ombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.   In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:     Month 1 2 3 4 Quality control measures:                 Number of defects 201   179   140   98   Number of warranty claims 62   55   46   43   Number of customer complaints 118   112   95   74   Material control measures:                 Purchase order lead time 10 days 9 days 7 days 5 days Scrap as a percent of total cost 1%   1%   2%   3%   Machine performance measures:                 Machine downtime as a percentage of availability 5%   6%   6%   10%   Use as a percentage of availability 94%   91%   88%   84%   Setup time (hours) 10   12   13   14   Delivery performance measures:                 Throughput time ?   ?   ?   ?   Manufacturing cycle efficiency (MCE) ?   ?   ?   ?   Delivery cycle time ?   ?   ?   ?   Percentage of on-time deliveries 95%   94%   91%   88%     The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:     Average per Month (in days) 1 2 3 4 Wait time per order before start of production 9.0 10.9 12.0 14.0 Inspection time per unit 0.9 0.8 0.8 0.8 Process time per unit 3.2 2.7 2.0 1.1 Queue time per unit 3.6 5.0 6.6 8.4 Move time per unit 0.3 0.6 0.6 0.7   Required: 1-a. Compute the throughput time for each month. 1-b. Compute the manufacturing cycle efficiency (MCE) for each month. 1-c. Compute the delivery cycle time for each month.   3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE. 3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE. Subparts 3a and 3b only

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.

 

In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:

 

  Month
1 2 3 4
Quality control measures:                
Number of defects 201   179   140   98  
Number of warranty claims 62   55   46   43  
Number of customer complaints 118   112   95   74  
Material control measures:                
Purchase order lead time 10 days 9 days 7 days 5 days
Scrap as a percent of total cost 1%   1%   2%   3%  
Machine performance measures:                
Machine downtime as a percentage of availability 5%   6%   6%   10%  
Use as a percentage of availability 94%   91%   88%   84%  
Setup time (hours) 10   12   13   14  
Delivery performance measures:                
Throughput time ?   ?   ?   ?  
Manufacturing cycle efficiency (MCE) ?   ?   ?   ?  
Delivery cycle time ?   ?   ?   ?  
Percentage of on-time deliveries 95%   94%   91%   88%  

 

The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:

 

  Average per Month (in days)
1 2 3 4
Wait time per order before start of production 9.0 10.9 12.0 14.0
Inspection time per unit 0.9 0.8 0.8 0.8
Process time per unit 3.2 2.7 2.0 1.1
Queue time per unit 3.6 5.0 6.6 8.4
Move time per unit 0.3 0.6 0.6 0.7

 

Required:

1-a. Compute the throughput time for each month.

1-b. Compute the manufacturing cycle efficiency (MCE) for each month.

1-c. Compute the delivery cycle time for each month.

 

3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE.

3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE.

Subparts 3a and 3b only

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.