Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami Cut bread 0.75 minutes 0.75 minutes 0.75 minutes Grill 1.4 minutes 1.4 minutes Slice meat 3 minutes Toast 2 minutes 2 minutes 2 minutes Wrap 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no mattor which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. (a) What is the implied utilization of each of the five steps in this process? 62.5 % 93.3 % 50.이% 83.3 % 41.7 % Cut Grill Slice Toast Wrap (b) What is the actual and maximum flow rates of the three sandwich types? per hour Veg Chicken per hour
Q: A hospital emergency room (ER) Is currently organized so thất all patients register through an…
A: Here now we assume a stable system. IT shows that average inflows equal average outflow at every…
Q: In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 11.5…
A: Given, Waiting time before the start of the batch = 2 hours Setup time = 2 hours Waiting time for…
Q: For a food-processing plant such as Kraft Foods, capacity refers to the number of employees working…
A: Introduction: The term Business refers to an exchange of goods and services between the buyer and…
Q: In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 12.75…
A: Find the given details below: Given details: Flow time 12.75 hours Waiting time before…
Q: Drivers are trained in a process with two resources (workers in each resource work independently).…
A: Given that: Drivers are trained in a number of processes = 2 Processing time of the first resource =…
Q: A machine used for cutting materials in a factory has the following outputs per hour at various…
A: Given data is Output by speed A = 200 pieces every 8 hours Output by speed B = 280 pieces every 5…
Q: (a) Develop a sequence using SPT based on processing time for preparing the area.
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: 18Every company has a Bottleneck True False 19Capacity of each sequence in a process is independent…
A: The detailed solution is given in Step ahead.
Q: You observe a bank and notice that a customer leaves the bank about every five minutes.These five…
A: Cycle Time is the time taken by an individual unit under the process. Cycle time can always be…
Q: A manufacturing company produces four parts that require the use of a lathe and a drill press. The…
A: Let us assume that Xj is the number of Part-j that is to be produced for j=1,2,3,4 & Also, let…
Q: Consider the system with one server at each of the stations A and B as before, and two identical…
A: Below is the solution
Q: CodeDeskInc matches programmers with freelance jobs. It has 30 employees who staffits online chat…
A: Active chat sessions=Average request per hour×Chat session timeMinutes per hour=240×560=20
Q: If a flow unit type j does not consume any time at a resource i, the corresponding cell inthe…
A: The corresponding cell of the type j cell in the workload matrix, which is referred as WL (i, j)…
Q: a) The Operations Manager at Metal Fabricators must decide the sequence in which the four Block…
A: Given, Machine Number EstimatedMaintenance days Time to promised delivered FCFS Order…
Q: The magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two…
A: Formula:
Q: Consider a production line with five stations. Station 1 can produce a unit in 8 minutes. Station 2…
A: This question is related to the topic-Production Management and this topic falls under the…
Q: Given this set of daily service operation, assuming a processing order of A-B-C-D-E; Determined the…
A: If four cycles are used, then the inventory size of the operation can be minimized and be more…
Q: A manufacturing company has a small production line dedicated to the production of a particular…
A: Given data is Station Output Station 1 2700 Station 2 2500 Station 3 2300 Station 4 2100
Q: Panini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken,…
A: Following formula can be used to calculate implied utilization rate: Firstly, the workload needs to…
Q: 20 ______ are high-volume product processes that typically produce standardized products and require…
A: Note: We'll answer the first question since the exact one wasn't specified. Please submit a new…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: It is commonly represented in "hours" and refers to the output capacity of employees or machinery.…
Q: Students are going through a three-step process to obtain their ID cards. Each student will first…
A: To be calculated: Time is taken to process 10 students Given values: A 3-step process Process 1 -…
Q: A manufacturing company has a small production line dedicated to the production of a particular…
A: Operation management in an organization aims at providing the highest efficiency possible. It…
Q: The maximum cycle time is the time of the longest task when the tasks are running in parallel. O a…
A: Answe is option (a)
Q: Customers are served in a process with two resources. The first resource has a capacity of 45…
A:
Q: Kinga Doll Company manufactures eight versions of its popular girl doll, Shari. The company operates…
A: Given: a). Batch size = 475 dolls Capacity expressed in number of dolls per hour The processing…
Q: Consider the system with one server per station. What is this system's capacity? What is the cycle…
A: Below is the solution
Q: Why is it important to view a batch-process operation as a network of interconnected queues?
A: Batch process operation is a type of operation in which a fixed no. inputs are loaded into the…
Q: A bottled water production process is described by the following flowchart. Production Setup 40…
A:
Q: Applications are scanned in a process with two resources. The first resource has a capacity of 0.38…
A: GIven Information: Capacity for the first resource: 0.38 applications per minute Capacity for the…
Q: What is the maximum output number per week?
