Deforrest Marine Motors manufactures engines for the speedboat racing circuit. As part of their annual planning cycle, they forecasted demand for the next four quarters. The number of available days of production and the anticipated demand are given below.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 46P
icon
Related questions
Question
If management at Deforrest Marine Motors is interested in a level strategy with their current employees using overtime and
subcontracting when demand cannot be balanced with inventory, what is the total cost of this plan?
6,099,200
Transcribed Image Text:If management at Deforrest Marine Motors is interested in a level strategy with their current employees using overtime and subcontracting when demand cannot be balanced with inventory, what is the total cost of this plan? 6,099,200
Deforrest Marine Motors manufactures engines for the speedboat racing circuit. As part of their annual planning cycle, they forecasted
demand for the next four quarters. The number of available days of production and the anticipated demand are given below.
Employees
Production Rate
Production Cost
Backorder Cost
Overtime Cost
Overtime Limit
Demand
Q1
2,400
6,019,000
They also estimated many of the costs required to conduct operations planning. Some of these key figures are listed below.
30
70 units/employee/quarter
Q2
2,200
$1,000/unit
$200/unit/quarter
$1,500/unit
<= 25% of Reg. Production
Q3
1,700
Q4
1,800
Hire Cost
Fire Cost
Subcontracting Cost
Subcontracting Limit
Inventory Cost
Initial Inventory
$1,200/employee
$800/employee
$1,800/unit
400 units maximum
$100/unit/quarter
280 units
Deforrest Marine Motors wishes to maintain the current number of employees for the entire year to follow a level strategy balanced with
inventory and backorders as needed. What is the total cost of this plan?
Transcribed Image Text:Deforrest Marine Motors manufactures engines for the speedboat racing circuit. As part of their annual planning cycle, they forecasted demand for the next four quarters. The number of available days of production and the anticipated demand are given below. Employees Production Rate Production Cost Backorder Cost Overtime Cost Overtime Limit Demand Q1 2,400 6,019,000 They also estimated many of the costs required to conduct operations planning. Some of these key figures are listed below. 30 70 units/employee/quarter Q2 2,200 $1,000/unit $200/unit/quarter $1,500/unit <= 25% of Reg. Production Q3 1,700 Q4 1,800 Hire Cost Fire Cost Subcontracting Cost Subcontracting Limit Inventory Cost Initial Inventory $1,200/employee $800/employee $1,800/unit 400 units maximum $100/unit/quarter 280 units Deforrest Marine Motors wishes to maintain the current number of employees for the entire year to follow a level strategy balanced with inventory and backorders as needed. What is the total cost of this plan?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L