Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource. On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, C and D all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which should be started first?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource.

On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, C and D all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which should be started first?

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same
resource.
Activity Duration (days) Predecessor
A
B
15
A
10
A
D
5
A
E
5
B, C, D
On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource-
constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, Cand D
all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which
should be started first?
Either activity B or activity D
O Activity C
O Activity D
O Activity B
Both activities Cand D
Transcribed Image Text:Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource. Activity Duration (days) Predecessor A B 15 A 10 A D 5 A E 5 B, C, D On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource- constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, Cand D all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which should be started first? Either activity B or activity D O Activity C O Activity D O Activity B Both activities Cand D
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.