A: The process capacity is the ability to produce maximum output from the available resources and…
Q: Consider a production line with five stations. Station 1 can produce a unit in 10 minutes. Station 2…
A: The bottleneck is a situation that often occurs in the production processes of the manufacturing…
Q: Super Fun Industries manufactures four top-selling toys code-named A-148, B-356, B-457, and C-843.…
A: Here, we could see that the company is manufacturing four types of toys, I would determine the total…
Q: Applications are scanned in a two step process with two resources. The processing time at the first…
A: For question 1: Arrival rate = 19 patients per hour Service rate = 18 patients per hour
Q: Chairs are made in a process with a single resource. There are two types of chairs. The resource's…
A: Given - The demand and capacity for the resource - D1 = 2.3 per hour and D2 = 2.8 per hourS1 = 2 per…
Q: The time from when a patient is discharged from NorthShore Hospital to the time the discharged…
A: Solution a) The x-chart in conjunction with an R-chart is drawn by calculating following limits-…
Q: At a cruise ship terminal, each day on average 1000 passengers embark on ships. Onaverage,…
A: Given Information: Number of passengers embark on ships daily = 1000 passengers per day Time spent…
Q: There are 3 servers in the checkout area. The interarrival time of customers is 2 minutes. The…
A: The normal circle back of giving customer service is vital to any service-situated business.…
Q: The magnetic resonance imaging (MRI) unit of St Francis hospital has 2 MRI machines and sees two…
A: Following formula can be used to calculate implied utilization rate: Given Information: No. of…
Q: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and…
A: Given data is Number of tasks = 9 Number of workers = 3 Task Processing time 1 60 2 70 3 25…
Q: Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843.…
A: Total plant capacity=16hrs×5days+8hrs=88 hrs =88×60=5280 minFor 1 unit of toy A-148 time required…
Q: Posh Nails Katie Posh runs an upscale nail salon. The service process includes five activities that…
A: The wages that are incurred for buying the goods and services to the customer is known as direct…
Q: Does increasing the capacity of a resource ever increase the arrival rate to the resource group that…
A: Increasing the ability of resources often improves the flow of the operation. By increasing power,…
Q: Suppose for a particular process that the bottleneck cycle time is 54 seconds, and raw processing…
A: We have joined after 4 customers, hence there are a total of 5 customers in the system now
Q: The bottleneck resource in a process has the least idle time. True or false?a. Trueb. False
A: The bottleneck resource in a process has the least idle time.
Q: The help desk at Triple Stacked handles calls from customers regarding their high-end industrial…
A: Implied UtilizationMatches the demand with capacity and it Can be higher than the 100% Implied…
Q: Callers are helped in a process with two sequential resources. The capacities of the resources are 1…
A: Given, Two resources which are in series. So, the lower capacity will be bottleneck. Capacity of…
Q: If value for an airline passenger is defined as reaching from point A (departure terminal of home…
A: The steps that an airplane company can follow to minimize the total time from departure terminal A…
Q: In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 14.35…
A:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Raquel’s Landscaping Company has contracted for several landscaping jobs. Each job requires preparing the areas (identifying the locations and types of plants, preparing the soil, etc.) and then planting the trees, bushes, and shrubs. The expected time for each of the jobs is shown next. Job Preparingthe Area (days) Planting(days) R 3 2 S 1 3 T 4 5 U 8 5 V 6 4 W 4 3 Raquel is concerned with efficiency. She believes it is probably more efficient to use SPT (shortest processing time) as her priority rule. (a) Develop a sequence using SPT based on processing time for preparing the area. (If two of more jobs have the same processing time, list them alphabetically.) Preparing the Area select a job select a job select a job…Consider a two-step process that handles three types of customers. Each resourceis staffed by one employee. Type 1 customers spend 5 minutes at resource 1 and 2 minutesat resource 2. Type 2 customers also spend 5 minutes at resource 1, but spend 10 minutes atresource 2. Finally, type 3 customers spend no time at resource 1 and 8 minutes at resource2. Each hour, the demand is 10 customers of type 1, 4 customers of type 2, and 2 customers oftype 3. Where in the process is the bottleneck? What is the flow rate for each customer type?A factory has two stations, station X and station Y. There are two different types of units, flow units A, and flow units B. The table below includes details about how long each unit type spends at each station: Flow Unit A Flow Unit B Station X 6 min 5 min Station Y 15 min 4 min The demand rate: Flow units A: 10 units per hour. Flow units B: 15 units per hour There are 4 machines at station X and 2 machine at station Y. What is the flow rate for unit B?
