PM.63 Ultimate Idol is an IBC company that is planning to hold a talent/entertainment contest on campus this semester. As a result of their work breakdown efforts they have come up with the following list of activities that are required to pull off their final show. Unfortunately, an unforeseen schedule conflict has emerged with the venue, and this conflict will require Ultimate Idol to hold their final show 6 days earlier than initially planned: Activity Normal Time (days)| Crashed Time (days) Normal Cost Crashed Cost Predecessor(s) A 17 12 $210 $270 В 12 7 $120 $280 12 10 $90 $180 D 10 9 $70 $110 E 8 $150 $720 A, B F 14 10 $220 $290 A G 9 7 $100 $280 E

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
PM.63 Ultimate Idol is an IBC company that is planning to hold a talent/entertainment contest on campus this semester. As a result of their work breakdown
efforts they have come up with the following list of activities that are required to pull off their final show. Unfortunately, an unforeseen schedule conflict has
emerged with the venue, and this conflict will require Ultimate Idol to hold their final show 6 days earlier than initially planned:
Activity
Normal Time (days)
Crashed Time (days)
Normal Cost
Crashed Cost
Predecessor(s)
A
17
12
$210
$270
В
12
7
$120
$280
12
10
$90
$180
D
10
9.
$70
$110
C
E
8
$150
$720
А, В
F
14
10
$220
$290
A
G
9.
7
$100
$280
E
Transcribed Image Text:PM.63 Ultimate Idol is an IBC company that is planning to hold a talent/entertainment contest on campus this semester. As a result of their work breakdown efforts they have come up with the following list of activities that are required to pull off their final show. Unfortunately, an unforeseen schedule conflict has emerged with the venue, and this conflict will require Ultimate Idol to hold their final show 6 days earlier than initially planned: Activity Normal Time (days) Crashed Time (days) Normal Cost Crashed Cost Predecessor(s) A 17 12 $210 $270 В 12 7 $120 $280 12 10 $90 $180 D 10 9. $70 $110 C E 8 $150 $720 А, В F 14 10 $220 $290 A G 9. 7 $100 $280 E
To finish crashing the project by the required 6 days (6 days total off the original project duration), which activity (or activities) should you now crash?
O A
C and G
B and C
B and G
O E
Crash the project by 6 days. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two
decimal places.)
Number
Transcribed Image Text:To finish crashing the project by the required 6 days (6 days total off the original project duration), which activity (or activities) should you now crash? O A C and G B and C B and G O E Crash the project by 6 days. What is the total cost of crashing the project (just the additional cost, not total project cost)? (Display your answer to two decimal places.) Number
If you wanted to shorten the overall duration of the project by 6 days, which activity would you crash first?
O E
A
В
After crashing the activity you answered in the previous question--and crashing it as many days as it can possibly be crashed--which of the following will now
be the critical path (or paths)?
A-E-G
Both A-E-G and B-E-G
A-F
Both C-D and B-E-G
В-Е-G
Transcribed Image Text:If you wanted to shorten the overall duration of the project by 6 days, which activity would you crash first? O E A В After crashing the activity you answered in the previous question--and crashing it as many days as it can possibly be crashed--which of the following will now be the critical path (or paths)? A-E-G Both A-E-G and B-E-G A-F Both C-D and B-E-G В-Е-G
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.