain something: an inability ...
Q: g) Suppose that the profit contribution of component 3 decrease by $2.00 . Would the optimal solutio...
A:
Q: Discuss in detail the steps for Import of goods and equipment’s for a tertiary care teaching hospita...
A: A Small Introduction about Documentation The presentation ordinarily depicts the extent of the re...
Q: Identify and analyze one of the leading causes of hospital readmissions over the past 5 In your opin...
A: Hospital readmission is that the client will be getting admitted within 30 days after being discharg...
Q: Solve the game whose pay-off matrix is given by Player B B1 B2 B3 A1 1 3 Player A A2 -4 -3 A3 1 -1 1...
A: Game theory is a theoretical framework for conceiving social problems among competing players. Game ...
Q: The proposed Ghana Airways Airline project is being procured through a Public-Private Partnership (P...
A: Decision tree analysis can be stated as the approach of sketching or drawing a decision tree, which ...
Q: (a) What capacity plans do you think ESCOM should make for next year? Why? (6) What longer-term capa...
A: The following information is given: Year Forecast 0 100 1 140 2 195 3 27...
Q: Tyler bakes Cookies (C) and Breads (B) with the help of two ovens in his little bakery. The time tak...
A: since, the cookies and breads cannot be made in decimals, integer constraint will be kept to find th...
Q: The sensitivity range for an objective function coefficient is the range of values over which the op...
A: YES the statement is true. The sensitivity range for an objective function coefficient is the range ...
Q: A tender advert appeared in the print media on 12th March 2020 to run for four (4) weeks. A week fro...
A: The tender advertisement: It floated in the media on 12th March 2020 to run for 4 weeks. The tende...
Q: 4) The choice of technology revolves around two basic questions: (1) What is the desired amount of...
A: Choices of technology has important implications for capacity planning, facility layout, equipment c...
Q: With reference to project of an organization of your choice, describe how goods, works and services ...
A: Procurement is buying goods or services and is generally about business investing or spending. Busin...
Q: Managing quality is an important integral in operations management. In addition to being a critical ...
A: Quality is defined as an outcome, a feature of a product or service supplied to a client and the hal...
Q: Urgently need For a table manufacturing company, variable cost is $125.00 per Unit, rent is $2,537....
A: Contribution margin refers to the margin that gives clear picture about the aggregate amount of reve...
Q: eanie realizes that she has another project that needs to be completed by Saturday and wonders if sh...
A: A Small Introduction about Crashing Model The CRASH model has been proposed by Medical Research C...
Q: 1. A company that makes shopping carts for supermarkets and other stores recently purchased some new...
A:
Q: evelop a swot matrix for MacDonalds
A: SWOT is basically- S-strengths W-weaknesses O-opportunities T-threats
Q: Case Narrative: As a young investor with a moderate risk attitude, you consulted a financial adviser...
A: given, maximum PHP 650,000 DIAKOM TRAICING CURRENT = PHP 30 PER SHARE
Q: Max −A + 2B s.t. -2A + 3B ≤ 8 (Constraint 1) 6A - 2B ≤ 5 (Constraint 2) A + ...
A: a) Z is maximum when A = 1.4 and B = 3.6
Q: what is a turnkey contract what are advantage and disadvantages
A: Turnkey contracts are the type of contracts in which a contractor promises to build a project which ...
Q: With the use of a diagram, show (illustrate) the typical levels of uncertainty or project risks asso...
A: A project risk is a dubious occasion that could conceivably happen during a project. In spite of our...
Q: Explain the difference between past time focus and present time focus.
A: The difference between the past time focus and the present time focus can be stated as the conduct o...
Q: 10. Quarterly demand for Jaguar XJ8’s at a Tacloban Auto dealership is forecast with the equation, ...
A: Forecasting is used by companies to match supply with demand and to avoid opportunity costs issues. ...
Q: What does change management accomplish and what are the components of an effective change management...
A: As it is said that change is the law of nature so the business also undergoes number of changes on e...
Q: You have been asked to estimate the cost of 100 prefabricated structures to be sold to a local schoo...
A: Production costs mirror all of the costs associated with a company conducting its business while man...
Q: 12 A bill of lading that states"consigned toJ. Smith" is a ? A .short form bill of lading B.negoti...
A: A bill of lading is described as the document (legal) that is issued to a shipper by a carrier and i...
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 65 images
- You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1Given the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…
- A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN): a. The expected project completion time for this problem is and the standard deviation is . b. There is a 0.95 probability that the project will be completed by weeks. Activity Expected time Variance Critical? A 10 0.36 Yes B 7 0.11 No C 7 0.25 No D 3 0.48 Yes E 5 1.60 Yes F 7 0.69 No G 2 3.69 YesA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?
- The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty clause requiring the contractor to pay a penalty of $2000 for each week late. The project must therefore be expedited. The possible reductions and associated costs are shown in the table. Times in the table are given in weeks. Only activity 4 can be expedited two weeks. The other activities can be expedited one week. (a) Determine the critical path(s), the expected duration of the project, and the slack time for each activity (indicate value on network)? What is the total project cost with penalty included? (b) How could the project time be reduced to 11 weeks and what is the total project cost? Activity Immediate predecessor Normal time Expedited time Normal cost ($) Expedited cost ($) 1 - 4 3 5,000 6,900 2 - 2 2 3,000 3,000 3 1 5 4 7,000 9,200 4 2 6 4 9,000 11,000 5 2 5 4 6,000 7,800…Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?Based on the case below, answer the following questions:The duration for the project is two year. Recall that PV is the planned value, EV is theearned value, AC is the actual cost, and BAC is the budget at completion.PV = 38,000EV = 40,000AC = 36,000BAC = 220,000(a) What is the Cost Variance (CV), Schedule Variance (SV), Cost Performance Index(CPI), and Schedule Performance Index (SPI) for the project?
- You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost (Direct) Cost (Direct) A None 3 2 $300 $408 B A 3 3 $100 $100 C A 1 1 $200 $200 D B and C 3 2 $400 $550 E D 2 1 $500 $900 F E 3 3 $200 $200 G F 2 2 $200 $200 The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $408, 15 days they will be $350, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?A project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion time is 8. Optimistic Most Probable Pessimistic Activity Time (hr) Time (hr) Time (hr) A Floor sanding 3 4 5 B Paint mixing 0.5 1 1.5 C Ceiling painting 1 5.5 7 D Wall painting 1 2 9 E Floor buffing 1 2 3 What is the probability that the project can be completed within 9 hr.?Draw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and O