- A book binder has one printing press, one binding machine and manuscripts of 7 different books. The times required for performing printing and binding operations for different books are shown below. Book 1 2 3 4 5 6 7 Printing time (hours) 20 90 80 20 120 15 65 Binding time (hours) 25 60 75 30 90 35 50 Decide the optimum sequence of processing of books in order to minimize the total time required to bring out all the books.Can you check my work and tell me why I am not getting the answer $9100? Model Inc. has to transport 100 bags of Type Abags, 100 bags of Type B bags, and 100 bagsof Type C bags. They can hire Truck and Minivans. Each truck can carry 10 bags of Type Abags, 20 bags of Type B bags, and 10 bags ofType C bags. On the other hand, each minivancan carry 20 bags of Type A bags, 5 bags ofType B bags, and 10 bags of Type C bags. Eachtruck's rental cost is $1000, and eachminivan's rental cost is $850. There are only 5truck drivers available to drive the trucks(Hint:It means the number of trucks should be lessthan or equal to 5). If Model Inc wants tominimize the transportation cost, how manytrucks and vans should they rent? (PossibleAnswer: $9100) Data A B C COST TRUCK 10 20 10 $ 1,000.00 MINIVAN 20 5 10 $ 850.00 Model…You work for a small shipping company and warehouse. The owners have decided to update the software used for tracking, shipping, receiving, and inventory. Fifteen computers need to be updated. Hours of operation are 7 a.m. to 7 p.m. Monday through Saturday. Each computer must be updated manually by one of two trained employees, both of whom must be borrowed from other managers. The update procedure consumes 4 hours of the updater's time and generates an additional 1.5 hours of computer downtime. The work must be performed at a central loading station, away from the current location of the computer. How does the project portfolio management approach lead to enhanced strategic management for an organization and give an example how you woulduse this in a work place?
- A final assembly plant for a certain automobile model is to have a capacity of 240,000 units annually. The plant will operate 50 weeks/yr, two shifts/day, 5 days/week, and 8.0 hours/shift. It will be divided into three departments: (1) Body shop, (2) paint shop, (3) trim-chassis-final department. The body shop welds the car bodies using robots, and the paint shop coats the bodies. Both of these departments are highly automated. Trim-chassis-final has no automation. There are 15.5 hours of direct labor content on each car in this department, where cars are moved by a continuous conveyor. Determine: (a) Hourly production rate of the plant, (b) number of workers and workstations required in trim-chassis-final if no automated stations are used, the average manning level is 2.5, balancing efficiency = 93%, proportion uptime = 95%, and a repositioning time of 0.15 min is allowed for each worker.Posh Nails Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses): Activity 1: Welcome a guest. (1 minute)Activity 2: Clip and file nails. (3 minutes)Activity 3: Paint. (5 minutes)Activity 4: Dry. (10 minutes)Activity 5: Check out the customer. (4 minutes)Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and 3. S3 does Activities 4 and 5. The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon. Assume a wage rate of $12 per hour. What are the direct labor costs for one customer (in dollars)?Posh Nails Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses): Activity 1: Welcome a guest. (1 minute)Activity 2: Clip and file nails. (3 minutes)Activity 3: Paint. (5 minutes)Activity 4: Dry. (10 minutes)Activity 5: Check out the customer. (4 minutes)Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and 3. S3 does Activities 4 and 5. The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon. What is the average labor utilization of the servers (in decimal form)? Assume that there is unlimited demand and that the process only admits…
- A furniture factory makes two types of wooden tables,large and small. See the flowchart below .Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart. a. What is the capacity of the system, and what is thebottleneck? b. What are the throughput times for batches of large and small tables? c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?Tyler bakes Cookies (C) and Breads (B) with the help of two ovens in his little bakery. The time taken by Oven A to bake each cookie batch is 14 minutes and the time taken by Oven B is 12 minutes. The time taken by Oven A to bake a batch of bread is 16 minutes and the time taken by Oven B is 17 minutes. Each week both Ovens can be used for 50 hours each to bake Cookies and Breads. The rest of the time is used for baking other products. Moreover, Tyler starts each week with a stock of 25 batches of Cookies and 30 batches of Breads because the Cookies and Breads he produces can be considered to be “fresh” for a maximum of 2 weeks. There is an average weekly demand of 70 batches of Cookies and 50 batches of Breads. For each batch of Cookies, Tyler makes $30 in profit and for each batch of Breads Tyler makes $25 in profit. If there are any “close to losing freshness” goods at the end of the week, Tyler sells them at heavily discounted prices on weekends with a profit of $5 per batch of…Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and a grinder. The times (in minutes) required on each machine are as follows: Machine Component Shaper Grinder 1 6 4 2 4 5 3 4 2 The shaper is available for 120 hours, and the grinder is available for 110 hours. No more than 200 units of component 3 can be sold, but up to 900 units of each of the other components can be sold. In fact, the company already has orders for 600 units of component 1 that must be satisfied. The profit contributions for components 1, 2, and 3 are $8, $6, and $9, respectively. (a) Formulate and solve for the recommended production quantities. component 1 unitscomponent 2 unitscomponent 3 units (b) What are the objective coefficient ranges for the three components? (If there is no upper or lower limit, enter NO LIMIT. Round your answers to the nearest integer.) component 1 to unitscomponent 2 to…